This document is a Contract Amendment Summary from the Arizona Department of Transportation (ADOT) for the construction of the Keams Canyon Truck Barn and Office Building. The primary contractor is AJ Roberts Industrial Inc., with DFDG Architecture serving as the design professional. The amendment is specific to the ADOT Keams Canyon project located in Keams Canyon, Arizona, with the contract number CTR073892.

The amendment introduces Change Order No. 1, which adds a line item to the contract with a total not to exceed $77,859.05, including taxes. The change order covers various construction-related activities, such as air compressor electrical work, installation of communication conduits, receptacle and data box installation, water line modifications, and site-specific concrete and excavation work. The original contract sum was $3,069,434.00, and this change order increases the contract sum to $3,147,293.05. The amendment also extends the number of calendar days for substantial completion by 60 days, moving the revised substantial completion date to January 31, 2026.

View the file

Other files

File Type Posted
CTR073892_Contract_Documents.pdf PDF
CTR073892_Contract_Amendment_Summary_Two__2_.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARIZONA DEPARTMENT OF TRANSPORTATION

1655 W. Jackson Street, MD 100P

Phoenix, AZ 85007

Contract Amendment Summary CONTRACTOR: AJ Roberts Industrial Inc. AMENDMENT NO.: One (1)

DESCRIPTION: Construction of ADOT Keams Canyon Truck Barn, Office Building

Rev. 03/2025

Pursuant to the Uniform Terms and Conditions, Section 5, Contract Changes, the above referenced contract is amended. Summary of changes is as follows:

1. The following line item has been added to the contract:

CTR073892-3 Change Order No. 1 including taxes – Total not to exceed $77,859.05 See attached Change Order Summary No. 1

2. All other terms, conditions and provisions of this contract remain unchanged.