Attachment A - Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage_Rate_-_CA37.docx | DOCX document | |
| Amend_1.pdf | ||
| Bidding_Schedule.pdf | ||
| Revised_Specs_2-9-2017.pdf | ||
| Attachment_B.__PAD-Rock_Surfacing_12-14-16.pdf | ||
| Attachment_D.__Foreign_National_Data_Card.pdf | ||
| Attachment_C.__Wage_Grade_-_Davis_Bacon.pdf | ||
| DE-SOL-0010751.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date : 12/14/16
PARKER SUBSTATION
SURFACE ROCK ADDITION
SECTION C
DESCRIPTION/SPECIFICATIONS
California
SPEC NO.
Date : 12/14/16
SECTION C
DESCRIPTION / SPECIFICATIONS
PARKER SUBSTATION SURFACE GRAVEL ADDITION
DIVISION 1 – GENERAL REQUIREMENT
A. CONTRACT REQUIREMENT
B. DESCRIPTION OF WORK
C. DESCRIPTION OF BIDDING SCHEDULE ITEM
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
E. CONSTRUCTION SCHEDULE
F. MATERIAL
G. ELECTRIC POWER FOR CONSTRUCTION PURPOSES
H. WATER FOR CONSTRUCTION PURPOSES
I. ACCESS AND RESTRICTIONS
J. SAFETY
K. SUBMITTALS
A submittal is required if the item is used in the performance of the contract
DIVISION 2 – SITEWORK
A. GENERAL
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. GENERAL
B. SPECIAL CONDITIONS
DIVISION 1 – GENERAL REQUIREMENT
A. CONTRACT REQUIREMENT
Construct and complete the Mead Substation Erosion Repair Project in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western Area Power Administration (WAPA) Construction Standards (September 2013), including Standard 1 – General Requirements, Standard 2 – Sitework, Standard 13 – Environmental Quality Protection, Standard 15 Drawings; Standard Drawings; and these Project Specifications and Drawings.
If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and Drawings are used to take exceptions or provide additions to the Standard Specifications. Some paragraphs in the Standard Specifications will not apply to this job.
WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at: https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx
WAPA’s Project Specifications and Standards are explained in Standard 1 – General Requirements, Section 1.1.1., “Standards and Project Specifications”.
B. DESCRIPTION OF WORK
Provide all necessary equipment, material, and labor to completely install the following:
1. Provide surface gravel and repair structural fill as designated on Drawings PAD T2000-1, PAD
T2000-2, PAD T2020, PAD T2021, PAD T2047-1 and PAD T1500.
Paragraphs “Description of Bidding Schedule Items” in Divisions – 1, 2, and 3 describe the work to be performed.
Location: Parker Dam (PAD), San Bernadino County, Ca.
The switchyards are 18 miles north of the town of Parker on Highway 95.
Parker Dam 230-kV Switchyard:
Latitude: 34 17 27 N Longitude: 114 08 26 W
Parker Dam Upper 161-kV Switchyard:
Latitude: 34 17 38 N Longitude: 114 08 26 W
Parker Dam Lower 161-kV Switchyard:
Latitude: 34 17 41 N Longitude: 114 08 26 W
Parker Dam 69-kV Switchyard:
Latitude: 34 17 37 N Longitude: 114 08 27 W
Direction: Approximately 167 miles from Phoenix, Arizona. Proceeding from the intersection of California Avenue and Riverside Drive in Parker, Arizona. Head northwesterly on California Avenue into California. Turn right onto Parker Dam Road and head northeasterly past Trails End Camp Road (Mwd Road). About ¼ mile past Trails End Camp Road to the Mead Substation, make the first left making a U-turn to the main gate entrance of Parker Dam Substation. Refer to Drawing PAD 0015B.
https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx
C. DESCRIPTION OF BIDDING SCHEDULE ITEM
1. Bidding Schedule item “Mobilization and Preparatory Work” includes the following:
a) Perform mobilization and preparatory work in accordance with Section H of the contract clauses.
b) Prepare and submit a Construction Schedule within 5-days after work commences. A Safety and Health Program shall be submitted to the Construction Officer Representative (COR) for approval at least 10-days prior to construction operations. The Contractor shall not begin construction operations until approval has been received from the COR.
c) All bond costs.
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
1. COMMENCEMENT AND COMPLETION: Refer to Section F, Clause 52.211-10.
2. RESTRICTIONS: Outage requests shall be submitted no less than 10-work-days prior to need.
Approval is based on customer approval and timing, and may be denied.
3. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 20-calendar-days for review of submittals.
4. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized to carry the maximum available fault current in accordance with Standard 1 – General Requirements, Section 1.4., “Safety and Health”, and the following:
The maximum available fault current in the 69-kV area is 4,587 amps, X/R = 34.8.
The maximum available fault current in the 161-kV area is 11,995 amps, X/R = 13.2.
The maximum available fault current in the 230-kV area is 14,615 amps, X/R = 10.3.
E. CONSTRUCTION SCHEDULE
SUBMITTAL TIME: Refer to FAR Clause 52.236-15 for Construction Schedule submittal. The Schedule shall be submitted to the COR no later than 10-calendar-days after the issuance of the Notice to Proceed. As part of the Schedule, the Contractor shall submit an approved Microsoft Project logic-based, time-phase Baseline Schedule with the critical paths identified. The Schedule shall be approved prior to the commencement of work.
F. MATERIAL
Contractor shall furnish all material for completing the work.
Point of Delivery: The Contractor is responsible for pick-up and delivery to the jobsite. The Contractor shall inspect the material in accordance with the Specifications’ requirements, and immediately report any damages to the COR.
G. ELECTRIC POWER FOR CONSTRUCTION PURPOSES
The Contractor shall furnish power for his operations by own means.
H. WATER FOR CONSTRUCTION PURPOSES
The Contractor shall provide water needed for construction purposes, and potable water for employees. Make arrangements for obtaining, and conveying water to points of use.
I. ACCESS AND RESTRICTIONS
WAPA’s business hours are Monday through Friday from 7:30 AM to 4:30 PM. The substation will be live during construction. The contractor’s onsite work is restricted to be performed within these hours. Due to the security requirements for this site, access to the site and work performed outside normal work hours shall be coordinated with the COR. Work will also be restricted to one substation level and location at a time.
J. SAFETY
1. In performing the work required by this contract, the Contractor shall comply with all applicable
Federal, State, and local safety, health, or industrial safety codes, including the latest effective standards promulgated by the Secretary of Labor for the Department of Labor and Health Administration, Safety and Health Standards (29 CFR 1910), and the Construction Safety and Health regulations promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (29 CFR 1926). If there is a conflict between the requirements of the applicable Federal, State, and local safety, health, or industrial safety codes, the more stringent requirements shall prevail. The United States is liable only for negligence on the part of its employees in accordance with the Federal Government Claims Act, as amended.
2. Prior to commencing work, an on-site safety meeting shall be held with WAPA’s representatives to address and discuss safety procedures related to the work required, and to discuss potential hazards and their mitigation. WAPA has the right to remove any Contractor employee that does not adhere to the safety requirements.
K. SUBMITTALS
1. GENERAL: Submittals shall be provided in accordance with the Construction Standards and Project Specifications. The Contractor shall furnish submittals electronically (i.e. E-mail), unless otherwise specified by the COR. Submittals shall be sent to:
DSW-G5600-CS@wapa.gov in standard PDF or electronic CAD “*.dwg” (AutoCAD 2010) formats. All submittals shall include WAPA's contract number, project title, transmittal/submittal number, and corresponding item number. Refer to the Submittal Log for the list of required submittals. This list may not be all-inclusive, and it remains the Contractor's responsibility to ensure conformance to the individual Specifications for possible additional submittal requirements. The submittal cover sheet in Microsoft Word or PDF format shall be included.
2. In addition to required submittals, the Contractor shall submit the following information electronically to DSW-G5600-CS@wapa.gov:
a) Payrolls
b) Sub-Contractor List/Forms
c) Citizenship Forms
d) Erosion Control Plan
e) Environmental Submittals
f) Request For Information (RFI)
g) Request for Equitable Adjustment (REA)
h) Any questions, comments, correspondence relevant to this project.
A submittal is required if the item is used in the performance of the contract.
mailto:DSW-G5600-CS@wapa.gov mailto:DSW-G5600-CS@wapa.gov
3. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph.
4. ADDRESS: The Contractor shall transmit specified non-electronic submittals to the following address:
Western Area Power Administration Western Area Power Administration
ATTN: G5600 ATTN: G5600
P.O. Box 6457 615 43rd Avenue Phoenix, AZ 85005-5313 Phoenix, AZ 85009
DIVISION 2 – SITEWORK
A. GENERAL
1. Site work shall be in accordance with WAPA’s Construction Standard 2 except as indicated below.
2. Washed crushed rock as specified in WAPA Standard 2.11.3 must be placed such to ensure protection from damage to the ground grid while providing a minimum three inch depth. At no time will the top of the washed rock exceed the top of any existing concrete slab. Ground grid damaged by the Contractor must be immediately repaired to the satisfaction of the COR and at no cost to WAPA. Ground grid repairs must be “Thermowelded”.
3. New washed crushed rock fill will be loosely placed over currently exposed horizontal ground grid as indicated within this item and on project drawings PAD T2000-1, PAD T2000-2, PAD T2020 and PAD T2021. The surface gravel will extend a minimum of 5 feet in all horizontal directions beyond the previously exposed ground grid. Additional two feet of transitional surface gravel will be used to provide a smooth appearance between old and new surface gravel as indicated on drawing PAD T2000-1.
4. New washed crushed rock fill will be loosely placed over the 230 kV yard at a four inch depth as indicated on project drawing PAD T2047-1. The surface gravel will transition from one inch below the top of the cable trench or concrete foundation to a three inch depth located ten feet from the outside of the cable trench as shown on PAD 2047-1A.
5. Structural fill repair will be made at structure 0/1 of the PAD-PNT 69kV transmission line which is located within the Parker Dam 69 kV yard. Install two cubic feet of concrete slurry to fill a poorly compacted area next to the structure. Place top six inches of compacted soil to drain away from the structure.
11. Implement construction Best Management Practices (BMP’s) to prevent siltation and erosion damage during construction repair.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Provide Washed Crushed Rock” includes the following:
a) Washed Crushed Rock per drawings (1179 loose cubic yards).
b) Repair of existing grounding grid includes new grounding copper wire (500 MCM to be verified) to repair the existing grounding mat. Locate ground mat and connect ground wire to the mat with exothermic or compression connector. Installation shall be in accordance with WAPA's Standard Drawings, and include ground rod as required.
2. Bidding Schedule item “Provide Structural Fill Repair” includes the following:
a) Slurry fill (2 c.f.) with compacted soil surface.
3. Bidding Schedule item “Miscellaneous Sitework” includes the following:
a) Best Management Practices.
b) Soil applied herbicide where gravel is placed.
c) Survey of existing ground grid to determine depth of scarification (to be approved by COR) to eliminate destruction of ground grid.
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. GENERAL
1. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items:
a) Contractor-furnished Data (refer to Standard 13.2)
b) Environmental Requirements (refer to Standard 13.3)
c) Landscape Preservation (refer to Standard 13.4)
d) Preservation of Cultural and Paleontological Resources (refer to Standard 13.5)
e) Noxious Weed Control (refer to Standard 13.6)
f) Recycled Material Quantities (refer to Standard 13.7)
g) Use of Recovered Material and Bio-based Material Products (refer to Standard 13.8)
h) Disposal of Waste Material (refer to Standard 13.9)
i) Contractor’s Liability for Regulated Material Incidents (refer to Standard 13.10)
j) Pollutant Spill Prevention, Notification, and Cleanup (refer to Standard 13.11)
k) Pesticides (refer to Standard 13.12)
l) Prevention of Air Pollution (refer to Standard 13.14)
m) Prevention of Water Pollution (refer to Standard 13.17)
n) Removal of Oil-Contaminated Material (refer to Standard 13.19)
o) Conservation of Biological Resources (refer to Standard 13.20)
B. SPECIAL CONDITIONS
1. PREVENTION OF AIR POLLUTION (IN ADDITION TO STANDARD 13.14):
The Contractor shall complete and submit a Dust Control Permit Application and applicable fees to Clark County Department of Air Quality before construction activities begin within Clark County. The Contractor shall submit copies of all permit applications and plans to the COR 14-calendar-days prior to the start of work on-site. Information on dust control permitting can be found at the following website address:
http://www.clarkcountynv.gov/depts/AirQuality/Pages/Compliance_DustPermitting.aspx
2. CONSERVATION OF BIOLOGICAL RESOURCES (IN ADDITION TO STANDARD 13.20):
All project personnel will complete biological pre-activity awareness training to ensure that they are familiar with sensitive biological resources, including Mojave Desert Tortoise, in the Mead Substation area.
http://www.clarkcountynv.gov/depts/AirQuality/Pages/Compliance_DustPermitting.aspx
Project vehicles shall be restricted to designated access routes and approved worksites.
Vehicle speeds will not exceed 25-mph on access and maintenance roads, and 20-mph on unimproved access routes. Project vehicles and equipment will be parked on pavement, existing roads, and previously disturbed areas, to the maximum extent feasible.
At the end of each work day, the Contractor shall fence, cover, or fill excavations greater than one-foot-deep. Alternately, the Contractor shall provide escape ramps (1:1 slope) in open excavations to prevent the entrapment of wildlife. The Contractor shall inspect open excavations for entrapped wildlife before excavations are filled. Any entrapped animals will be allowed to escape voluntarily before activities resume, or they may be removed by qualified personnel, under the direction of the COR, by a qualified Biologist possessing the appropriate handling permit(s), if necessary.
At the end of each work day, all project personnel will remove food-related trash from the worksite in closed containers for disposal. Workers will not feed wildlife.
Message from the Administrator
At WAPA, we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our Contractors who provide products or services to WAPA. In performing work for WAPA, all Contractors shall make the right decisions to ensure that the work environment is as safe as possible.
Our Safety Program is based on four points:
Safety procedures or common sense shall be applied by each Federal and
Contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.
Employees and Contractors shall believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.
Managers and Supervisors shall lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.
Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.
By integrating these principles into every task we take, together we can ensure WAPA is a safe place to work.
Mark A. Gabriel Administrator
| DIVISION 1 – GENERAL REQUIREMENT |
| A. CONTRACT REQUIREMENT |
| B. DESCRIPTION OF WORK |
| C. DESCRIPTION OF BIDDING SCHEDULE ITEM |
| D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK |
| E. CONSTRUCTION SCHEDULE |
| F. MATERIAL |
| G. ELECTRIC POWER FOR CONSTRUCTION PURPOSES |
| H. WATER FOR CONSTRUCTION PURPOSES |
| I. ACCESS AND RESTRICTIONS |
| J. SAFETY |
| K. SUBMITTALS |
| A submittal is required if the item is used in the performance of the contract. |
| DIVISION 2 – SITEWORK |
| A. GENERAL |
| B. DESCRIPTION OF BIDDING SCHEDULE ITEMS |
| DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION |
| A. GENERAL |
| B. SPECIAL CONDITIONS |