D.2 - VHA Specifications 000110.docx

DOCX document 66 KB Posted

Attached to
5450--AMA Mobile Range Federal contract opportunity
Solicitation number
36C25723Q1035
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

This document is a master specifications manual for the Department of Veterans Affairs containing technical specifications for various construction divisions and systems. It outlines specifications for general construction requirements, existing conditions, concrete, masonry, metals, woods and plastics, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, conveyances, fire suppression, plumbing, HVAC, integrated automation, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and transportation. The related federal contract opportunity is a solicitation from the VA Veterans Health Administration for mobile medical equipment. It includes the solicitation number, brief name, opportunity type as a solicitation, and contracting agency but provides no further detail on required products or services, pricing, response dates or other salient information.

View the file

Other files for this federal contract opportunity

Other files attached to 5450--AMA Mobile Range, newest first.
File Type Posted
36C25723Q1035 0002.docx DOCX document
B49 reference.pdf PDF
36C25723Q1035 0002_1.docx DOCX document
36C25723Q1035 0001.docx DOCX document
36C25723Q1035 0001_1.docx DOCX document
D.5 - Service Contract Act Wage Determination 2015-5213.pdf PDF
D.1 - General Requirements 010000.docx DOCX document
D.4 - Construction Wage Determination TX20220265.pdf PDF
D.3 - Range SOW_.docx DOCX document
36C25723Q1035 Solicitation.pdf PDF
36C25723Q1035_1.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

07-01-14 02-01-23

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO.
DIVISION AND SECTION TITLES
DATE

DIVISION 00 SPECIAL SECTIONS

00 01 15
List of Drawing Sheets
05-20

DIVISION 01 GENERAL REQUIREMENTS

01 00 00
General Requirements
11-21
01 32 16.15
Project Schedules (Small Projects – Design/Bid/Build
11-21
01 33 23
Shop Drawings, Product Data, and Samples
02-23
01 35 26
Safety Requirements
10-22
01 42 19
Reference Standards
11-20
01 45 00
Quality Control
02-21
01 45 29
Testing Laboratory Services
11-18
01 45 35
Special Inspections
06-21
01 57 19
Temporary Environmental Controls
01-21
01 58 16
Temporary Interior Signage
07-15
01 74 19
Construction Waste Management
04-22
01 81 13
Sustainable Construction Requirements
10-17
01 81 13.02
Sustainability Certification Requirements – LEED NC V4
01-21
01 81 13.21
Sustainability Certification Requirements – GREEN GLOBES
01-21
01 91 00
General Commissioning Requirements
04-22

DIVISION 02 – EXISTING CONDITIONS

02 21 13
Site Surveys
01-21
02 41 00
Demolition
08-17

DIVISION 03 – CONCRETE

03 23 00
Stressing Tendons
01-21
03 30 00
Cast-in-Place Concrete
01-21
03 30 53
(Short-Form) Cast-in-Place Concrete
01-21
03 37 13
Shotcrete
01-21
03 41 13
Precast Concrete Hollow Core Planks
01-21
03 41 33
Precast Structural Pretensioned Concrete
01-21
03 45 00
Precast Architectural Concrete
01-21
03 51 13
Cementitious Wood Fiber Decks
01-21
03 51 16
Gypsum Concrete Roof Decks
01-21
03 52 00
Lightweight Concrete Roof Insulation
01-21
03 55 11
Gypsum Concrete Floor Decks
01-21

DIVISION 04 – MASONRY

DIVISION 05 – METALS

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00
Rough Carpentry
10-17
06 16 63
Cementitious Sheathing
01-21
06 20 00
Finish Carpentry
01-21

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 01 50.19
Preparation for Re-Roofing
01-21
07 08 00
Facility Exterior Closure Commissioning
01-21
07 08 00.01
DVA/USACE Projects Facility Exterior Closure Commissioning
08-19
07 11 13
Bituminous Dampproofing
01-21
07 12 00
Built-Up Bituminous Waterproofing
01-21
07 13 00
Sheet Waterproofing
01-21
07 13 52
Modified Bituminous Sheet Waterproofing
01-21
07 14 21
Latex Mastic Deck Covering
01-21
07 18 13
Pedestrian Traffic Coatings
01-21
07 21 13
Thermal Insulation
01-21
07 21 23
Loose-Fill Insulation
01-21
07 22 00
Roof and Deck Insulation
01-21
07 24 00
Exterior Insulation and Finish Systems
01-21
07 27 26
Fluid-Applied Membrane Air Barrier, Vapor Permeable
01-21
07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Retarding
01-21
07 31 13
Asphalt Shingles
02-21
07 31 26
Slate Shingles
01-21
07 31 29.13
Wood Shingles
01-21
07 32 13
Clay Roof Tiles
01-21
07 40 00
Roofing and Siding Panels
01-21
07 51 00
Built-Up Bituminous Roofing
12-21
07 51 13.11
Hot-Applied Built-Up Asphalt Roofing
12-21
07 51 13.13
Cold-Applied Built-Up Asphalt Roofing
12-21
07 52 16.11
Cold Adhesive Styrene-Butadiene-Styrene Modified Bituminous Membrane Roofing
12-21
07 52 16.12
Hot-Mopped Styrene-Butadiene-Styrene Modified Bituminous Membrane Roofing
12-21
07 53 23
Ethylene-Propylene-Diene-Monomer Roofing
01-21
07 54 16
Ethylene Interpolymer (KEE) Roofing
01-21
07 54 19
Polyvinyl-Chloride (PVC) Roofing
12-18
07 54 23
Thermoplastic Polyolefin (TPO) Roofing
01-21
07 56 00
Fluid-Applied Roofing
01-21
07 57 13
Sprayed Polyurethane Foam Roofing
12-21
07 60 00
Flashing and Sheet Metal
01-21
07 61 16
Batten Seam Copper Roofing
01-21
07 71 00
Roof Specialties
01-21
07 72 00
Roof Accessories
01-21
07 81 00
Applied Fireproofing
10-17
07 84 00
Firestopping
01-21
07 92 00
Joint Sealants
04-22
07 95 13
Expansion Joint Cover Assemblies
01-21

DIVISION 08 OPENINGS

08 11 13
Hollow Metal Doors and Frames
01-21
08 11 73
Sliding Metal Fire Doors
01-21
08 14 00
Interior Wood Doors
01-21
08 17 10
Integrated Door Assemblies
01-21
08 31 13
Access Doors and Frames
04-22
08 32 13
ICU Sliding Glass Doors
01-21
08 33 00
Coiling Doors and Grilles
01-21
08 33 13
Coiling Counter Doors
01-21
08 34 53
Security Doors and Frames
01-21
08 34 59
Vault Doors and Day Gates
01-21
08 35 13.13
Accordion Folding Doors
01-21
08 36 13
Sectional Doors
01-21
08 38 16
Flexible Traffic Doors
01-21
08 41 13
Aluminum-Framed Entrances and Storefronts
01-21
08 42 33
Revolving Door Entrances
01-21
08 44 13
Glazed Aluminum Curtain Walls
04-20
08 51 13
Aluminum Windows
01-21
08 51 13.11
Side-Hinged Aluminum Windows
01-21
08 51 23
Steel Windows
01-21
08 51 69.11
Aluminum Storm Windows
01-21
08 56 19
Pass Windows
01-21
08 56 53
Blast Resistant Windows
01-21
08 56 59
Service and Teller Window Units
01-21
08 56 66
Detention Window Screens
01-21
08 63 00
Metal-Framed Skylights
01-21
08 71 00
Door Hardware
05-22
08 71 13
Automatic Door Operators
01-21
08 71 13.11
Low Energy Power Assist Door Operators
01-21
08 80 00
Glazing
01-21
08 90 00
Louvers and Vents
01-21

DIVISION 09 – FINISHES

DIVISION 10 – SPECIALTIES

DIVISION 11 – EQUIPMENT

11 05 12
General Motor Requirements for Equipment
01-21
11 12 00
Parking Control Equipment
01-21
11 17 36
Package Transfer Units
01-21

DIVISION 12 – FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41
Seismic Restraint Requirements for Non-Structural Components
01-21

DIVISION 14– CONVEYING EQUIPEMENT

DIVISION 21- FIRE SUPPRESSION

DIVISION 22 – PLUMBING

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 11
Common Work Results for HVAC
04-22
23 05 12
General Motor Requirements for HVAC and Steam Generation Equipment
02-20
23 08 00
Commissioning of HVAC Systems
04-22
23 09 23
Direct-Digital Control System for HVAC
09-11
23 31 00
HVAC Ducts and Casings
02-20
23 34 00
HVAC Fans
02-20
23 36 00
Air Terminal Units
02-20
23 37 00
Air Outlets and Inlets
02-20
23 40 00
HVAC Air Cleaning Devices
03-20
23 73 00
Indoor Central-Station Air-Handling Units
03-20
23 74 13
Packaged, Outdoor, Central-Station Air-Handling Units
03-20
23 81 23
Computer-Room Air-Conditioners
03-20
23 84 00
Humidity Control Equipment
03-20

DIVISION 25 – INTEGRATED AUTOMATION

25 10 10
Advanced Utility Metering System
02-10

DIVISION 26 – ELECTRICAL

26 05 11
Requirements for Electrical Installations
11-22
26 05 13
Medium-Voltage Cables
11-22
26 05 19
Low-Voltage Electrical Power Conductors and Cables
11-22
26 05 26
Grounding and Bonding for Electrical Systems
11-22
26 05 33
Raceway and Boxes for Electrical Systems
11-22
26 05 36
Wireways for Radiology Equipment
11-22
26 05 39
Underfloor Raceways for Electrical Systems
11-22
26 05 41
Underground Electrical Construction
11-22
26 05 73
Overcurrent Protective Device Coordination Study
11-22
26 08 00
Commissioning of Electrical Systems
11-22
26 08 00.01
DVA/USACE Projects Commissioning of Electrical Systems
08-19
26 09 23
Lighting Controls
11-22
26 11 16
Secondary Unit Substations
11-22
26 12 19
Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers
11-22
26 13 13
Medium-Voltage Circuit Breaker Switchgear
11-22
26 13 16
Medium-Voltage Fusible Interrupter Switches
11-22
26 20 11
Isolated Power Systems
11-22
26 22 00
Low-Voltage Transformers
11-22
26 23 00
Low-Voltage Switchgear
11-22
26 23 13
Generator Paralleling Controls
11-22
26 24 13
Distribution Switchboards
11-22
26 24 16
Panelboards
11-22
26 24 19
Motor Control Centers
11-22
26 25 11
Busways
11-22
26 26 00
Power Distribution Units for Static Uninterruptible Power Systems
11-22
26 27 26
Wiring Devices
11-22
26 29 11
Motor Controllers
11-22
26 29 21
Enclosed Switches and Circuit Breakers
11-22
26 32 13
Engine Generators
11-22
26 33 53
Static Uninterruptible Power Supply
11-22
26 35 26
Harmonic Filters
11-22
26 36 23
Automatic Transfer Switches
11-22
26 41 00
Facility Lightning Protection
11-22
26 42 00
Cathodic Protection
11-22
26 43 13
Surge Protective Devices
11-22
26 51 00
Interior Lighting
11-22
26 55 71
Medical and Surgical Lighting Fixtures
11-22
26 56 00
Exterior Lighting
11-22

DIVISION 27 – COMMUNICATIONS

27 05 11
Requirements for Communications Installations
09-19
27 05 26
Grounding and Bonding for Communications Systems
06-15
27 05 33
Raceways and Boxes for Communications Systems
10-18
27 05 61
Leased Space, Communication Equipment and Systems
06-15
27 08 00
Commissioning of Communications Systems
11-16
27 08 00.01
DVA/USACE Projects Commissioning of Communications Systems
08-19
27 10 00
Control, Communication and Signal Wiring
06-15
27 11 00
Communications Equipment Room Fittings
06-15
27 15 00
Communications Structured Cabling
01-16
27 31 00
Voice Communications Switching and Routing Equipment
06-15
27 31 31
Voice Communications Switching and Routing Equipment - Extension
06-15
27 32 41
Two-Way Radio Equipment and Systems
10-18
27 41 31
Master Antenna Television Equipment and Systems
06-15
27 51 16
Public Address and Mass Notification Systems
11-22
27 51 23
Intercommunications and Program Systems
06-15
27 52 23
Nurse Call and Code Blue Systems
10-18
27 52 41
Miscellaneous Medical Systems
06-15
27 53 19
Distributed Radio Antenna (Within Building) Equipment and System
10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00
Common Work Results for Electronic Safety and Security
04-18
28 05 13
Conductors and Cables for Electronic Safety and Security
10-18
28 05 26
Grounding and Bonding for Electronic Safety and Security
09-11
28 05 28.33
Conduits and Backboxes for Electronic Safety and Security
09-11
28 08 00
Commissioning of Electronic Safety and Security Systems
11-16
28 08 00.01
DVA/USACE Projects Commissioning of Electronic Safety and Security Systems
08-19
28 13 00
Physical Access Control System
10-11
28 13 16
Physical Access Control System and Database Management
09-11
28 13 53
Security Access Detection
09-11
28 16 00
Intrusion Detection System
10-11
28 23 00
Video Surveillance
09-11
28 26 00
Electronic Personal Protection System
09-11
28 31 00
Fire Detection and Alarm
10-11
28 52 31
Emergency Call System
06-15

DIVISION 31 – EARTHWORK

31 20 00
Earthwork
07-16
31 20 11
Earthwork (Short Form)
10-12
31 23 19
Dewatering
10-12
31 23 23.33
Flowable Fill
10-12
31 32 23
Pressure Grouting Soil Stabilization
10-12
31 62 00
Driven Piles
10-12
31 63 16
Auger Cast Grout Piles
10-12
31 63 26
Drilled Caissons
10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23
Cement and Concrete for Exterior Improvements
08-16
32 12 16
Asphalt Paving
09-15
32 17 23
Pavement Markings
08-16
32 31 13
Chain Link Fences and Gates
06-18
32 31 40
High Security Fences and Gates
08-16

DIVISION 33 – UTILITIES

33 08 00
Commissioning of Site Utility Systems
11-16
33 46 13
Foundation Drainage
10-11

DIVISION 34 – TRANSPORTATION

DIVISION 48 – Electrical Power Generation

00 01 10-1

File details come from the government source that posted it. Updated .