Project Drawings.pdf

PDF 16 MB Posted

Attached to
Appeldorn Substation, Stage 01, Minnesota Federal contract opportunity
Solicitation number
DE-FB65-11WC92475
Issued by
Department of Energy Western Area Power Administration

About this file

Appeldorn Substation Construction Drawings

View the file

Other files for this federal contract opportunity

Other files attached to Appeldorn Substation, Stage 01, Minnesota, newest first.
File Type Posted
Amendment 002 Drawing.pdf PDF
Amendment 002 Spec Pages Wage Rates.pdf PDF
Amendment 001 Spec Pages Wage Rates.pdf PDF
Amendment 001 Drawings.pdf PDF
Contract Clauses Bid Schedule.pdf PDF
Project Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPELDORN SUBSTATION

STAGE 01

MINNESOTA

SECTION C

DESCRIPTION/SPECIFICATIONS

Solicitation No. DE- FB65-11WC92475 Spec. No. 11WC92475-735

DIVISION 15 - DRAWINGS

A. GENERAL:

A complete set of standard drawings are available at http://www.wapa.gov/business/buys.htm.

LIST OF DRAWINGS:

LOCATION MAP:

1. APD 0015 – Location and Vicinity Map

2. GF 0015 – Location and Vicinity Map – Rev. B

3. APD 0016 – Topographic Survey

ELECTRICAL:

4. APD 0001 – Switching Diagram

5. APD 0010 – Plot Plan

6. APD 1000 – Arrangement Plan

7. APD 1020 – 115kV Area Plan

8. APD 1021 – 69kV Area Plan-Bays 3Z-6Z

9. APD 1022 – 115kV Area Plan

10. APD 1023 – 69kV Area Plan-Transformer KV4A & Bays 1Z & 2Z

11. APD 1024 – 230kV Area Plan-Bays 1 V & 3 V

12. APD 1025 – 230kV Area Plan-Bays 2 V & 4 V

13. APD 1026 – 230kV Area Plan-Bays 5 V & 7 V

14. APD 1027 – 230kV Area Plan-Bays 6 V & 8 V

15. APD 1100 – Equipment & Material Index

16. APD 1110 – 230kV Area – Section A-A

17. APD 1111 – 230kV Area – Section B-B

18. APD 1112 – 230kV Area – Section C-C

19. APD 1113 – 230kV Area – Section D-D

20. APD 1114 – 230kV Area – Section E-E

21. APD 1115 – 230kV Area – Sections F-F & G-G

22. APD 1116 – 230kV Area – Sections H-H & I-I

23. APD 1117 – Transformer KV4A – Section J-J

24. APD 1118 – 69kV Area – Sections K-K & L-L

25. APD 1119 – 69kV Area – Sections M-M & N-N

26. APD 1120 – 69kV Area – Sections O-O & P-P

27. APD 1121 – 69kV Area – Sections Q-Q, T-T & W-W

28. APD 1122 – 230kV Area – Section R-R, Detail A and Detail B

29. APD 1123 – 69kV Area – Sections S-S & U-U

30. APD 1124 – 69kV Area – Sections X-X, Y-Y & Z-Z

31. APD 1125 – 69kV Area – Section AA-AA

32. APD 1500 – General Grounding Plan

33. APD 1520 – 115kV Area Grounding Plan

34. APD 1521 – 69kV Area Grounding Plan-Bays 3Z-6Z

35. APD 1522 – 115kV Area Grounding Plan

36. APD 1523 – 69kV Area Grounding Plan-Transformer KV4A & Bays 1Z & 2Z

37. APD 1524 – 230kV Area Grounding Plan-Bays 1 V & 3 V

38. APD 1525 – 230kV Area Grounding Plan-Bays 2 V & 4 V

39. APD 1526 – 230kV Area Grounding Plan-Bays 5 V & 7 V

40. APD 1527 – 230kV Area Grounding Plan-Bays 6 V & 8 V

41. APD 1600 – Unit Substation DWA – Wiring Diagram

42. APD 1601 – 230kV North Area Station Service – Panel DHA1 – Wiring Diagram

43. APD 1602 – 230kV South Area Station Service – Panel DHA2 – Wiring Diagram

44. APD 1603 – 69kV Area Station Service – Panel DHA3 – Wiring Diagram

45. APD 1610-1 – Station Service Panel DHA1 – 240/120 Volt Power and Lighting – Wiring Diagram

46. APD 1610-2 – Station Service Panel DHA2 – 240/120 Volt Power and Lighting – Wiring Diagram

47. APD 1610-3 – Station Service Panel DHA3 – 240/120 Volt Power and Lighting – Wiring Diagram

48. APD 1710 – General Conduit Plan

49. APD 1720 – 115kV Area Conduit Plan

50. APD 1721 – 69kV Area Conduit Plan-Bays 3Z-6Z

51. APD 1722 – 115kV Area Conduit Plan

52. APD 1723 – 69kV Area Conduit Plan-Transformer KV4A & Bays 1Z & 2Z

53. APD 1724 – 230kV Area Conduit Plan-Bays 1 V & 3 V

54. APD 1725 – 230kV Area Conduit Plan-Bays 2 V & 4 V

55. APD 1726 – 230kV Area Conduit Plan-Bays 5 V & 7 V

56. APD 1727 – 230kV Area Conduit Plan-Bays 6 V & 8 V

57. APD 1728 – Station Service – Conduit Details

58. APD T600 – Control Cable List

FOUNDATION AND STRUCTURAL DRAWING INDEX:

59. APD 2000 – Foundation/Structural Data – and Drawing Index

GRADING & SITE:

60. APD T0001 – Pipe Location Map

61. APD 2050 – Grading Plan

62. APD 2051 – Grading Sections

63. APD 2052 – Grading Details

SUBSTATION CONCRETE:

64. APD 2210 – General Foundation Plan

65. APD 2220 – Foundation Plan – 115kV Area

66. APD 2221 – Foundation Plan – 69kV Area – Bays 3Z–6Z

67. APD 2222 – Foundation Plan – 115kV Area

68. APD 2223 – Foundation Plan – 69kV Area – Transformer KV4A & Bays 1Z & 2Z

69. APD 2224 – Foundation Plan – 230kV Area – Bays 1 V & 3 V

70. APD 2225 – Foundation Plan – 230kV Area – Bays 2 V & 4 V

71. APD 2226 – Foundation Plan – 230kV Area – Bays 5 V & 7 V

72. APD 2227 – Foundation Plan – 230kV Area – Bays 6 V & 8 V

73. APD 2300 – Foundations – Outline and Reinforcement

74. APD 2301 – Foundations – Outline and Reinforcement

75. APD 2302 – Foundations – Outline and Reinforcement

76. APD 2303 – Foundations – Outline and Reinforcement

77. APD 2304 – Foundations – Outline and Reinforcement

78. APD 2305 – Foundations – Outline and Reinforcement

79. APD 2306 – Foundations – Outline and Reinforcement

CABLE TRENCH:

80. APD 2500 – Type “C” Cable Trench – Plan

81. APD 2501 – Type “C” Cable Trench – Sections

STEEL STRUCTURES:

82. APD 2550 – Anchor Bolts

83. APD 2600 – 230kV Take-Off Structure – Type I – Elevations

84. APD 2601 – 230kV Take-Off Structure – Type I – Assemblies and Connections

85. APD 2602 – 69V Take-Off Structure – Type I – Elevations

86. APD 2603 – 69kV Take-Off Structure – Type I – Assemblies and Connections

87. APD 2604 – 230kV Bus Tower – Type I – Elevations

88. APD 2605 – 230kV Bus Tower – Type I – Assemblies and Connections

89. APD 2606 – 14.4kV Switch & Bus Support – Type II

90. APD 2608 – 69kV Switch Supports – Type III, IV, V

91. APD 2609 – 230kV Switch Supports – Type I, II

92. APD 2610 – 230kV Bus Frame – Type I, II, III, IV

93. APD 2611 – 69kV Tee Pole – Type I, II, III

94. APD 2612 – 230kV Tee Pole – Type IV, V

95. APD 2613 – Bus Poles – Type I, II, III, IV, V

96. APD 2614 – Equipment Support – Type I, II, III

97. APD 2615 – 65 Ft Ground Mast – Type I

98. APD 2616 – 69kV Fuse Disconnecting – Switch Support – Type I

99. APD 2617 – 14.4kV Switch & Bus Support – Type I

100. APD 2618 – 24.9kV Transformer Support – Type I

101. APD 2925 – Equipment Cabinet Platforms – Steel Design and Details

102. APD 2926 – Building Entry Platforms – Steel Design and Details

103. APD 2927 – Switch Operating Platforms – Steel Design and Details

104. APD 2950 – General Erection Plan

105. APD 2951 – Erection Plan – 115kV Area

106. APD 2952 – Erection Plan – 69kV Area – Bays 3Z-6Z

107. APD 2953 – Erection Plan – 115kV Area

108. APD 2954 – Erection Plan – 69kV Area – Transformer KV4A & Bays 1Z & 2Z

109. APD 2955 – Erection Plan – 230kV Area – Bays 1 V & 3 V

110. APD 2956 – Erection Plan – 230kV Area – Bays 2 V & 4 V

111. APD 2957 – Erection Plan – 230kV Area – Bays 5 V & 7 V

112. APD 2958 – Erection Plan – 230kV Area – Bays 6 V & 8 V

STRINGING REQUIREMENTS:

113. APD 2910 – Stringing Requirements

SERVICE BUILDING:

114. APD 3000-1 – General Structural Notes, – Abbreviations & Reference Drawings

115. APD 3000-2 – Structural – Building Grading Plan & Details

116. APD 3001 – Structural – Foundation Plan

117. APD 3002-1 – Structural – Foundation Sections & Details 1 of 2

118. APD 3002-2 – Structural – Foundation Sections & Details 2 of 2

119. APD 3003-1 – Structural – Cable Entry Details (Sheet 1 of 2)

120. APD 3003-2 – Structural – Cable Entry Details (Sheet 2 of 2)

121. APD 3004 – Architectural – Floor Plan

122. APD 3005 – Architectural – Exterior Elevations

123. APD 3006 – Architectural – Building Sections

124. APD 3007 – Architectural Wall Details

125. APD 3008 – Architectural – Door and Window Details

126. APD 3009 – Mechanical – Floor Plan

127. APD 3010 – Mechanical – Enlarged Plan and Schedules

128. APD 3011 – Mechanical – Battery Room Diagram & Schedules

129. APD 3012 – Mechanical Mounting Details

130. APD 3013 – Electrical – Power Plan

131. APD 3014 – Electrical – Mechanical Power Plan

132. APD 3015 – Electrical – Lighting Plan

133. APD 3016 – Electrical – Luminaire Schedule

134. APD 3017 – Electrical – AC Distribution Panels DHB1, DHB2

135. APD 3018 – Electrical – Equipment Mounting Details

136. APD 4000 – Electrical – Arrangement, Conduit and Grounding

137. APD 6000 – DC Distribution Panel BHA – Wiring Diagram

TRANSMISSION LINE:

138. WT-GF D 1002 – Material Quantities - for Structures – Rev. B

139. WT-GF D 1003 – Vibration Dampers - for Structures

TRANSMISSION LINE STEEL POLE STRUCTURES:

140. 43-266D 2200 – 266D Pole Structures – Outline and Design Loads

PLAN AND PROFILES:

141. WT–GF D 4029 - Rev. A – Watertown-Granite Falls – Existing Installation

142. WT-GF D 4029-2 - Rev A – Watertown-Granite Falls 230kV DBL Circuit Transmission Line Plan & Profile

GEOLOGY:

143. APD 8000-1 – Geologic Bore Logs (sheet 1 of 2)

144. APD 8000-2 – Geologic Bore Logs (sheet 2 of 2)

STEEL LATTICE TOWERS:

145. 43-208A 2200 – Type 208A Tower

146. 43-208A 2201 – Extensions for Type 208A & 208A1 Towers

147. 43-208S 2200 – Type 208S Tower

148. 43-208S 2201 – Extensions for Type 208S Tower

149. FT-HUD 2015 – Rev A – Footing Data and Selection Criteria

Co Hwy 2

20 21 APD T0001

Designed:____________________ Approved:____________________Doug Hanson

G I S

Eric Weisbender

This map and data are the property of WAPA/DOE and are intended for planning and analysis only. No reproduction or copying of this product is allowed without the sole consent of WAPA/DOE. To contact WAPA about this map, please call 1-800-336-7288.

This cartographic product and GIS data were prepared in accordance with professional practice standards. The data represented on this map has been developed from the best available sources. Although efforts have been made to ensure that the data is accurate and reliable, errors may be reflected in the data. Users must be aware of these conditions and bear responsibility for the appropriate use of this map. The data on this map is for reference use only.

M i n n e s o t a

I o w a

S o u t h D a k o t a

N o r t h D a k o t a

N e b r a s k a

W i s c o n s i n

Project Area ^

Fi le

: M :\v ec to r\u gp

\p ro je ct s\ ap pe ld or n\ ci vi l_ m ap \p ip e_ lo ca tio n.

m xd

K

0 150 300 45075 Feet

MAY 27, 2011

UNITED STATES DEPARTMENT OF ENERGY

WESTERN AREA POWER ADMINISTRATION

CORPORATE SERVICES OFFICE - LAKEWOOD, COLORADO

Legend

Substation Drawing

1 Foot Elevation Contours

Section Boundary

MINNESOTA

APPELDORN SUBSTATION

PIPE LOCATION MAP

1:3,200Scale

Ap pr ox im ate ly

' to R oa d D itc h

" 40' Centerline Road to Pipe

Pipe Elevation Profile

CORPORATE SERVICES OFFICE - LAKEWOOD, COLORADO

CIVIL ENGINEERING MANAGER

denton Rectangle denton Typewritten Text

APRIL 29, 2011

Rectangle denton Typewritten Text denton Typewritten Text

APRIL 29, 2011

Typewritten Text

Message from the Administrator

At Western, we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to Western. In performing work for Western, all contractors must make the right decisions to ensure that the work environment is as safe as possible.

Our safety program is based on four points:

� Safety procedures or common sense must be applied by each

Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.

� Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.

� Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.

� Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.

By integrating these principles into every task we take, together we can ensure Western is a safe place to work.

apd_0015
gf_0015b
apd_0016
apd_0001
apd_0010
apd_1000
apd_1020
apd_1021
apd_1022
apd_1023
apd_1024
apd_1025
apd_1026
apd_1027
apd_1100
apd_1110
apd_1111
apd_1112
apd_1113
apd_1114
apd_1115
apd_1116
apd_1117
apd_1118
apd_1119
apd_1120
apd_1121
apd_1122
apd_1123
apd_1124
apd_1125
apd_1500
apd_1520
apd_1521
apd_1522
apd_1523
apd_1524
apd_1525
apd_1526
apd_1527
apd_1600
apd_1601
apd_1602
apd_1603
apd_1610_1
apd_1610_2
apd_1610_3
apd_1710
apd_1720
apd_1721
apd_1722
apd_1723
apd_1724
apd_1725
apd_1726
apd_1727
apd_1728
apd_t600
apd_2000
apd_t0001
apd_2050
apd_2051
apd_2052
apd_2210
apd_2220
apd_2221
apd_2222
apd_2223
apd_2224
apd_2225
apd_2226
apd_2227
apd_2300
apd_2301
apd_2302
apd_2303
apd_2304
apd_2305
apd_2306
apd_2500
apd_2501
apd_2550
apd_2600
apd_2601
apd_2602
apd_2603
apd_2604
apd_2605
apd_2606
apd_2608
apd_2609
apd_2610
apd_2611
apd_2612
apd_2613
apd_2614
apd_2615
apd_2616
apd_2617
apd_2618
apd_2925
apd_2626
apd_2927
apd_2950
apd_2951
apd_2952
apd_2953
apd_2954
apd_2955
apd_2956
apd_2957
apd_2958
apd_2910
apd_3000_1
apd_3000_2
apd_3001
apd_3002_1
apd_3002_2
apd_3003_1
apd_3003_2
apd_3004
apd_3005
apd_3006
apd_3007
apd_3008
apd_3009
apd_3010
apd_3011
apd_3012
apd_3013
apd_3014
apd_3015
apd_3016
apd_3017
apd_3018
apd_4000
apd_6000
wt_gf_d_1002b
wt_gf_d_1003
43_266d_2200
wt_gf_d_4029a_ei
wt_gf_d_4029_2a
apd_8000_1
apd_8000_2
43_208_a_2200
43_208_a_2201
43_208_s_2200
43_208_s_2201
ft_hu_d_2015d

File details come from the government source that posted it. Updated .