Specification - B316 Chiller Replacement.pdf
PDF 1 MB Posted
- Attached to
- Pre-Qualification: FAA WJHTC Building 316 Chillers Replacement Project Federal contract opportunity
- Solicitation number
- DTFACT-17-R-00012
About this file
Specification - B316 Chiller Replacement (pdf)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment I -B316-Chiller-Replacement-Project Draft SOW.doc | DOC document | |
| Attachment III -B316-Chiller-Replacement-Project-Pre-qualification-Worksheet.docx | DOCX document | |
| Attachment II - Business Declaration.doc | DOC document | |
| B316-F2014074-FULL-SET-11-28-2016-E.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FAA Chiller Replacement Building 316 FCWC5711
PROJECT SPECIFICATIONS
FAA Chiller Replacement Building 316
FEDERAL AVIATION ADMINISTRATION
WILLIAM J. HUGHES TECHNICAL CENTER
ATLANTIC CITY INTERNATIONAL AIRPORT
NEW JERSEY
17 November 2016
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
1 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
2 41 00 DEMOLITION
DIVISION 03 - CONCRETE
3 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 05 23 WELDING, STRUCTURAL
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
6 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
7 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
8 11 13 STEEL DOORS AND FRAMES
08 71 00 DOOR HARDWARE
8 91 00 LOUVERS
DIVISION 09 - FINISHES
9 90 00 PAINTS AND COATINGS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY
PROJECT TABLE OF CONTENTS Page 2
26 08 00 APPARATUS INSPECTION AND TESTING
26 11 16 SECONDARY UNIT SUBSTATIONS
26 28 00.00 10 MOTOR CONTROL CENTERS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
DIVISION 40 - PROCESS INTEGRATION
40 95 00 PROCESS CONTROL
-- End of Project Table of Contents --
Section 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
07/10
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal
Contract Clause 3.2.2.3-45, "Material and Workmanship" and 3.2.2.3-60, "Specifications, Drawings and Material Offers", apply to all submittals.
1.1.2 Submittal Descriptions (SD)
Submittals requirements are specified in The Schedule, Part I, of the contract. Submittals are identified by SD numbers and titles as follows.
SD-01 Preconstruction Submittals
Submittals which are required prior to a notice to proceed on a new contract.
Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work, submitted prior to contract notice to proceed or next major phase of construction. Examples include:
Certificates of insurance
Surety bonds
Construction Schedule
Submittal register
Schedule of prices
Health and safety plan
Waste Management Plan
Demolition Plan
(Note that not all of these submittals are listed on the submittal register provided by the government. See the Schedule, Part I, Section H for other Preconstruction Submittals required for the contract.)
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Section 01 33 00 Page 2
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Section 01 33 00 Page 3
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data Sheets concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings, manufacturer's help and product lines necessary to maintain and install equipment. Also, submittal
Section 01 33 00 Page 4 requirements necessary to properly close out a major phase of construction on a multi-phase contract.
(Note that not all of these submittals are listed on the submittal register provided by the government. See the Schedule, Part I, Section H for a complete listing of Closeout Submittals required for the contract.)
1.1.3 Approving Authority
Office or designated person authorized to approve submittal.
1.1.4 Work
As used in this section, on-and off-site construction required by contract documents, including labor necessary to produce construction submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
Submittal Register; G
1.3 USE OF SUBMITTAL REGISTER
Submittal register will be delivered to the Contractor by the Contracting Officer. Register will have the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g.
SD-04 Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submittal requirements. Do not consider entries in column (e) as limiting project requirements.
Column (f): Indicate approving authority for each submittal. A "G" indicates approval by Contracting Officer.
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved.
1.3.1 Submittal Register
Section 01 33 00 Page 5
Submit submittal register. Submit within 10 calendar days after contract award and before the issuance of a notice to proceed with the work. Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered for Contractor approval.
1.3.2 Contractor Use of Submittal Register
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code.
Column (k) Date of action used to record Contractor's review when forwarding submittals.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.3.3 Approving Authority Use of Submittal Register
Update the following fields.
Column (l) List date of submittal receipt.
Column (m) through (p).
Column (q) List date returned to Contractor.
1.3.4 Contractor Action Code and Action Code Entries
Entries used shall be as follows (others may be prescribed by Transmittal Form):
NR -Not Received
AN -Approved as noted
A -Approved
RR -Disapproved, Revise, and Resubmit
1.3.5 Copies Delivered to the Government
Section 01 33 00 Page 6
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.4 PROCEDURES FOR SUBMITTALS
1.4.1 Reviewing, Certifying, Approving Authority
The contractor shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the Contracting Officer unless otherwise specified for specific submittal. At each "Submittal" paragraph in individual specification sections, a notation "G," following a submittal item, indicates Contracting Officer is approving authority for that submittal item.
1.4.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.4.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 15 working days for submittals for Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives submittal from the contractor. Period of review for each resubmittal is the same as for initial submittal.
1.4.4 Variations
Variations from contract requirements require Government approval pursuant to Contract Clause 3.2.2.3-60, "Specifications, Drawings and Material Offers", and will be considered where advantageous to the Government.
1.4.4.1 Considering Variations
Discussion with Contracting Officer prior to submission, will help ensure functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal
(VECP).
Section 01 33 00 Page 7
1.4.4.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.4.4.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.4.4.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.4.5 Contractor's Responsibilities
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to the government in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to Government, or delays to separate Contractors.
c. Advise Contracting Officer of variation, as required by paragraph titled "Variations."
d. Correct and resubmit submittal as directed by approving authority. When resubmitting disapproved transmittals or transmittals noted for resubmittal, the Contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
e. Furnish additional copies of submittal when requested by Contracting
Officer, to a limit of 20 copies per submittal.
f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.
g. Ensure no work has begun until submittals for that work have been returned as "approved," or "approved as noted", except to the extent that a portion of work must be accomplished as basis of submittal.
1.4.6 Government's Responsibilities
When approving authority is Contracting Officer, the Government will:
Section 01 33 00 Page 8
a. Note date on which submittal was received from the contractor, on each submittal for which the Contracting Officer is approving authority.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.
1.4.7 Actions Possible
Submittals will be returned with one of the following notations:
a. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required , does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
b. Submittals marked "approved" or "approved as submitted" authorize
Contractor to proceed with work covered.
c. Submittals marked "approved as noted" or "approval except as noted;
resubmission not required" authorize Contractor to proceed with work as noted provided Contractor takes no exception to the notations.
d. Submittals marked "revise and resubmit" or "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until resubmittal is approved.
1.5 FORMAT OF SUBMITTALS
1.5.1 Transmittal Form
Transmit each submittal, except sample installations and sample panels, to office of approving authority. Transmit submittals with transmittal form prescribed by Contracting Officer and standard for project. The transmittal form shall identify Contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph titled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations.
1.5.2 Identifying Submittals
Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location.
Section 01 33 00 Page 9
b. Construction contract number.
c. Section number of the specification section by which submittal is required.
d. Submittal description (SD) number of each component of submittal.
e. When a resubmission, add alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.
f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier Contractor associated with submittal.
g. Product identification and location in project.
1.5.3 Format for SD-02 Shop Drawings
a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.
b. Present 8 1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section. Present larger drawings in sets.
c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."
d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.
e. Drawings shall include the nameplate data, size and capacity. Also include applicable federal, military, industry and technical society publication references.
1.5.4 Format of SD-03 Product Data and SD-08 Manufacturer's Instruction
a. Present product data submittals for each section as a complete, bound volume. Include table of contents, listing page and catalog item numbers for product data.
b. Indicate, by prominent notation, each product which is being submitted;
indicate specification section number and paragraph number to which it pertains.
c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project, with information and format as required for submission of SD-07 Certificates.
d. Provide product data in English dimensions.
e. Product data shall include the manufacturer's name, trade name, place of manufacture, and catalog model or number. Submittals shall also
Section 01 33 00 Page 10 include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, the supplemental information shall be submitted as specified for SD-07 Certificates.
f. Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. The certificate shall state that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
g. Submit manufacturer's instruction prior to installation.
1.5.5 Format of SD-04 Samples
a. Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:
(1) Sample of Equipment or Device: Full size.
(2) Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by
11 inches.
(3) Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
(4) Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
(5) Sample of Non-Solid Materials: Pint. Examples of non-solid materials are sand and paint.
(6) Color Selection Samples: 2 by 4 inches.
(7) Sample Panel: 4 by 4 feet.
(8) Sample Installation: 100 square feet.
b. Samples Showing Range of Variation: Where variations are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range.
c. Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples shall be in undamaged condition at time of use.
Section 01 33 00 Page 11
d. Recording of Sample Installation: Note and preserve the notation of area constituting sample installation but remove notation at final clean up of project.
e. When color, texture or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.5.6 Format of SD-05 Design Data and SD-07 Certificates
a. Provide design data and certificates on 8 1/2 by 11 inches paper.
Provide a bound volume for submittals containing numerous pages.
1.5.7 Format of SD-06 Test Reports and SD-09 Manufacturer's Field Reports
a. Provide reports on 8 1/2 by 11 inches paper in a complete bound volume.
b. Indicate by prominent notation, each report in the submittal. Indicate specification number and paragraph number to which it pertains.
1.5.8 Format of SD-10 Operation and Maintenance Data (O&M)
a. O&M Data format shall comply with the requirements per the schedule, Part I.
1.5.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
a. When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply Contractor's approval stamp to document, but to a separate sheet accompanying document.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of SD-02 Shop Drawings
a. Submit six copies of submittals of shop drawings requiring review and approval by Contracting Officer.
1.6.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
a. Submit in compliance with quantity requirements specified for shop drawings.
1.6.3 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel. Include components listed in technical section or as directed.
c. Submit sample installations, where directed.
Section 01 33 00 Page 12
d. Submit one sample of non-solid materials.
1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates
a. Submit in compliance with quantity requirements specified for shop drawings.
1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
a. Submit in compliance with quantity with quality requirements specified for shop drawings.
1.6.6 Number of Copies of SD-10 Operation and Maintenance Data
a. Submit three copies of O&M Data to the Contracting Officer for review and approval.
1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
a. Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for shop drawings.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
-- End of Section --
Section 01 42 00 Page 1
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
08/10
1.1 REFERENCES
Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
38800 Country Club Drive Farmington Hills, MI 48331 Ph: 248-848-3700 Fax: 248-848-3701 E-mail: bkstore@concrete.org Internet: http://www.concrete.org
AIR MOVEMENT AND CONTROL ASSOCIATION INTERNATIONAL (AMCA)
30 West University Drive Arlington Heights, IL 60004-1893 Ph: 847-394-0150 Fax: 847-253-0088 E-mail: amca@amca.org Internet: http://www.amca.org
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
2111 Wilson Blvd, Suite 500 Arlington, VA 22201 Ph: 703-524-8800 Fax: 703-528-3816 E-mail: fdietz@ahrinet.org Internet: http://www.ahrinet.org
ALUMINUM ASSOCIATION (AA)
National Headquarters 1525 Wilson Boulevard, Suite 600 http://www.concrete.org/ http://www.amca.org/ http://www.ahrinet.org/
Section 01 42 00 Page 2
Arlington, VA 22209 Ph: 703-358-2960 Fax: 703-358-2961 Internet: http://www.aluminum.org
AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)
1827 Walden Office Square Suite 550 Schaumburg, IL 60173-5774 Ph: 847-303-5664 Fax: 847-303-5774 E-mail: webmaster@aamanet.org Internet: http://www.aamanet.org
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
444 North Capital Street, NW, Suite 249 Washington, DC 20001 Ph: 202-624-5800 Fax: 202-624-5806 E-Mail: info@aashto.org Internet: http://www.aashto.org
AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)
2025 M Street, NW, Suite 800 Washington, DC 20036 Ph: 202-367-1155 Fax: 202-367-2155 E-mail: info@americanbearings.org Internet: http://www.abma-dc.org
AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)
1330 Kemper Meadow Drive Cincinnati, OH 45240 Ph: 513-742-2020 or 513-742-6163 Fax: 513-742-3355 E-mail: mail@acgih.org Internet: http://www.acgih.org
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
One East Wacker Drive, Suite 700 Chicago, IL 60601-1802 Ph: 312-670-2400 Fax: 312-670-5403 Publications: 800-644-2400 E-mail: pubs@aisc.org Internet: http://www.aisc.org
AMERICAN LUMBER STANDARDS COMMITTEE (ALSC)
P.O. Box 210 Germantown, MD 20875-0210 Ph: 301-972-1700 Fax: 301-540-8004 E-mail: alsc@alsc.org Internet: http://www.alsc.org
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
http://www.aluminum.org/ http://www.aamanet.org/ http://www.aashto.org/ http://www.abma-dc.org/ http://www.acgih.org/ http://www.aisc.org/ http://www.alsc.org/
Section 01 42 00 Page 3
1819 L Street, NW,11th Floor Washington, DC 20036 Ph: 202-293-8020 Fax: 202-293-9287 E-mail: info@ansi.org Internet: http://www.ansi.org/
AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)
1711 Arlingate Lane P.O. Box 28518 Columbus, OH 43228-0518 Ph: 800-222-2768; 614-274-6003 Fax: 614-274-6899 E-mail: webmaster@asnt.org Internet: http://www.asnt.org
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
1791 Tullie Circle, NE Atlanta, GA 30329 Ph: 800-527-4723 or 404-636-8400 Fax: 404-321-5478 E-mail: ashrae@ashrae.org Internet: http://www.ashrae.org
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
1800 East Oakton Street Des Plaines, IL 60018-2187 Ph: 847-699-2929 Fax: 847-768-3434 E-mail: customerservice@asse.org Internet: http://www.asse.org
AMERICAN WATER WORKS ASSOCIATION (AWWA)
6666 West Quincy Avenue Denver, CO 80235 Ph: 800-926-7337 Fax: 303-347-0804 E-mail: smorrison@awwa.org Internet: http://www.awwa.org
AMERICAN WELDING SOCIETY (AWS)
8669 NW 36 Street, #130550 N.W. LeJeune Road Miami, FL 33166-6672 Ph: 800-443-9353 - 305-443-9353 Fax: 305-443-7559 E-mail: info@aws.org or customerservice@awspubs.com Internet: http://www.aws.org
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
P.O. Box 361784 Birmingham, AL 35236-1784 Ph: 205-733-4077 Fax: 205-733-4075 E-mail: email@awpa.com Internet: http://www.awpa.com http://www.ansi.org/ http://www.asnt.org/ http://www.ashrae.org/ http://www.asse.org/ http://www.awwa.org/ http://www.aws.org/ http://www.awpa.com/
Section 01 42 00 Page 4
ASME INTERNATIONAL (ASME)
Three Park Avenue, M/S 10E New York, NY 10016-5990 Ph: 800-854-7179 or 800-843-2763 Fax: 212-591-7674 E-mail: infocentral@asme.org Internet: http://www.asme.org
ASSOCIATED AIR BALANCE COUNCIL (AABC)
1518 K Street, NW Washington, DC 20005 Ph: 202-737-0202 Fax: 202-638-4833 E-mail: info@aabc.com Internet: http://www.aabchq.com
ASSOCIATION OF EDISON ILLUMINATING COMPANIES (AEIC)
600 North 18th Street P.O. Box 2641 Birmingham, AL 35291 Ph: 205-257-2530 Fax: 205-257-2540 E-Mail: aeicdir@bellsouth.net Internet: http://www.aeic.org
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 610-832-9585 Fax: 610-832-9555 E-mail: service@astm.org Internet: http://www.astm.org
BUILDERS HARDWARE MANUFACTURERS ASSOCIATION (BHMA)
355 Lexington Avenue 15th Floor New York, NY 10017 Ph: 212-297-2122 Fax: 212-370-9047 E-mail: assocmgmt@aol.com Internet: http://www.buildershardware.com
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
933 North Plum Grove Road Schaumburg, IL 60173-4758 Ph: 847-517-1200 or 800-328-6306 Fax: 847-517-1206 Internet: http://www.crsi.org/
FM GLOBAL (FM)
270 Central Avenue P.O. Box 7500 Johnston, RI 02919 Ph: 401-275-3000 ext. 1945 Fax: 401-275-3029 E-mail: servicedesk.myrisk@fmglobal.com http://www.asme.org/ http://www.aabchq.com/ http://www.aeic.org/ http://www.astm.org/ http://www.buildershardware.com/ http://www.crsi.org/
Section 01 42 00 Page 5
Internet: http://www.fmglobal.com
FOREST STEWARDSHIP COUNCIL (FSC)
212 Third Avenue North Suite 280 Minneapolis, MN 55401 Ph: 612-353-4511 Fax: 612-208-1565 E-mail: info@fscus.org Internet: http://www.fscus.org
HYDRAULIC INSTITUTE (HI)
6 Campus Drive, First Floor North Parsippany, NJ 07054-4406 Ph: 973-267-9700 Fax: 973-267-9055 E-mail: webmaster@pumps.org Internet: http://www.pumps.org
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
445 Hoes Lane or 2001 L Street, NW. Suite 700 Piscataway, NJ 08855-1331 or Washington, DC 20036-4910 USA Ph: 732-981-0060 or 800-701-4333 Fax: 732-562-6380 E-mail: onlinesupport@ieee.org or ieeeusa@ieee.org Internet: http://www.ieee.org
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
3050 Old Centre Ave. Suite 102 Portage, MI 49024 Ph: 269-488-6382 Fax: 269-488-6383 E-mail: neta@netaworld.org Internet: http://www.netaworld.org
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
127 Park Street, NE Vienna, VA 22180 Ph: 703-281-6613 Fax: 703-281-6671 E-mail: info@mss-hq.com Internet: http://www.mss-hq.com
MASTER PAINTERS INSTITUTE (MPI)
2800 Engleton Avenue Burnaby, BC CANADA V5C 6G7 Ph: 1-888-674-8937 Fax: 1-888-211-8708 E-mail: info@paintinfo.com,jody@mpi.net,bgl@mpi.net Internet: http://www.paintinfo.com/mpi
MIDWEST INSULATION CONTRACTORS ASSOCIATION (MICA)
16712 Elm Circle Omaha, NE 68130 Ph: 800-747-6422 Fax: 402-330-9702 http://www.fmglobal.com/ http://www.fscus.org/ http://www.pumps.org/ http://www.ieee.org/ http://www.netaworld.org/ http://www.mss-hq.com/ http://www.paintinfo.com/mpi
Section 01 42 00 Page 6
E-mail: mica@tconl.com Internet: http://www.micainsulation.org
NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS (NAAMM)
800 Roosevelt Road, Bldg C, Suite 312 Glen Ellyn, IL 60137 Ph: 630-942-6591 Fax: 630-790-3095 E-mail: wlewis7@cox.net(Vernon Lewis,technical consultant) Internet: http://www.naamm.org
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
1300 North 17th Street, Suite 1752 Rosslyn, VA 22209 Ph: 703-841-3200 Fax: 703-841-5900 Internet: http://www.nema.org/
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
8575 Grovemont Circle Gaithersburg, MD 20877 Ph: 301-977-3698 Fax: 301-977-9589 E-Mail: elana@nebb.org Internet: http://www.nebb.org
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
1 Batterymarch Park Quincy, MA 02169-7471 Ph: 617-770-3000 or 800-344-3555 Fax: 617-770-0700 E-mail: webmaster@nfpa.org Internet: http://www.nfpa.org
NATIONAL HARDWOOD LUMBER ASSOCIATION (NHLA)
6830 Raleigh LaGrange Road Memphis, TN 38184-0518 Ph: 901-377-1818 E-mail: info@nhla.com Internet: http://www.natlhardwood.org
NORTHEASTERN LUMBER MANUFACTURERS ASSOCIATION (NELMA)
272 Tuttle Road Cumberland, ME 04021 Ph: 207-829-6901 Fax: 207-829-4293 E-mail: barbara@nelma.org Internet: http://www.nelma.org
ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT (OECD)
2, rue Andre Pascal F-75775 Paris Cedex 16, France Ph: + 33 1 45 24 82 00 Fax: 33 1 45 24 85 00 E-mail: bookshop@oecd.org Internet: http://www.oecd.org U.S. Contact Center http://www.micainsulation.org/ http://www.naamm.org/ http://www.nema.org/ http://www.nebb.org/ http://www.nfpa.org/ http://www.natlhardwood.org/ http://www.nelma.org/ http://www.oecd.org/
Section 01 42 00 Page 7
OECD Washington Center 2001 L Street, NW, Suite 650 Washington, DC 20036-4922 Ph: 202-785-6323 Fax: 202-785-0350 E-mail: washington.contact@oecd.org
REDWOOD INSPECTION SERVICE (RIS) OF THE CALIFORNIA REDWOOD
ASSOCIATION (CRA)
405 Enfrente Drive, Suite 200 Novato, CA 94949 Ph: 415-382-0662 or 888-CALREDWOOD Fax: 415-382-8531 E-Mail: info@calredwood.org Internet: http://www.redwoodinspection.com/
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
4201 Lafayette Center Drive Chantilly, VA 20151-1219 Ph: 703-803-2980 Fax: 703-803-3732 E-mail: info@smacna.org Internet: http://www.smacna.org
SOUTHERN CYPRESS MANUFACTURERS ASSOCIATION (SCMA)
400 Penn Center Boulevard, Suite 530 Pittsburgh, PA 15235-5605 Ph: 412-829-0770 Fax: 412-829-0844 Internet: http://www.cypressinfo.org
SOUTHERN PINE INSPECTION BUREAU (SPIB)
P.O. Box 10915 Pensacola, FL 32504-0915 Ph: 850-434-2611 Fax: 850-433-5594 E-mail: Fill out form at http://www.spib.org/contact.shtml Internet: http://www.spib.org
STEEL DOOR INSTITUTE (SDI/DOOR)
30200 Detroit Road Westlake, OH 44145 Ph: 440-899-0010 Fax: 440-892-1404 E-mail: info@steeldoor.org Internet: http://www.steeldoor.org
TECHNICAL ASSOCIATION OF THE PULP AND PAPER INDUSTRY (TAPPI)
15 Technology Parkway South, Suite 115 Peachtree Corners, GA 30092 Ph: 800-322-8686 or 770-446-1400 Fax: 770-446-6947 E-mail: memberconnection@tappi.org Internet: http://www.tappi.org http://www.redwoodinspection.com/ http://www.smacna.org/ http://www.cypressinfo.org/ http://www.spib.org/ http://www.steeldoor.org/ http://www.tappi.org/
Section 01 42 00 Page 8
THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)
40 24th Street, 6th Floor Pittsburgh, PA 15222-4656 Ph: 412-281-2331 Fax: 412-281-9992 E-mail: info@sspc.org Internet: http://www.sspc.org
UNDERWRITERS LABORATORIES (UL)
2600 N.W. Lake Road Camas, WA 98607-8542 Ph: 877-854-3577 Fax: 360-817-6278 E-mail: CEC.us@us.ul.com Internet: http://www.ul.com/ UL Directories available through IHS at http://www.ihs.com
U.S. ARMY CORPS OF ENGINEERS (USACE)
Order CRD-C DOCUMENTS from:
U.S. Army Engineer Waterways Experiment Station ATTN: Technical Report Distribution Section, Services Branch, TIC 3909 Halls Ferry Road Vicksburg, MS 39180-6199 E-mail: MTC-INFO@erdc.usace.army.mil Internet: http://gsl.erdc.usace.army.mil/SL/MTC/handbook/handbook.htm Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.usace.army.mil/publications or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
U.S. DEPARTMENT OF DEFENSE (DOD)
Order DOD Documents from:
Room 3A750-The Pentagon 1400 Defense Pentagon Washington, DC 20301-1400 Ph: 703-571-3343
FAX: 215-697-1462
E-mail: pia@hq.afis.asd.mil Internet: http://www.dod.gov Obtain Military Specifications, Standards and Related Publications from:
Acquisition Streamlining and Standardization Information System
(ASSIST)
Department of Defense Single Stock Point (DODSSP) Document Automation and Production Service (DAPS) Building 4/D 700 Robbins Avenue Philadelphia, PA 19111-5094 http://www.sspc.org/ http://www.ul.com/ http://www.ihs.com/ http://gsl.erdc.usace.army.mil/SL/MTC/handbook/handbook.htm http://www.usace.army.mil/publications http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx http://www.ntis.gov/
Section 01 42 00 Page 9
Ph: 215-697-6396 - for account/password issues Internet: http://assist.daps.dla.mil/online/start/; account registration required Obtain Unified Facilities Criteria (UFC) from:
Whole Building Design Guide (WBDG) National Institute of Building Sciences (NIBS) 1090 Vermont Avenue NW, Suite 700 Washington, CD 20005 Ph: 202-289-7800 Fax: 202-289-1092 Internet: http://www.wbdg.org/references/docs_refs.php
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Ariel Rios Building 1200 Pennsylvania Avenue, N.W.
Washington, DC 20004 Ph: 202-272-0167 for Fax and E-mail see below Internet: http://www.epa.gov --- Some EPA documents are available only from:
National Technical Information Service (NTIS) 5301 Shawnee Road Alexandria, VA 22312 Ph: 703-605-6050 or 1-688-584-8332 Fax: 703-605-6900 E-mail: info@ntis.gov Internet: http://www.ntis.gov
U. S. GREEN BUILDING COUNCIL (USGBC)
2101 L St NW, Suite 500 Washington, D.C. 20037 Fax: 202-828-5110 E-mail: info@usgbc.org Internet: http://www.usgbc.org
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
General Services Administration 1800 F Street, NW Washington, DC 20405 Ph: 202-501-0800 Internet: www.GSA.gov Obtain documents from:
Acquisition Streamlining and Standardization Information System
(ASSIST)
Department of Defense Single Stock Point (DODSSP) Document Automation and Production Service (DAPS) Building 4/D 700 Robbins Avenue Philadelphia, PA 19111-5094 Ph: 215-697-6396 - for account/password issues Internet: http://assist.daps.dla.mil/online/start/; account registration required
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
8601 Adelphi Road College Park, MD 20740-6001 Ph: 866-272-6272 http://assist.daps.dla.mil/online/start http://www.wbdg.org/references/docs_refs.php http://www.epa.gov/ http://www.ntis.gov/ http://www.usgbc.org/ http://www.gsa.gov/ http://assist.daps.dla.mil/online/start
Section 01 42 00 Page 10
Fax: 301-837-0483 E-mail: contactcenter@gpo.gov Internet: http://www.archives.gov Order documents from:
Superintendent of Documents U.S.Government Printing Office (GPO) 732 North Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: http://www.gpoaccess.gov
WEST COAST LUMBER INSPECTION BUREAU (WCLIB)
P.O. Box 23145 Tigard, OR 97281 Ph: 503-639-0651 Fax: 503-684-8928 E-mail: info@wclib.org Internet: http://www.wclib.org
WESTERN WOOD PRODUCTS ASSOCIATION (WWPA)
Yeon Building 522 SW 5th Avenue Suite 500 Portland, OR 97204-2122 Ph: 503-224-3930 Fax: 503-224-3934 E-mail: info@wwpa.org Internet: http://www.wwpa.org
Not used
Not used http://www.archives.gov/ http://www.gpoaccess.gov/ http://www.wclib.org/ http://www.wwpa.org/
Section 01 57 19 Page 1
SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS
07/10
1.1 SUMMARY
This section covers the furnishing of all labor, material, and equipment and performing all work required for the protection of the environment during construction operations except for those measures set forth in other sections of these specifications.
1.2 APPLICABLE PUBLICATIONS
The publications listed below are integral to this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. Department of Labor, Occupational Safety and Health Administration
(OSHA) Regulations, including but not limited to:
29 CFR 1910.12 Subpart B - Adoption and Extension of Established Federal Standards, Construction Work
29 CFR 1910.94 Subpart G - Occupational Health and Environmental Control, Ventilation
29 CFR 1910.95 Subpart G - Occupational Health and Environmental Control, Occupational Noise Exposure
29 CFR 1910.106 Subpart H - Hazardous Materials, Flammable and Combustible Liquids
29 CFR 1910.109 Subpart H - Hazardous Material, Explosives and Blasting Agents
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1910.147 Subpart J - General Environmental Controls - The Control of Hazardous Energy (Lockout/Tagout)
29 CFR 1910.120 Hazardous Waste Operations and Emergency Response
29 CFR 1910.134 Subpart I - Personal Protective Equipment, Respiratory Protection
29 CFR 1910.178 Subpart N - Materials Handling and Storage, Powered Industrial Truck
Section 01 57 19 Page 2
29 CFR 1910.1000 Subpart Z- Toxic and Hazardous Substances, Air Contaminants
29 CFR 1910.1200 Subpart Z - Toxic and Hazardous Substances Hazard Communication
29 CFR 1926.21 Subpart C - Safety Training and Education
29 CFR 1926.350 Subpart J - Welding and Cutting
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA) Regulations
40 CFR 51 Federal Conformity Determination for Federal Actions
40 CFR 173 Shippers - General Requirements for Shipments and Packaging
40 CFR 761 Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 263 Standards Applicable to Transporters of Hazardous Waste
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 300 National Contingency Plan
49 CFR 178 Specifications for Packaging
New Jersey Administrative Code (NJAC)
NJAC 2:90 State Soil Conservation Committee
NJAC 7:1E Discharges of Petroleum and Other Hazardous Substances
NJAC 7:9 Water Pollution Control
NJAC 7:10 Safe Drinking Water Act
NJAC 7:14A The New Jersey Pollutant Discharge Elimination System
NJAC 7:14B Underground Storage Tanks
NJAC 7:18 Regulations Governing the Certification of Laboratories and Environmental Measurements
Section 01 57 19 Page 3
NJAC 7:19 Water Supply Allocation Permits
NJAC 7:26 Solid Waste
NJAC 7:26G Hazardous Waste
NJAC 7:27 Bureau of Air Pollution Control Regulations
NJAC 7:30 Pesticide Control Code
NJAC 7:50 Pinelands Comprehensive Management Plan
Federal Aviation Regulations (FAR)
FAR Part 77 Obstructions
FAR Part 139 Wildlife Hazards/Attractants
Federal Aviation Administration (FAA) Orders
1050.1D Policies and Procedures for Considering Environmental Impacts
1050.10B Prevention, Control, and Abatement of Environmental Pollution at FAA Facilities
1050.12 Application of Nonrestricted and
Restricted-Use Pesticide
1050.14 Polychlorinated Biphenyls (PCBs) at FAA
Facilities
1050.15 Underground Storage Tanks (UST) at FAA
Facilities
1050.17 Airway Facilities Environmental and Safety
Compliance Program
3900.13B Personal Protective Equipment and Clothing
3900.24A Accident and Fire Reporting
3900.25 Respiratory Protection Program
4443.1 Building Permit
Federal Aviation Administration
William J. Hughes Technical Center (Center) Orders
1050.2 Recycling
3900.55 Occupational Safety and Health
Army Corps of Engineers (COE)
COE EM-385-1-1 (1996) Corps of Engineers Safety and Health Requirements Manual
Section 01 57 19 Page 4
1.3 DEFINITIONS
1.3.1 Chemical Wastes
This includes salts, acids, alkali's, herbicides, pesticides, and organic chemicals.
1.3.2 Debris
Combustible and noncombustible wastes such as ashes and waste materials resulting from construction or maintenance and repair work, leaves, and tree trimmings.
1.3.3 Discharge
Any intentional or unintentional action or omission resulting in the releasing, spilling, leaking, pumping, pouring, emitting, emptying or dumping of hazardous substance into surface or ground waters or onto lands from which it might flow or drain into said waters or into the air.
1.3.4 Drip Line
The outer most horizontal perimeter of the foliage or limbs of trees and shrubs.
1.3.5 Hazardous Substance
Such elements and compounds, including petroleum, petroleum products, pesticides, solvents and other substances as set forth in NJAC 7:1E.
1.3.6 Hazardous Waste
Hazardous substances as defined in 40 CFR 261 or as defined by applicable state and local regulations.
1.3.7 Oily Waste
Petroleum products and bituminous materials.
1.3.8 Pollutant
Any dredged spoil, solid waste, sewage, garbage, refuse, oil, grease, sewage sludge, munitions, chemical wastes, biological materials, thermal waste, wrecked or discarded equipment, rock, sand, construction waste or runoff or other residue discharged to the land, ground waters or surface waters.
1.3.9 Rubbish
Combustible and noncombustible wastes such as paper, boxes, glass, crockery, metal, lumber, cans, and bones.
1.3.10 Sanitary Wastes
1.3.10.1 Sewage
Wastes characterized as domestic sanitary sewage.
Section 01 57 19 Page 5
1.3.10.2 Garbage
Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.
1.3.11 Sediment
Soil and other debris that have eroded and have been transported by runoff water or wind.
1.3.12 Solid Waste
Rubbish, debris, garbage, and other discarded solid materials, except hazardous waste as defined in paragraph entitled "Hazardous Waste," resulting from industrial, commercial, and agricultural operations and from community activities.
1.3.13 Volatile Organic Substance (VOS)
Any organic substances, mixture of organic and inorganic substances including, but not limited to , petroleum crudes, petroleum fractions, petrochemicals, solvents, diluents, and thinners which have vapor pressures or sums of partial pressures of substances of 0.02 pounds per square inch (one millimeter of mercury) absolute or greater measured at standard conditions of atmospheric pressure and a temperature of 60 degrees Fahrenheit; in the case of surface coating formulations, includes coalescing or other agent, regardless of vapor pressure, which evaporates from the coating during the drying phase; but does not include methane, CFC-11, CFC- 12, CFC-22, FC-23, CFC-113, CFC-114 and CFC-115.
1.3.14 Wetlands
Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, bogs and similar areas. National Wetland Inventory Maps, promulgated by the U.S. Fish and Wildlife Service, shall be used to identify wetlands to be protected. Maps are available from the Fish and Wildlife Service and the New Jersey Department of Environmental Protection.
1.4 SUBMITTALS
The following shall be submitted in accordance with Section 013300, "Submittal Procedures."
Government approval is required for submittals with a "G" designation.
Site Safety and Health Plan (SSHP); G
The Contractor shall submit four copies of a SSHP to the Contracting Officer within ten (10) days after the contract award.
SD-03 Product Data
Section 01 57 19 Page 6
a. Generators; G
b. Petroleum, Gasoline and Volatile Substance Storage Tanks; G
c. Surface Coating Equipment
SD-06 Test Reports
Monthly Recycling Report; G
SD-08 Manufacturer's Instructions
Material Safety Data Sheets (MSDS); G Submit (3) copies of all MSDS for each material to be used in accordance with 29 CFR 1910.1200, Subpart Z.
1.5 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain, all environmental protection measures established, during the life of the contract. Plan for and provide environmental protective measures to control pollution that develops during normal construction practice.