This is a mandatory use contract issued by the Ohio Department of Administrative Services, General Services Division, Office of Procurement Services for response services related to hazardous materials and environmental incidents. The contract is awarded to Reworld Tron Corp. (previously Chemtron Corporation) with two identified subcontractors: Green Charge, Inc. and Superior Environmental Solutions, LLC. The contract number is CSP020829 and is effective from July 1, 2024 to June 30, 2027, with the primary beneficiary being the Ohio Environmental Protection Agency.

The contract covers two service categories: (1) Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants, and (2) Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants. The pricing structure includes detailed rate schedules for labor/personnel at four protection levels (A, B, C, D), equipment rental, materials, and disposal services. Labor rates range from $49 to $245 per hour depending on job role and protection level, with daily maximum rates. Equipment and material rates are comprehensive, covering items like vac trucks, emergency response trailers, protective gear, and various specialized environmental response equipment. The contract allows for a 7% markup on reimbursable expenses not listed in the cost summary, with prior agency authorization, and specifies that all costs are in U.S. dollars with no additional travel reimbursement.

View the file

Other files

File Type Posted
CSP020829_EPA003_A1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Index No.: EPA003

Eff. Date: 07/01/24

STATE OF OHIO

DEPARTMENT OF ADMINISTRATIVE SERVICES

GENERAL SERVICES DIVISION

OFFICE OF PROCUREMENT SERVICES

4200 SURFACE ROAD, COLUMBUS, OH 43228-1395

MANDATORY USE CONTRACT FOR: RESPONSE SERVICES TO ABATE HAZARDOUS MATERIALS, PETROLEUM AND OTHER POLLUTANTS (CATEGORY ONE) AND ENVIRONMENTAL RESPONSE TO INCIDENTS INVOLVING

HAZARDOUS MATERIALS, PETROLEUM OR OTHER POLLUTANTS (CATEGORY TWO)

CONTRACT NUMBER: CSP020829 EFFECTIVE DATES: 07/01/24 TO 06/30/27

The Department of Administrative Services has accepted Proposals submitted in response to Request for Proposal (RFP) No.

SRC0000016251 that opened on 03/29/24. The evaluation of the Proposal responses has been completed. The Offeror listed herein has been determined to be the highest ranking Offeror and has been awarded a Contract for the services listed. The respective Proposal response including, Contract Terms & Conditions, any Proposal amendment, special Contract Terms & Conditions, specifications, pricing schedules and any attachments incorporated by reference and accepted by DAS become a part of this Services Contract.

This Requirements Contract is effective beginning and ending on the dates noted above unless, prior to the expiration date, the Contract is renewed, terminated, or cancelled in accordance with the Contract Terms and Conditions.

This Requirements Contract is available to the Ohio Environmental Protection Agency as applicable.

The agency is eligible to make purchases of the contracted services in any amount and at any time as determined by the agency. The State makes no representation or guarantee that department will purchase the volume of services as advertised in the Request for Proposal.

This Requirements Contract and any Amendments thereto are available from the DAS Web site at the following address:

https://procure.ohio.gov/

Page No.: 2

COST SUMMARY FORMS

INSTRUCTIONS

All costs must be in U.S. Dollars. There will be no additional reimbursement for travel or other travel-related expenses.

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior authorization from the agency representative.

I. LABOR/PERSONNEL

A. The Labor/Personnel rates are billing rates for services under this Contract and are inclusive of (i.e., no separate charges will be made for) safety gear for any necessary level of protection.

B. Straight Time (ST) must consist of a standard eight (8) hour work day 40 hours per week Monday through Friday. Work performed outside ST on Monday through Friday and all work performed on Saturday is Overtime (OT) and is chargeable at Time-and-one half (1.5 X ST rate). Work performed on Sunday and National Legal Holidays is chargeable at Double Time (DT) (2.0 X ST rate). The Contractor must not have non-professional work beyond ST without prior verbal approval of OT by the EPA Contract Manager or designee.

C. No charge will be made for travel time or for personnel mileage charges. Travel expenses should be built into the Contractor(s) cost summary. There will be no additional reimbursement for travel or other related expenses.

D. No portion of equipment, personnel or subsistence allowance may be charged for that portion of a day during which the Contractor’s equipment is determined by the EPA Contract Manager or designee to be inoperable.

II. EQUIPMENT

A. The hourly rate must be charged for a piece of equipment during any one day of operation or use until the total charge equals the daily rate specified in the cost summary. The maximum charge for a piece of equipment in any one day of operation or use must be the daily rate specified in the cost summary.

B. All equipment operators must be fully licensed to operate equipment.

C. All equipment rates are inclusive of, and no separate charge will be made for, all auxiliary attachments and appurtenances (e.g., fittings, hoses, etc.).

D. No charges for equipment will be payable except when equipment is on location of a response action or, subject to provisions of this paragraph (Equipment), when the equipment is used for the transport of hazardous wastes or hazardous materials from such location to a hazardous waste disposal or storage facility. No charges will be made for the portion of a day during which equipment is inoperable due to mechanical failure.

E. The Contractor will be responsible for maintaining security of its equipment.

F. Rental of equipment not listed in the cost summary must be billed at the current supplier actual invoiced rate plus 10 percent, with prior approval from the EPA Contract Manager or designee.

Page No.: 3

III. MATERIAL

A. Materials not listed in the cost summary which are kept in stock by the Contractor must be billed to the

Ohio EPA at actual supplier invoiced rates plus 10 percent.

B. Ohio EPA and the Contractor hereby acknowledge that the prices of the materials and supplies set forth in the cost summary reflect the Contractor’s best estimates based on information available at the time of execution of this Contract.

IV. TRANSPORTATION

A. Off-loading: The Ohio EPA will compensate the Contractor for 1 hour off-loading charge at the treatment, storage or disposal; facilities at the hourly rate for labor and equipment as listed in cost summary I.) Labor/Personnel and II.) Equipment.

B. Loading: The Ohio EPA will compensate the Contractor for only the actual time spent loading a vehicle.

The rate of compensation will be the applicable labor and equipment rate as listed in the cost summary.

C. Vehicles in Transit

1. The Ohio EPA will compensate the Contractor, at the loaded mile rate referenced on the disposal transportation line item cost below, for full loads of petroleum, hazardous waste or hazardous material in the transit to treatment, storage or disposal facilities.

2. The Ohio EPA will compensate the Contractor for partial loads of petroleum, hazardous waste or hazardous material in transit to intrastate treatment, storage or disposal facilities within Ohio at the hourly rate for labor and equipment specified in the cost summary. The loaded mile rate will not be applicable to such transport.

3. The Ohio EPA will compensate the Contractor for partial loads of petroleum, hazardous waste or hazardous materials in transit to treatment, storage or disposal facilities outside Ohio at the lesser of the following charges: the applicable hourly rate for labor and equipment or the applicable loaded mile rate.

D. Mixed Shipments: In the event that petroleum, hazardous waste or hazardous materials from a response action under this Contract is shipped together with hazardous wastes or hazardous materials from other sources, the Ohio EPA will compensate the Contractor for a prorated portion of the transportation charge of its hazardous wastes or hazardous materials, in accordance with items IV.C1 through IV.C3 of this Attachment.

V. TREATMENT, DISPOSAL and STORAGE

A. Hazard Waste Treatment & Storage: Billings for all hazardous waste treatment or disposal must be completed with the prior verbal approval of the EPA Contract Manager or designee on a case-by-case basis, in accordance with Attachment One, Part Two of this Contract, and must be billed at the cost invoiced to the Contractor.

B. Charges for treatment or disposal will not be paid until actual treatment or disposal is confirmed by a manifest (invoice, receipt or other shipping document, if waste is non-hazardous) showing location and invoice showing cost of treatment or disposal.

C. Proper selection of treatment, storage and/or disposal location must be documented in response action Final Report as required by the Scope of Work.

VI. STORAGE

A. The rates for storage do not include costs to the Contractor for equipment in storage which will be compensated as described in the equipment rate schedule in the cost summary.

B. Entrance fees include normal unloading and warehousing labor. Repacking costs are additional per the labor and materials rates in the cost summary.

C. Containers smaller than thirty (30) gallons should be over-packed into fifty-five (55) gallon drums if reasonable.

D. The cost summary rates should reflect assorted types of hazardous wastes and TSD facility is permitted to store before full analytical work can be accomplished.

E. Contractor must provide a list of hazardous wastes that doesn’t need to be stored and can be disposed of at any time that the cost summary rates not will apply.

F. All other details (i.e., quantity, duration, non-permitted waste) must be addressed in the Site Safety Work Plan.

Page No.: 4

VII. LABORATORY ANALYTICAL METHODS AND COSTS

Applicable Documents: Latest versions of the following documents in whole or in parts as determined by OHIO EPA must apply within the scope of this Contract. Please submit a complete list of laboratory methods with associated costs using the general parameters listed below.

A. 40 CFR Part 136 Clean Water Act Analytical Methods and Part 261 Identification and Listing of

Hazardous Waste B. USEPA’s Test Methods for Evaluating Solid Waste, SW-846 C. USEPA’s Methods for Chemical Analysis of Water & Waste, EPA 600/4-79-020

VIII. IMPORTANT NOTES

The State of Ohio is exempt from federal excise and all Ohio state and local taxes. The State does not agree to pay any taxes on commodities or services acquired directly from any Contractor. However, the State may reimburse the Contractor for taxes incurred by a third party.

Brand names, trade names, manufacturer’s names, and/or catalog numbers, listed in the Cost Summary are used only for the purpose of description and to establish a base level of quality. Items considered to be of equal or better quality may be offered and/or used.

Eff. Date: 12/23/24* Page No.: 5

PRICE PAGE

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two) *Contract # CSP020829 *Contractor Name: Reworld Tron Corp.

LABOR/PERSONNEL RATES

LEVEL A PROTECTION CATEGORY ONE CATEGORY TWO

ITEM

UNIT OF

MEASUREMENT

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

RATE

PER

HOUR

MAXIMUM

RATE PER

DAY

Project Manager Hours $245 $6,120 $245 $6,120

Onsite Supervisor Hours $213 $5,112 $213 $5,112

Health & Safety Officer Hours $235 $5,640 $235 $5,640

Chemist Hours $245 $6,120 $245 $6,120

Foreman Hours $205 $4,920 $205 $4,920

Equipment Operator Hours $205 $4,920 $205 $4,920

Laborers Hours $175 $4,200 $175 $4,200

Truck Driver Hours $200 $4,800 $200 $4,800

Special Hazard Security Guard Hours $182 $4,368 $182 $4,368

Technicians Hours $188 $4,512 $188 $4,512

Other Management Hours $213 $6,120 $213 $6,120

Others / non-management Hours $180 $4,320 $180 $4,320

All costs must be in U.S. Dollars There will be no additional reimbursement for travel or other travel-related expenses.

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 6

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two)

LEVEL B PROTECTION CATEGORY ONE CATEGORY TWO

ITEM

UNIT OF

MEASUREMENT

RATE PER

HOUR

MAXIMUM

RATE

PER DAY

RATE PER

HOUR

MAXIMUM

RATE

PER DAY

Project Manager Hours $145 $3,480 $145 $3,480

Onsite Supervisor Hours $113 $2,712 $113 $2,712

Health & Safety Officer Hours $135 $3,240 $135 $3,240

Chemist Hours $145 $3,480 $145 $3.480

Foreman Hours $105 $2,520 $105 $2,520

Equipment Operator Hours $205 $4,920 $205 $4,920

Laborers Hours $75 $1,800 $75 $1,800

Truck Driver Hours $115 $2,760 $115 $2,760

Special Hazard Security Guard Hours $92 $2,208 $92 $2,208

Technicians Hours $98 $2,352 $98 $2,352

Other Management Hours $130 $3,120 $130 $3,120

Others / non-management Hours $75 $1,800 $75 $1,800

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 7

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two)

LEVEL C PROTECTION CATEGORY ONE CATEGORY TWO

ITEM

UNIT OF

MEASUREMENT

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

Project Manager Hours $120 $2,880 $120 $2,880

Onsite Supervisor Hours $88 $2,112 $88 $2,112

Health & Safety Officer Hours $110 $2,640 $110 $2,640

Chemist Hours $120 $2,880 $120 $2,880

Foreman Hours $80 $1,920 $80 $1,920

Equipment Operator Hours $80 $1,920 $80 $1,920

Laborers Hours $50 $1,200 $50 $1,200

Truck Driver Hours $75 $1,800 $75 $1,800

Special Hazard Security Guard Hours $67 $1,608 $67 $1,608

Technicians Hours $73 $1,752 $73 $1,752

Other Management Hours $105 $2,520 $105 $2,520

Others / non-management Hours $50 $1,200 $50 $1,200

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 8

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two)

LEVEL D PROTECTION CATEGORY ONE CATEGORY TWO

ITEM

UNIT OF

MEASUREMENT

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

Project Manager Hours $115 $2,760 $115 $2,760

Onsite Supervisor Hours $73 $1,752 $73 $1,752

Health & Safety Officer Hours $95 $2,280 $95 $2,280

Chemist Hours $115 $2,760 $115 $2,760

Foreman Hours $65 $1,560 $65 $1,560

Equipment Operator Hours $75 $1,800 $75 $1,800

Laborers Hours $49 $1,176 $49 $1,176

Truck Driver Hours $65 $1,560 $65 $1,560

Special Hazard Security Guard Hours $52 $1,248 $52 $1,248

Technicians Hours $58 $1,392 $58 $1,392

Other Management Hours $95 $2,280 $95 $2,280

Others / non-management Hours $55 $1,320 $55 $1,320

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior authorization from the agency representative.

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 9

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two)

EQUIPMENT CATEGORY ONE CATEGORY TWO

ITEM

UNIT OF

MEASUREMENT

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

Vac Truck Hours $145 $3,480 $145 $3,480

Vac Trailer Hours $165 $3,960 $165 $3,960

Box Truck Hours $65 $1,560 $65 $1,560

Emergency Response Trailer Days $75 $1,800 N/A $1,800

Emergency Response Trailer Hours $75 $1,800 $75 $1,800

Spill Response Boat Hours $40 $960 $40 $960

Stake Body Truck Hours $35 $840 $35 $840

Service Vehicle Hours $75 $1,800 $75 $1,800

Service Vehicle Days $75 $1,800 $75 $1,800

Backhoe / Excavator / Skid steer Hours $110 $2,640 $110 $2,640

Backhoe / Excavator Attachments Hours $65 $1,640 $65 $1,640

Excavator MOB / DEMOB Hours $100 $2,400 $100 $2,400

Skid steer MOB/DEMOB Hours $100 $2,400 $100 $2,400

Skid Steer Attachments Hours $50 $1,200 $50 $1,200

Frac Tank MOB / DEMOB and Berm Hours $100 $2,400 $100 $2,400

Frac Tank Days N/A $75 N/A $75

Submersible Pump Hours $36.25 $870 $36.25 $870

Submersible Pump Days N/A $870 N/A $870

High Pressure Wash Unit Hours $45 $1,080 $45 $1,080

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior authorization from the agency representative.

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 10

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two)

EQUIPMENT (Cont.) CATEGORY ONE CATEGORY TWO

ITEM

UNIT OF

MEASUREMENT

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

RATE PER

HOUR

MAXIMUM

RATE PER

DAY

Generator Hours $16 $384 $16 $384

Mercury / Drum Vac Hours $25 $600 $25 $600

Aeration Unit (for streams) Hours $10.80 $259.20 $10.80 $259.20

Air Compressor Hours $35 $840 $35 $840

Dump Truck Hours $135 $3,240 $135 $3,240

Roll-off Containers Hours $30 $30 $30 $30

Office Trailer Days $20 $480 $20 $480

High Volume Pump Hours $36.25 $870 $36.25 $870

Explosion Proof Fan (air) Hours $28.90 $693.60 $28.90 $693.60

Photo Ionizer Detector (PID) Hours $25.50 $612 $25.50 $612

Multiple Gas Meter (CO, H2S, CN, etc.) Hours $25.50 $612 $25.50 $612

Explosimeter/O2 Meter Hours $25.50 $612 $25.50 $612 pH Meter Hours $25.50 $612 $25.50 $612

Mercury Vapor Analyzer Hours $124.40 $2,980.80 $124.20 $2,980.80

Draeger Set (tube or chip) Hours $1.80 $43.20 $1.80 $43.20

Lighting System Hours $17.50 $420 $17.50 $420

Jack Hammer Hours $21.35 $512.40 $21.35 $512.40

Metal Detector Hours $36.90 $885.60 $36.90 $885.60

Leaf Blower Hours $75 $1,800 $75 $1,800

Weed Eater Hours $21.35 $512.40 $21.35 $512.40

Chainsaw Hours $21.35 $512.40 $21.35 $512.40

Intrinsically Safe Transfer Pump Hours $40 $960 $40 $960

AreaRae System and AreaRae Report Hour $40 $960 $40 $960

AreaRae System and AreaRae Report Days N/A $960 N/A $960

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior authorization from

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 11

RFP Title: Response Services to Abate Hazardous Materials, Petroleum and Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum or Other Pollutants (Category Two)

MATERIALS

CATEGORY

ONE

CATEGORY

TWO

ITEM SIZE

UNIT OF

MEASUREMENT

RATE PER

UNIT

RATE PER

UNIT

Absorbent Pads Bundle of 100 Lbs. 18"x18"x3/8" Each $ 62.50 *$ 62.50

Sorbent Boom 4 booms 10'x8" Each $ 157.50 $ 157.50

Containment Boom 4 booms 10'x5" Each $ 157.50 $ 157.50

Sorbent Pillows 10/Bale, 14” X 25” Each $ 105 $105

Sorbent Sweeps 1 Sweep, 19” X 100’ Each $ 100 $ 100

Dry Granular Absorbents Per 30lb Bag Each $ 38 $ 38 Instant Spill Absorber or equivalent 25 lb. bag Each $ 38 $ 38

Polyethylene Roll 8 mil thickness, 20’ X 100’ 1 roll Rolls $ 100 $ 100

Sodium Bicarbonate 50lb bag or pale Each $ 60 $ 60

17 H 1 Steel 55 Gallon Drum Each $ 55 $ 55

Overpack – Steel 1 Steel 85 Gallon Drum Each $ 175 $ 175

Overpack – Poly 1 Poly 85 Gallon Drum Each $ 180 $ 180

Rolloff Box Liners greater than 10 mil thickness Each $ 100 $ 100

Duct Tape 2” x 60 yards Rolls $ 20 $ 20

Nitrile Gloves *per set (pair) of gloves *Set *$ 1 *$ 1

Drum Liners Greater than 5 mil thickness Each $ 8 $ 8

Booties Disposable, pair, waterproof, chemical resistant Each $ 11 $ 11

Work Gloves *Leather Work Glove pair(set) *Set $ 6 $ 6 *Clarification with the award on the unit of measure and/or pricing.

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior authorization from

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 12

RFP Title : Response Services To Abate Hazardous Materials, Petroleum And Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum Or Other Pollutants (Category Two)

MATERIALS (Cont.)

ONE

CATEGORY

TWO

ITEM SIZE

UNIT OF

MEASUREMENT

RATE PER

UNIT

RATE PER

UNIT

Polyethylene Rolls 20’ X 100’ 1 roll Each $ 100 $ 100

Plastic Bags 55 Gallon or Larger, 3 mill or greater Each $ 6 $ 6

Cascade Air Supply System To refill SCBA bottles Each $ 960 $ 960

Air Purifying Respirator w/cartridges

Full face, multiple cartridges for organic vapors, mercury.

ammonia, Each $ 960 $ 960

SCBA - self-contained breathing apparatus Reusable (Per person/per day*) Each $ 1,200 $ 1,200 Tyvek / Saranex Suits or Equivalent Protective Clothing Each $ 50 $ 50

Level A Entry Suit Level A fully encapsulating Each $ 3,282 $ 3,282 Confined Space Entry Tripod/Harness Each $ 840 $ 840

Drum Thief’s (disposable - glass) Each $ 35 $ 35

Coliwasa (disposable - glass) 200 ml composite liquid waste sampler Each $ 20 $ 20

Work Gloves Mechanic Work Glove pair Each $ 6 $ 6 *Clarification with the award on the unit of measure and/or pricing.

All costs must be in U.S. Dollars There will be no additional reimbursement for travel or other travel-related expenses.

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior authorization from

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 13

RFP Title : Response Services To Abate Hazardous Materials, Petroleum And Other Pollutants (Category One) And Environmental Response to Incidents Involving Hazardous Materials, Petroleum Or Other Pollutants (Category Two)

DISPOSAL CATEGORY ONE

TWO

ITEM

UNIT OF

MEASUREMENT RATE PER UNIT

RATE PER

UNIT

Transportation (loaded rate) Miles $7 $7

Non-hazardous Materials Drum $72 $72

Non-hazardous Materials - Fuel & Water Gallon $1 $1

Drum Storage (per pound / per month*) Pound $0.15 $0.15

Paint Related Materials Drum $532 $532

Other Materials Disposals Drum $250 $250

Empty Drum Disposal Drum $15 $15

Waste Profiles Each $60 $60 *Clarification with the award on the unit of measure and/or pricing.

All costs must be in U.S. Dollars There will be no additional reimbursement for travel or other travel-related expenses.

Reimbursable expenses, not listed in the Cost Summary, are subject to a 7% mark up before tax, with prior

*Denotes Contractor name change to Reworld Tron Corp. and update to contract number with amendment 1.

Page No.: 14

CONTRACTOR INDEX

CONTRACTOR AND TERMS: CONTRACT NO.: CSP020829

OAKS ID # 56740

*Reworld Tron Corp. TERMS: Net 30 days

*HOU1149

*PO Box 650998

DALLAS, TX 75265-0998

CONTRACTOR’S CONTACT: Nickie Majjasie TELEPHONE: (440) 937-6845

DIRECT LINE: (440) 930-8539

MOBILE: (440) 653-3342

FAX: (440) 933-9500

*E-MAIL: nmajjasie@reworldwaste.com

PAYMENT ADDRESS:

OAKS ID #56740

*Reworld Tron Corp.

*HOU1149

*PO Box 650998

DALLAS, TX 75265-0998

SUBCONTRACTORS:

Green Charge, Inc.

Superior Environmental Solutions, LLC.

*Denotes Contractor name change to Reworld Tron Corp, address change and email change with amendment 1.

mailto:nmajjasie@reworldwaste.com

Eff. Date: 12/23/24 Page No.: 15

SUMMARY OF AMENDMENTS

Amendment

Number Revision

Date Description

1 12/23/24

This amendment is issued to update the contractor’s name from Chemtron Corporation to Reworld Tron Corp, update their address information and contact information.

Additionally, this amendment is issued to fix the contract number on the price pages and to repaginate.

CONTRACT FOR: RESPONSE SERVICES TO ABATE HAZARDOUS MATERIALS, PETROLEUM AND OTHER POLLUTANTS (CATEGORY ONE) AND ENVIRONMENTAL RESPONSE TO INCIDENTS INVOLVING HAZARDOUS MATERIALS, PETROLEUM OR OTHER POLLUTANTS (CATEGORY TWO)
SUMMARY OF AMENDMENTS

File details come from the government source that posted it. Updated .