STATEMENT OF WORK

BOILER REPLACMENT PROJECT

Drug Enforcement Administration (DEA) Office of Training

2500 Investigation Parkway Quantico, Virginia 22135

1. OVERVIEW STATEMENT

The Drug Enforcement Administration (DEA) has a requirement to replace the aging and increasingly unreliable Superior Boilers located in the penthouse of the DEA Training Academy. The boilers having been installed in 1998, are at the end of their useful life and by industry standards are due for replacement. The boilers are critical in the operation of the Academy Building and the Training Mission and therefore need to be fully dependable and functional at all times which require replacement to accomplish this goal.

2. SCOPE OF WORK

A. General

The Contractor shall provide the following:

1. Remove, dispose, and replace the two (2) existing 250 BHP Superior Boilers in the penthouse of the DEA Academy. This work shall include all equipment, materials, crane, rigging, demolition, removal of debris, supervision, specialized trade work, and labor to complete this Scope of Work in a safe, timely, and professional manner in accordance with all Federal, State and local codes and ordinances, EPA, OSHA and all other governing regulatory standards. All work is to be performed in a workmanship like manner using trade and industry accepted methods and practices by properly trained and/or licensed (where required) personnel in any of the disciplines required to complete this Scope of Work. The contractor shall confirm the location, existing conditions, mechanical specifications, electrical, sizing, physical dimensions, weight, piping, controls, operation, connections, valve operation, and rigging requirements prior to beginning work and/or ordering materials to ensure that no discrepancies, shortages in service, or operation will result when the replacement project is complete and that every effort is made to prevent additional costs or modifications to the proposals submitted for work required in this scope.

2. The Contractor shall, prior to beginning, work provide all resources necessary to evaluate, plan, coordinate, schedule, pre-fabricate, and plan to obtain all parts and materials necessary for the project to insure the minimal amount of downtime to the building systems impacted by the work in this scope.

3. All work for this project shall be the sole responsibility of the Contractor, including any Sub- Contractors, Equipment Manufacturer Personnel, Riggers, Laborers, Equipment Operators, Delivery Persons, and Refuse Removers. The Contractor shall provide a designated onsite supervisory employee responsible for daily oversite in all matters in the above said persons.

4. The major equipment requirement in this scope was modeled after a Unilux Boiler Model No.

ZF1000W-FE3-GO Boiler with a Power Flame Model CR5-GO-30B-HTD high turndown burner.

This equipment was used as a baseline to generate this scope and is an example of acceptable equipment to satisfy the project requirements but the DEA will review for approval any equal or greater in the specifications of the equipment.

5. The new boilers to be provided in this scope shall have a minimum Twenty (20) year warranty, be high efficiency, hot water, dual fuel (natural gas and fuel oil), and each boiler to be sized to replace the existing 250BHP (each) built to ASME Code, Section IV 160 PSIG and 250 deg F

MAWT.

6. The new boilers shall be equipped with high efficiency/high turn down burners built to UL, CSD- 1 Code and shall include the following:

a. Dual fuel natural gas and # 2 oil

b. Full Modulation Operation up to 10:1

c. 3 Phase Voltage with control circuit transformer

d. Complete Gas Train - UL, CSD-1 Code

e. Remote Fuel Oil Pump for Easy Fuel Changeover

f. Separate ignitions for oil and gas

g. BACnet interface for BMS interface

7. The removal of existing boilers and the installation of the new boilers shall be accomplished one at a time insuring that there is one boiler fully operational at all times to keep the Academy’s heat and hot water systems functional.

8. The replacement of the boilers shall be accomplished with minimal changes or alterations to the building shell and openings. Any alterations or changes that the contractor proposes or deems necessary to accomplish the requirements of this Scope of Work must be submitted in writing with attached drawings to be reviewed for approval/denial by DEA with all costs included and detailed in the submission. If approved, any changes shall be returned to their original condition before the project is complete/

9. If it is deemed necessary to accomplish the installation and the new boilers need to be supplied fully or partially knocked down for field assembly on the jobsite, this field assembly shall only be performed by the boiler manufacturer’s personnel and shall be included in quoted price. This field assembly at minimum shall include the following:

a. Pressure vessel assembly.

b. ASME hydrostatic testing.

c. Pressure vessel ASME stamping.

d. Coordinated Inspection/testing requirements for any required certifications and/or registrations witnessed and approved by local Authorized State Inspector.

e. Complete boiler housing and boiler jacket assembly.

f. Boiler trim* mounting including wiring to boiler front wall terminal strip.

g. Burner mounting on boiler.

*Boiler trim equipment shall comply with ASME Code CSD-1 requirements and shall include:

a. Relief valve as per ASME Code requirements.

b. Thermometer, bi-metal, 0 to 250 degrees F, 3” dial-winters.

c. Pressure Gauge, 4-1/2” Dial – Winters.

d. Operating aqua stat, automatic reset, range 100 to 240F.

e. Modulating aquastat, 135-ohm proportional signal, range 160 to 260F, c/w well Honeywell # T991A1061 or equal .

f. – Honeywell # L4008E1040 or equal.

g. Probe type Main LWCO with manual reset c/w test switch and (2) LED indicating lights – Hydro-level Safguard # 550 or equal.

11. The Contractor shall provide all necessary changes to the building infrastructure to complete the work in this scope including Mechanical, Plumbing, Electrical, Communication, Controls, and all other supporting building areas.

12. The Contractor shall employ a Factory Authorized Automated Logic Company to provide any and all connections, devices, and programming to connect the new boilers to the existing Building Automation System. The integration of the new boilers into the existing automation system shall at minimum provide the same control, alarm, and monitoring points as currently exist.

B. Co-ordination of Hazardous Work

1. The refuse removal and replacement/installation, rigging, welding (hot work) and any other associated hazardous work is to be accomplished on weekdays and it is the contractor’s sole responsibility to coordinate the permitting, date, and time with the DEA Office of Training Facilities Staff, and any other parties including providing adequate personnel and equipment to insure public and property safety.

C. Hours of Contractor Access, Construction Hours, and Base Closings

1. The hours of contractor access will be Monday through Friday, 7:00 am to 4:30 pm. Any special access on weekends and holidays must be coordinated in advance with the appropriate DEA Task Monitor. Lack of coordination will not be the responsibility of the DEA for any costs or delays in the project, in any way. All access to the DEA Training Academy will be via the FBI/DEA Training Academy’s West Gate for daily personnel and the FBI East Gate for deliveries and large vehicles/equipment.

2. Work shall be scheduled so as to minimize the disruption to building occupants and operations.

Proper notification and coordination shall be made when project work necessitates shutting down equipment or otherwise terminating services to the building occupants. Requests shall be submitted in writing to DEA with a description of the shutdown and the reason for the requirement at least 72 hours prior to the need (see Section “D” below). No shutdown shall occur without written approval from DEA.

3. In the event the USMC Base Quantico, The FBI Academy, or DEA closes for any reason, the

DEA will not be the responsible for any costs or delays in the project. The time during which the closure occurs will be credited to the timeline for completion of the project without penalty to the contractor.

D. Project Schedule and “Down Time”

1. The project completion time shall be twenty (20) weeks for this Scope of Work from the official “Notice to Proceed” issued by the Government. The work in this Scope must begin before September 30th, 2019. The Contractor prior to beginning work shall provide a project schedule to DEA for review and concurrence.

2. While accomplishing the work detailed in this scope, every effort shall be made by The Contractor to provide no more than three (3) hours of actual downtime to the building hot water system at any given time on any day of the project. Downtime to any of the building systems shall be requested in writing at least 72 hours prior to the need and approved by DEA.

Shutdowns will be coordinated with the onsite Facilities Staff.

E. Personnel Security Requirements

1. Due to DEA’s security requirements The Contractor shall at least fourteen (14) days prior to starting the onsite work, submit a complete list of all persons (employees and sub-contractors) that they purpose to have work on this project. The list shall include the Name and position/Title/duties of each person. Additionally, each person that requires access to the DEA Property for this project is required to complete an access request form provided by DEA. The access forms shall be emailed to the designated DEA Contact and a log of submittals shall be kept by the contractor. A list of approved persons shall be updated and provided to the Contractor as changes occur. Failure to comply may result in person/s being refused access to the buildings and will not be the Governments responsibility for any costs or delays in the project.

2. It is the contractor’s responsibility to provide personnel suitable for access and it will not be the responsibility of the government for any additional costs or delays incurred from the submittal of unsuitable individuals by the contractor.

F. Clean Up and Damage Prevention

1. The Contractor shall be responsible for the removal and disposal of all unneeded materials and trash generated in the performance of the work in this Scope. All efforts will be made by the contractor to recycle the refuse generated in the accomplishment of this project to the greatest extent possible.

2. The Contractor shall keep all building and work areas safe and free of debris daily. Care is to be exercised in the removal and disposal of all materials. Special attention shall be exercised in the performance of all work on the membrane roof surface including any necessary protection to work areas and access routes.

3. The contractor shall be responsible for insuring the safety of all persons on or around the construction areas thru a designated Safety Person, including additional personnel when needed for life safety /traffic control when using any cranes and/or rigging equipment.

4. The Contractor shall be responsible for any damage to Government, building, and/or personal property damaged by any persons hired, employed, or contracted during the course of completing this work.

G. Finalization and Warranty

1. The Contractor shall provide a test of the hot water exchanger system on completion of the work detailed in this Scope. The start-up will be scheduled in advance and coordinated with all parties having a vested interest in this project.

2. The finalization and acceptance of this project shall include but not be limited to:

a. Testing all equipment installed by The Contractor.

b. Checking all mechanical connections.

c. Checking all wiring and electrical connections.

d. Checking and documenting voltages, temperatures, flow, and pressures.

e. Checking and adjusting the chemical water treatment for the hot water loop to 1000 ppm.

f. Submittal of all Manufacturers literature and specifications on the installed equipment.

g. Submittal of O & M manuals for all installed equipment with Model and Serial numbers.

h. Completion of all manufacturers’ check-list and completed warranty paperwork.

i. Correct any deficiencies and place equipment in service.

3. Unless a greater term is detailed in the above Scope, The Contractor shall provide a minimum of a one (1) year warranty on all parts, labor, material, and services provided on this project.

The warranty period shall begin on the date of written acceptance by the Government.

3. TASK MONITOR

The Task Monitor for this project will be identified at the time of award.