GOGA PMIS 235841
Maintain Unimproved Road Shoulders and Grade
SECTION 01 10 00
GENERAL REQUIREMENTS
PART 1 - DESCRIPTION OF WORK
1.1
1.2
BACKGROUND: The Park has approximately 38 miles of unpaved fire roads that need to be maintained on a regular basis. Storms and normal wear and tear cause ruts and unraveling of the surface material making it hazardous for bicyclist and hikers. The roads crew is short staffed and does not have enough people to properly maintain the roads and can only address bad spots on an emergency basis.
The goal of this project is to grade the roads and add material where needed to promote positive drainage. This will improve accessibility for visitors and employees and emergency services throughout the park. It will also address deferred maintenance. This contract will consist of grading approximately 3.5 miles of road, Marincello, Haypress, and Fox trail in Mill Valley, and approximately 2,000 Linear Feet (LF) of shoulder repair along Bunker Road in Sausalito. See maps attached.
1.2.1 The contractor will re-establish ditch lines using a motor grader to recontour the ditches, using the material to fill ruts and grade the surface smooth with a motor grader, wet and compact to a hardened surface that allows drainage. The park will provide material from an approved vendor (Mark West Quarry in Santa Rosa) that will be used to fill low areas and place a cap of approximately 2 inches on the roads, that will be watered and compacted to a hard surface. Contractor will use up to 750 tons of Mayacama Red (3/4” Minus) on the roads and up to 50 tons on the shoulders and will be responsible for hauling the material. Work site will be level or smoothed to the extent possible for visitor use, keeping existing slope for drainage. Contractor will be required to make final grade with a motor grader to achieve a uniform smooth finish. Road width will vary and contractor will match existing.
1.2.2 As an option item, the contractor will grade approximately an additional mile of road.
1.3 All work will be performed under a single contract.
1.4 PUBLIC / STAFF USE OF THE SITE
A. General: The project site will be open to the public and/or staff during construction.
The contractor shall at all times conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer. Contractor must submit written request a minimum of two weeks in advance.
PART 2 - EXISTING UTILITIES
2.1 There should be no need for any excavation during this project or utility location.
PART 3 - CONTRACTOR’S USE OF PREMISES
3.1 ON-SITE WORK HOURS: Work shall be generally performed during normal business working hours of 7 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.
3.2 CONSTRUCTION CAMP: N/A
3.3 STORAGE – STAGING AREAS:
A. Confine Storage of materials and equipment to the project area. Contractor can use an area of the parking lot by Rodeo Lagoon for staging. All permitting needs will be the responsibility of the contractor. Limits of use and control shall be subject to Contracting Officer’s approval.
3.4 PRESERVATION OF NATURAL FEATURES: N/A
3.5 HAULING RESTRICTIONS: Hauling to job site will be by single tandem trucks with transfer loads. Staging of trailers will be in the parking area by Rodeo Lagoon.
3.6 HOUSEKEEPING:
A. Keep project neat, orderly, and in a safe condition always. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all hazardous rubbish. Do not allow rubbish to accumulate. Provide onsite containers for collection of rubbish and dispose of it at frequent intervals during progress of work which will include grease cartridges, rags or other materials used to maintain the equipment.
B. Dispose of waste materials legally which will include food waste, wrappers, bottles and cans used for personal consumption of workers during their workday.
PART 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work within 15 calendar days after the date of receipt of the "Notice to Proceed."
PART 5 - EXAMINATION OF THE SITE
5.1 All quoters are urged to visit the job site and examine existing conditions before submitting quotes. All quoters will be held to have the same knowledge concerning the site and the on-ground conditions as if they had inspected the job site.
PART 6 - ABBREVIATIONS
6.1 The following list of abbreviations, which may be used in the Construction Specifications or Special Provisions, refer to the organizations and specifications of the organizations listed below:
AASHTO - American Association of State Highway and Transportation Officials ACI - American Concrete Institute AISC - American Institute of Steel Construction AI - Asphalt Institute ANSI - American National Standards Institute ASTM - American Society for Testing and Materials AWWA - American Water Works Association Caltrans- State of California Department of Transportation FHWA - Federal Highway Administration FS - Federal Specifications MSHA - Mine Safety and Health Administration MUTCD - Manual on Uniform Traffic Control Devices NEC - National Electric Code NEMA - National Electrical Manufacturers Association NFPA - National Fire Protection Association NIOSH - National Institute of Occupational Safety and Health NPS - National Park Service NSF - National Sanitation Foundation OSHA - Occupational Safety and Health Administration PCA _ Portland Cement Association UBC - Uniform Building Code UL - Underwriters Laboratories, Inc.
PART 7 - ACCIDENT PREVENTION
7.1 DESCRIPTION: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.
7.2 SUBMITTALS:
A. ACCIDENT PREVENTION PROGRAM: At the preconstruction conference submit for approval an accident prevention program. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. First aid procedures.
3. Training, both initial and continuing.
4. Planning for possible emergency situations.
5. Contractor to identify nearest location of medical facility for emergencies.
6. Recognition that work will be performed in remote areas with limited communication or cell phone coverage.
B. MEETING AND INSPECTION REPORTS: Submit a report of safety meetings and of inspections.
C. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.
7.3 QUALIFICATIONS OF EMPLOYEES:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
D. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
7.4 ACCIDENT REPORTING: The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
7.5 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.
7.6 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
7.7 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.8 PROTECTIVE EQUIPMENT:
A. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
B. It is the Contractor's responsibility to require all those working on or visiting the site to always wear necessary protective equipment.
7.9 SAFETY MEETINGS: As a minimum, conduct 15 minute "toolbox" safety meetings.
These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
7.10 HAZARDOUS MATERIAL ACTION: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.
PART 8 - PRECONSTRUCTION CONFERENCE:
8.1 PRECONSTRUCTION CONFERENCE: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following:
Roles and Responsibilities Key Personnel National Park Service regulations Documents required under the contract Subcontractors Labor standards provisions Modifications Payments to Contractor Payroll reports Technical Issues Correspondence procedures Acceptance/Rejection of Work Construction Meetings Submittal of shop drawings, project data, and samples Accident prevention program (including name of responsible supervisor) Accident reporting Safety program (compliance with the "Accident Prevention" clause of the General Provisions) Spill Response Plan Saturday, Sunday, holiday and night work Contract Time Tentative construction schedule Notice to Proceed
PART 9 - SUBMITTALS
9.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.
9.2 Equipment: Construction equipment and vehicles
Shop Drawings: Not Applicable (N/A)
Product Data: Provide construction equipment and vehicles to be used for this project.
Samples: N/ A
Erosion Controls: SWPPP or UPPP, whichever is applicable
A. For submittals specified above, forward submittals to Contracting Officer at least 15 days before need for approval.
B. After approving submittals, Contracting Officer will return one copy to the
Contractor.
C. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes.
D. Any work done before approval shall be at Contractor's own risk.
9.3 APPROVED EQUALS: A request for approval constitutes a representation that
Contractor:
A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
B. Will provide the same warranties for the proposed item as for the item specified.
C. Has determined that the proposed item is compatible with interfacing items.
D. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
E. Waives all claims for additional expenses that may be incurred as a result of the substitution.
9.4 PROGRESS SCHEDULES: As soon as possible after Notice of Award and before beginning any work, submit Progress Schedule. Contracting Officer will review the Progress Schedule for format and content. Submit four copies of Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted.
PART 10 - TEMPORARY SERVICES
10.1 DESCRIPTION: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.
10.2 FIRE PREVENTION AND PROTECTION:
A. Hazard Control: Take all necessary precautions to prevent fire during construction.
Provide adequate ventilation during use of volatile or noxious substances.
PART 11 – QUALITY REQUIREMENTS
11.1 QUALITY REQUIREMENTS
A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.
B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor’s Quality Control Supervisor shall utilize the forms attached at the end of this Section. The submission frequency of the QC Daily Report to the contracting officer will be determined at the preconstruction meeting.
PART 12 - PROJECT CLOSEOUT
12.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.
12.2 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
12.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project is substantially complete, and a final inspection is requested.
Contracting Officer will make an inspection within 10 days of receipt of request.
A. When Contracting Officer determines that the work is substantially complete; he will prepare a list of deficiencies (“Punch List”) to be corrected before final acceptance and issue a Letter of
B. Substantial Completion.
C. If Contracting Officer determines that the work is not substantially complete; he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection.
12.4 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a Letter of
Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
END OF SECTION
SECTION 01 27 00
DEFINITION OF CLINS
PART 1 GENERAL
DESCRIPTION
The intent of this section is to explain, in general, what is and what is not included in a Construction Line Item Number (CLIN), and the limits or cut-off points where one CLIN ends and another begins. If no CLIN exists for a portion of the work, include the costs in a related CLIN.
CLIN 1 – Mobilization/Demobilization:
This CLIN shall include all labor, materials, and equipment for the contractor to transport any and all items needed for the project to the project site, and removal of all said items at project end.
CLIN 2 – Traffic Control:
This CLIN shall include all necessary equipment, signage, labor, tools, etc. provided by the contractor to adequately inform the public of work taking place that may interfere with their travel. All signage shall conform to current MUTCD standards.
CLIN 3 - Road Grading:
The work of this CLIN includes re-establishing ditch line, grading road smooth, adding material, watering and compacting. This work includes but is not limited to all materials, labor and equipment to placement, grade, and compaction of material added. This includes all incidental work and preparation associated with this work. Measurement shall be made as a horizontal length of centerline of road section.
Payment shall be made at the contract unit price per lineal mile of road section installed.
CLIN 4 - Trucking:
This CLIN consists of the contractor hauling government supplied materials from the approved vendors.
CLIN 5 - SWPP/UPPP:
This CLIN consists of the contractor providing a plan for erosion controls for the Park to approve.
CLIN 6 - Shoulder Repair:
This CLIN includes furnish and install aggregate base shoulder backing. This work includes but is not limited to all materials, labor and equipment to placement and compaction of shoulder backing material.
Measurement shall be made as a horizontal length at road edge.
Payment shall be made at the contract unit price per lineal foot of shoulder section installed.
CLIN 7 – OPTION Line Item – Road Grading This CLIN consists of the contractor grading an extra one mile of road. This includes but not limited to all labor, materials, equipment and incidentals to grade and compact one mile of additional road, dependent on funding and bids.