Draft SOW - Chiller Compressor Replacement.pdf

PDF 545 KB Posted

Attached to
Chiller Compressor Replacements (Albany, CA) Federal contract opportunity
Solicitation number
12905B23Q0121
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Pacific West Area

About this file

This document is a Statement of Work (SOW) for replacing two failed compressors on an existing chiller unit located at a USDA facility in Albany, California. The contractor will be required to remove and dispose of the failed compressors, replace them with compressors that are identical or compatible with the existing unit, test all four compressors, and ensure the chiller is fully functional. The contractor must have at least five years of relevant experience and be able to complete the work within 60 days while coordinating all utility shutdowns with the Contracting Officer's Representative and not interfering with facility operations. The SOW provides requirements for safety, security, waste disposal, warranties, compliance with laws and regulations, and outlines the location, schedule, and point of contact for the work.

The related federal contract opportunity is a pre-solicitation notice for chiller compressor replacements at the same Albany facility. Interested vendors will be able to submit proposals in response to solicitation number 12905B23Q0121 once it is published by the USDA Agricultural Research Service Pacific West Area. The opportunity involves replacing failed compressors to restore functionality of an existing chiller unit.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chiller Compressor Replacement – SOW

General:

Currently, one of the Chillers at USDA Facility in Albany, CA is nonfunctional. This chiller provides cold temperature to several labs in South Wing of the Main Bldg. operated by Food Safety Inspection Service (FSIS). Some of the labs currently affected due to the failure of the chiller are (Rooms 0200, 0206, 0208, 0201, 0207, 2203). This is one of the several chillers at the facility and is located in the South Wing of the Main Bldg. at 4th Floor (Attic) (Attached Location). The non functionality is caused by the complete failure of two of four compressors supporting the Chiller.

The existing chiller is from Multistack, Model; No.: MS050XC2A2W2AACR410A, (See Figure 4). The new compressor must be either of the same kind or compatible to the existing Chiller. Refer to Figure 2 for the detailed existing chiller and the compressor.

Service Required:

The contractor is to determine which two of the four compressors have failed.

The contractor is to remove and dispose the failed compressors in accordance with local, state, and federal law and regulations.

Contractor shall replace the failed two compressors in kind or compatible with the existing chiller.

The contractor shall test all four compressors – the newly installed two compressors as well as the remaining two compressors.

If the remaining two compressors indicate any issues or malfunction the contractor shall contact the COR immediately for further action.

Contractor is to provide and install all accessories as required as part of the compressor replacement.

The contractor is required to complete the project in a way it is fully functional as intended.

Contractor is responsible for any damage to adjacent equipment, fixtures, and miscellaneous objects that may become damaged during installation. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.

Contractor is responsible to disconnect, dispose all hazardous and non-hazardous waste materials generated in accordance with current Federal, State, and local guidelines. Restore areas disturbed as nearly as possible to the original appearance and condition.

Upon completion of the project, and prior to testing, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

Location of The Project:

USDA

800 Buchanan Street Albany, CA 94710

Qualification

The contractor shall have at least 5 years of experience as part of their qualification. Contractor staffs shall possess the general knowledge, skills and be fully experienced in all aspects of works required to complete this project successfully.

Coordination:

Throughout the work activities, the contractor will maintain close liaison with the COR. If there is any unexpected risk identified during the contract, the Contractor shall coordinate with the COR immediately.

Storage Of Equipment & Materials:

The contractor shall arrange with the COR for allocation of required workspace and for the storage of equipment and material to be used for this project.

Safety:

The contractor shall enforce safety rules and regulations on installation sites - accident report forms, medical surveillance program, fall protection, electric work, hazardous materials, personnel protection equipment, ladders, and heavy equipment; provide an effective response to changing work conditions and activities. The contractor shall advise the Government of any accidents occurring on job site.

Site Utilities:

The contractor shall note any obstruction, utility, or condition that may hinder or interfere with the execution of this contract and the contractor shall make provisions in their contract price to resolve such interferences and other conditions that may hinder the proper completion of the work. All proposed utility relocations, reallocations, and shutdowns shall be approved by the COR prior to commencing such work. The contractor shall verify all existing utility installations and take appropriate action prior to working around any potential utility installation.

In the event of a shutdown, restriction, or interruption of any utility services is required, a written request must be submitted (at least 2 weeks in advance) and approved by the COR. All utility shutdowns must be subject review and approval by the COR.

Security, Identification, Check-in, Parking, and Smoking Regulations:

All contractor personnel shall obtain a short-term identification issued by the USDA. Such badge shall be used by the individual and prominently displayed at all times while on the facility. No employee of the contractor shall enter the project site without a valid identification badge issued by the USDA. In order to obtain a short-term identification badge, contractor personnel shall present to the COR a valid (non-expired) photo identification issued by a US federal, state or local government agency.

Contractor’s Service Personnel shall be required to sign in once on campus at the Main Building.

Contractor’s Service Personnel shall always report to COR once on campus and before the start of any work.

The Contractor’s Service Personnel shall park vehicles in appropriate designated parking areas.

Smoking is prohibited on the properties.

Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

Work Location and Restrictions:

The Project site is an active research facility and has full occupancy. The Contractor shall not interfere or hinder the daily operations of the facility while performing services. In the event of an emergency, contractor services may be stopped and rescheduled at no additional cost to the Government. If contractor anticipates any such interruption, he must coordinate with the COR in advance. All requests for outages must be submitted in writing to and approved by the COR.

Work Schedule:

Period of Performance is 60 days.

Since this is an active research facility, utility system shutdown during the normal business hour is strictly prohibited. Any work requiring utility shutdown shall be done during the weekend on a continuous basis.

Compliance:

All work shall be accomplished in strict compliance with federal, state, and local laws and regulations Appropriate personal protective equipment (PPE) shall be used where it is necessary.

The contractor shall follow all OHSA requirement applicable to this project – Fall protection, trench and excavation, confined space requirement, ladder use, crane lift.

If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution. All requests for outages/shutdown must be submitted in writing to and approved by the Facility Engineer.

Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

Notification of Noncompliance

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor shall take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the site, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuse to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or excess costs or damages by the Contractor.

Warranties

Submit data concerning the standard one-year warranty for workmanship, including the warranty periods, and warranty contacts with names, addresses and telephone numbers.

Extended Equipment/Product Warranties: Obtain and furnish to the COR all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract.

The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.

File details come from the government source that posted it. Updated .