Cole Grade Road Improvement Project - Phase 1.pdf

PDF 26 MB Posted

Attached to
Cole Grade Road Improvement Project - Phase 1
Solicitation number
131969
Issued by
San Diego County, San Diego City, California

About this file

This is a Request for Bid (RFB) document issued by the County of San Diego, Department of Public Works for the Cole Grade Road Improvement Project – Phase 1 (Oracle Project No. 1003046, RFB 13199). The project encompasses roadway construction, drainage improvements, bridge construction, traffic signal installation, irrigation and planting installation, utility work, and green street infrastructure construction in the vicinity of Valley Center in unincorporated San Diego County, California. The work includes demolition, clearing and grubbing, best management practices (BMPs) installation, signage, striping, decomposed granite path construction, fencing, gate construction, and temporary traffic control over a net length of 1.07 miles. The bid opening is scheduled for July 23, 2026 at 2:00 PM local time. The County's estimated project cost is $27,296,590.10 based on the total bid. The base bid schedule includes 190 line items covering field orders, resident engineer's office, traffic control systems, excavation work, structural concrete, drainage pipes, fencing, signage, and asphalt paving. Three additive alternates are included: Joint Utility Trench work, VCMWD Waterline Work, and SDG&E Transmission Electric Work. Prospective bidders must be prequalified by the County and possess a California Class A General Engineering Contractor's license. Questions regarding the solicitation must be submitted through BuyNet at least 10 days prior to bid opening.

Bid security of at least 10 percent of the bid amount is required in the form of cash, certified check, or bidder's bond. The successful bidder must provide a Performance Bond and Payment Bond each for 100 percent of the contract amount. The project is subject to California prevailing wage requirements under Labor Code Section 1720 et seq., and contractors must comply with the Working Families Ordinance regarding wage payment, skilled workforce utilization, and paid sick leave. The prime contractor must meet or exceed a 3 percent Small-Local Business Subcontractor Participation Requirement unless exempt, and must submit a Small-Local Business Utilization Plan (PC611 form). Contractors are required to register with the Department of Industrial Relations and comply with Labor Code Section 1771.4(a) regarding prevailing wage compliance monitoring. Additionally, contractors must comply with California Air Resources Board (CARB) In-Use Off-Road Diesel-Fueled Fleets regulations and submit appropriate fleet compliance certification. Subcontractors performing work exceeding one-half of one percent of the total bid must be designated at time of bid submittal with corrected license numbers provided within 24 hours of bid opening if needed. The contractor must perform at least 50 percent of the work with its own forces unless otherwise specified. Withdrawal of bids is prohibited for 75 days after the opening date, and the County reserves the right to reject any or all bids.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DOCUMENTS

FOR

COLE GRADE ROAD IMPROVEMENT PROJECT - PHASE 1

ORACLE PROJECT NO. 1003046

RFB 13199

BID OPENING DATE: July 23, 2026 – 2:00 PM, Local Time

Prime Contractor shall meet or exceed three-percent (3%) Small-Local Business Subcontractor Participation

Requirement.

COUNTY OF SAN DIEGO

DEPARTMENT OF PUBLIC WORKS

5510 OVERLAND AVENUE, SUITE 370

SAN DIEGO, CA 92123

COUNTY

SPECIAL NOTICES

Pre-Qualification: In accordance with Board of Supervisors Policy F-41, only those contractors that have been prequalified by the County are eligible to submit a bid in response to this RFB. The County’s list of prequalified contractors may be found at: https://www.sandiegocounty.gov/content/sdc/purchasing.html

Small-Local Business Subcontractor Participation Requirements: In accordance with Board of Supervisors Policy B-53 Small-Local Business Policy (SLBP), for public works projects the County has estimated to exceed $1 million in value:

i. The prime contractor shall meet or exceed three-percent (3%) Small-Local Business Subcontractor Participation Requirement if not exempt;

ii. Offeror or Contractor must submit a Small-Local Business Utilization Plan demonstrating that Offeror or Contractor: (i) will either meet or exceed a 3% Small-Local Business Subcontractor Participation Requirement or (ii) is exempt from the Small-Local Business Subcontractor Participation Requirements; and

iii. Offerors must use the Small-Local Business Utilization Plan (PC611) form, and if applicable the Small-Local Business Self-Certification Form (PC610), to comply with this requirement.

Forms are located at:

· Small-Local Business Utilization Plan (PC611):

https://www.sandiegocounty.gov/content/dam/sdc/purchasing/docs/PC611_dpc_SLB_Sub_Utilization.pdf

· Small-Local Business Self-Certification Form (PC610):

https://www.sandiegocounty.gov/content/dam/sdc/purchasing/docs/PC610_dpc_Small_Local_Self_Cert.pdf

Subcontractor Reporting Requirements: Subcontractor Reporting. Contractor shall provide periodic reports to the County of amounts paid under this Agreement to each Subcontractor, and whether each subcontractor qualifies as a Small-Local Business as defined in B-53 Small-Local Business Policy (SLBP). Such reports shall be submitted to the County using the “Subcontractor Data Collection Form (PC613)” located at https://www.sandiegocounty.gov/content/dam/sdc/purchasing/docs/PC613_dpc_Subcontractor_Data.xlsx or as otherwise directed by County. Reports shall be aligned with the County’s Fiscal Year, with a mid-year report of data through December 31 submitted by February 15th, and a full Fiscal Year report submitted by July 15.

Working Families Ordinance (WFO): Attention is directed to page 1-2a of the contract documents concerning the WFO. This page contains specific requirements for compliance with the WFO.

Vehicle Emissions Disclosure & Compliance Requirement: Attention is directed to Section 20 in PART 4-1 of the contract documents concerning compliance with California Air Resources Board (“CARB”) In-Use Off-Road Diesel- Fueled Fleets regulations in California Code of Regulations Title 13, Division 3. This section contains specific requirements for compliance with the CARB regulations.

Addenda and Interpretations: The Owner will not be responsible for any oral interpretation of the meaning of the plans, specifications, or other pre-bid documents. Offerors shall direct requests for explanation regarding the RFB or related documents to the Contracting Officer in writing as a question (“Question”). Questions should be submitted through BuyNet by sending a message to the Contracting Officer using the “Discussion” functionality. To be given consideration, questions must be received at least 10 days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be posted on the County BuyNet website at https://sdbuynet.sandiegocounty.gov. It is the responsibility of all prospective bidders to check the County BuyNet website for any updates to contract documents.

All addenda so issued shall become part of the Contract Documents.

Plan Holders List: All interested parties who would like to be placed on the plan holders list, please submit your information (company name, contact person, general or sub, address, phone and fax) in its entirety to the points of contact above on or before the due date for all RFIs. Plan holders lists will be posted on BuyNet labeled “plan holders list” as a courtesy and is not a requirement of this solicitation. The County of San Diego makes no representation as to the accuracy or for the completeness of the plan holders list.

CONTRACT DOCUMENTS

FOR

COLE GRADE ROAD IMPROVEMENT PROJECT - PHASE 1

ORACLE PROJECT NO. 1003046

The Contracting Officer for this solicitation is:

Cassandra Jackson-Grijalva, Procurement Specialist Department of Purchasing and Contracting Email: Cassandra.JacksonGrijalva@sdcounty.ca.gov

SUBMITTED BY:

ADOLFO CACHO, Senior Civil Engineer Department of Public Works

RECOMMENDED BY:

RYAN LAU, Project Manager Consultant to Department of Public Works

SAMIRA FARAHANI, Lead Project Manager Date Department of Public Works

CHRISTOPHER HANGER, LUEG Program Manager Date Department of Public Works

APPROVED BY:

4/26 COUNTY

Samira Farahani Digitally signed by Samira Farahani Date: 2026.05.19 06:01:18 -07'00'

Christopher.Hanger@sdcounty.

ca.gov

Digitally signed by Christopher.Hanger@sdcounty.ca.gov Date: 2026.05.20 20:47:14 -07'00'

SamirM.Nuhaily@sdcounty.ca.g Digitally signed by SamirM.Nuhaily@sdcounty.ca.gov

_ov____________________________________________Date: 2026.05.21 08:47:23 -07'00'___________________

SAMIR NUHAILY, Deputy Director of Public Works Date Department of Public Works

TABLE OF CONTENTS

PART 1 BIDDING INFORMATION ..................................................................................................... 1-1

NOTICE TO CONTRACTORS INVITING BIDS ........................................................................................ 1-2

INFORMATION FOR BIDDERS ............................................................................................................... 1-3

GENERAL INFORMATION REGARDING COMPLIANCE WITH SMALL-LOCAL BUSINESS

SUBCONTRACTOR PARTICIPATION REQUIREMENTS ....................................................................... 1-6

PART 2 DOCUMENTS TO BE EXECUTED BY BIDDER .................................................................. 2-1

PROPOSAL TO THE BOARD .................................................................................................................. 2-2

BID SCHEDULE ........................................................................................................................................ 2-3

BID COMPARISON AND AWARD ............................................................................................................ 2-4

PROHIBITED CONTRACTS ..................................................................................................................... 2-5

DRUG AND ALCOHOL POLICY .............................................................................................................. 2-5

DEBARMENT AND SUSPENSION ........................................................................................................... 2-5

NONCOLLUSION AFFIDAVIT .................................................................................................................. 2-6

FLEET COMPLIANCE CERTIFICATION ................................................................................................. 2-6

REPRESENTATIONS AND CERTIFICATIONS ...................................................................................... 2-6a

DESIGNATION OF SUBCONTRACTORS ............................................................................................... 2-7

SIGNATURE PAGE .................................................................................................................................. 2-8

BIDDER'S BOND ...................................................................................................................................... 2-9

SMALL-LOCAL BUSINESS SUBCONTRACTOR UTILIZATION PLAN ................................................ 2-10

PART 3 DOCUMENTS TO BE EXECUTED BY THE SUCCESSFUL BIDDER ................................ 3-1

CONTRACT .............................................................................................................................................. 3-2

CORPORATE CERTIFICATE ................................................................................................................... 3-5

PARTNERSHIP CERTIFICATE ................................................................................................................ 3-6

CONTRACTOR'S CERTIFICATE REGARDING WORKER'S COMPENSATION ................................... 3-7

PERFORMANCE BOND ........................................................................................................................... 3-8

PAYMENT BOND ..................................................................................................................................... 3-9

4/26 i COUNTY

TABLE OF CONTENTS (continued)

PART 4 SPECIAL PROVISIONS – GENERAL PROVISIONS

4-1 COUNTY OF SAN DIEGO SPECIAL CONDITIONS.................................................................... 4-1-3

4-2 COUNTY OF SAN DIEGO MODIFIED 2015 STANDARD SPECIFICATIONS DIVISION I......... 4-2-1

4-3 CALTRANS 2025 STANDARD SPECIFICATIONS DIGEST DIVISION II THROUGH XII .......... 4-3-1

PART 5 SPECIAL PROVISIONS - TECHNICAL PROVISIONS ........................................................ 5-1

PART 6 STANDARD DRAWINGS, STANDARD PLANS AND PROJECT PLANS .......................... 6-1

4/26 ii COUNTY

PART 1

BIDDING INFORMATION

4/26 1-1 PART 1/COUNTY

NOTICE TO CONTRACTORS INVITING BIDS

The County of San Diego, Owner, invites sealed bids for:

COLE GRADE ROAD IMPROVEMENT PROJECT - PHASE 1

ORACLE PROJECT NO. 1003046

RFB 13199

Bid Opening Date: July 23, 2026 - 2:00 PM, Local Time

Late submission cannot be considered unless there was mishandling on the part of the County of San Diego purchasing staff.

Duty to Inquire, Questions, and Explanation to Bidders: Bidders’ Inquiries and County Responses – All communications from the Bidder (including its employees, agents, and representatives) to the County or its officers and employees (including consultants working on or assisting with this procurement) related to this RFB must be directed in writing exclusively to the Contracting Officer, unless otherwise authorized in writing by the Contracting Officer. Any improper contact may, at County’s sole discretion, cause the Bidder to be removed from consideration for contract award.

Should a Bidder find discrepancies in or omissions from, or be in doubt as to the meaning of, the RFB or related documents, Bidder shall have a duty to at once notify the County. Such notifications, or other requests for explanation regarding the RFB or related documents, shall be directed to the Contracting Officer in writing as a question (“Question”). Questions should be submitted through BuyNet by sending a message to the Contracting Officer using the “Discussions” functionality. Bidder is responsible for ensuring that Questions are received by the County. The County may choose not to respond to Questions received after the date stated in the Cover Letter. Bidders should not communicate with or attempt to contact any other County personnel about this solicitation, except as otherwise allowed for in this RFB.

Bid Opening (Virtual): The County will conduct a public bid opening using the Microsoft Teams platform instead of in-person attendance.

Virtual bid opening link: DPC Bid Opening

You may also join by phone by calling 1-619-343-2539, access code ID #979 022 535

A bid abstract and the bids received will be posted on BuyNet after the bid opening.

Bid Submittal: Offeror must submit a complete original bid in accordance with the format provided in this solicitation to the County of San Diego, Department of Purchasing and Contracting through electronic upload to BuyNet, or via sealed envelope at the Purchasing and Contracting front desk, before the Date and Time listed in Schedule.

· Offerors are advised to review PART 2 of this RFB regarding acceptable formatting of documents and signatures.

· When submitting via BuyNet, Offeror should allow for sufficient time to submit by an alternate method in the event of technical difficulties.

· Offerors are advised to review the County’s COVID-19 Updates for County Contracts and Contractors, found at https://www.sandiegocounty.gov/content/sdc/purchasing/COVID- 19_Updates.html, for any guidance that may affect bid submission procedures.

· The County’s decision about the timeliness or responsiveness of any submitted document shall be final, and the County has the discretion to waive or not waive any defect or nonconformance.

Contractor’s License Requirements: The Contractor shall possess, at the time of submitting the bid, a California contractor's license, Class A, General Engineering Contractor.

4/26 1-2 PART 1/COUNTY

https://teams.microsoft.com/l/meetup-join/19%3ameeting_OWU0NWUzOGItYWZhMS00OTM5LTk2MTYtNjU2YzU5ZjNhYjUx%40thread.v2/0?context=%7b%22Tid%22%3a%224563af13-c029-41b3-b74c-965e8eec8f96%22%2c%22Oid%22%3a%2234b047f6-17e4-491a-a857-5c2ca53464d6%22%7d

Working Families Ordinance: The Contractor shall comply and shall ensure that its subcontractors at all levels comply, with the Working Families Ordinance set forth in Sections 73.10, et seq. of the San Diego County Administrative Code, which pertains to the payment of wages, utilization of a skilled and trained workforce, working conditions, and the provision of paid sick leave. The Contractor shall post the County’s Working Families Ordinance notice (available upon request and at https://www.sandiegocounty.gov/OLSE) in a conspicuous and accessible place in each location at which employees are employed, as required by the Working Families Ordinance. Contractor shall maintain records sufficient to document Contractor’s compliance with this section, including, if applicable, evidence of qualification for an exemption from the Working Families Ordinance, and shall provide such records to County upon request. Contractor hereby grants County permission to conduct an investigation regarding Contractor’s compliance with the Working Families Ordinance at any time, which investigation may include, but is not limited to, audit of documentation, inspection of the site of the work, and interviews of employees and/or workers.

Small-Local Business Subcontractor Participation Requirements: In accordance with Board of Supervisors Policy B-53 Small-Local Business Policy (SLBP), for public works projects the County has estimated to exceed $1 million in value:

i. The prime contractor shall meet or exceed three-percent (3%) Small-Local Business Subcontractor

Participation Requirement if not exempt;

ii. Offeror or Contractor must submit a Small-Local Business Utilization Plan demonstrating that Offeror or Contractor: (i) will either meet or exceed a 3% Small-Local Business Subcontractor Participation Requirement or (ii) is exempt from the Small-Local Business Subcontractor Participation Requirements; and

iii. Offerors must use the Small-Local Business Utilization Plan (PC611) form, and if applicable the Small-Local Business Self-Certification Form (PC610), to comply with this requirement.

Forms are located at:

· Small-Local Business Utilization Plan (PC611):

https://www.sandiegocounty.gov/content/dam/sdc/purchasing/docs/PC611_dpc_SLB_Sub_Utilization.pdf

· Small-Local Business Self-Certification Form (PC610):

https://www.sandiegocounty.gov/content/dam/sdc/purchasing/docs/PC610_dpc_Small_Local_Self_Cert.pdf

Subcontractor Reporting Requirements: Subcontractor Reporting. Contractor shall provide periodic reports to the County of amounts paid under this Agreement to each Subcontractor, and whether each subcontractor qualifies as a Small-Local Business as defined in B-53 Small-Local Business Policy (SLBP). Such reports shall be submitted to the County using the “Subcontractor Data Collection Form (PC613)” located at https://www.sandiegocounty.gov/content/dam/sdc/purchasing/docs/PC613_dpc_Subcontractor_Data.xlsx or as otherwise directed by County. Reports shall be aligned with the County’s Fiscal Year, with a mid-year report of data through December 31 submitted by February 15th, and a full Fiscal Year report submitted by July 15th.

County’s Estimated Cost: This public works project is $ 27,296,590.10 based on Total Bid.

4/26 1-2a PART 1/COUNTY

Engineer's Estimate of Work:

BASE BID SCHEDULE

Item No. Item Code Item Description Estimated Quantity 001 040000A Field Orders 100,000 DLR 002 051000A Resident Engineer's Office 500 DAY 003 070010A Trench Safety and Shoring of Excavations LS 004 080060 Level 2 Critical Path Method Schedule LS 005 090100 Time-Related Overhead 370 WDAY 006 090205 Dispute Resolution Board On-Site Meeting 8 EA 007 090210 Hourly Off-Site Dispute-Resolution-Board-Related Tasks 40 HR 008 100100 Develop Water Supply LS 009 120090 Construction Area Signs LS 010 120091A Project Identification Sign 2 EA 011 120100 Traffic Control System LS 012 120149 Temporary Pavement Marking (Paint) 660 SF 013 120159 Temporary Traffic Stripe (Paint) 56,045 LF 014 120202A Portable Signal System LS 015 120300 Temporary Pavement Marker 858 EA 016 128601 Temporary Signal System LS 017 128652 Portable Changeable Message Sign 2 EA 018 129000 Temporary Railing (Type K) 8,800 LF 019 129101A Temporary Alternative Crash Cushion 49 EA 020 129152 Temporary Radar Speed Feedback Sign System 2 EA 021 130100 Job Site Management LS 022 130110A Dewatering System LS 023 130301 Stormwater Pollution Prevention Plan LS 024 130310 Rain Event Action Plan 40 EA 025 130315A QSD Onsite Inspection 15 DAY 026 130505 Move-In/Move-Out (Temporary Erosion Control) 10 EA 027 130560 Temporary Soil Binder 3,000 SY 028 130570 Temporary Cover 1,000 SY 029 130620 Temporary Drainage Inlet Protection 39 EA 030 130640 Temporary Fiber Roll 15,300 LF 031 130651A Temporary Gravel Bag Berm 9,500 LF 032 130680 Temporary Silt Fence 6,510 LF 033 130710 Temporary Construction Entrance 7 EA 034 130900 Temporary Concrete Washout LS 035 131001A BMP Maintenance Cost Sharing 25,000 DLR 036 131103 Water Quality Sampling and Analysis Day 25 EA 037 130331 Stormwater Annual Report 4 EA 038 131201 Temporary Creek Diversion Systems LS 039 132000A BMP Maintenance Period 40 WDAY 040 160110 Temporary High-Visibility Fence 90 LF 041 170103 Clearing and Grubbing LS 042 190101 Roadway Excavation 17,676 CY 043 190161 Rock Excavation 3,620 CY 044 (F) 192003 Structure Excavation (Bridge) 1,250 CY 045 (F) 192032 Structure Excavation (Rock Slope Protection) 955 CY 046 (F) 193003 Structure Backfill (Bridge) 600 CY 047 200113 Rock Mulch 1,293 SF 048 200122 Weed Germination 11,559 SY 049 200123 Cultivation 2,705 SY 050 200210A Choker Layer 33 CY 051 200220A Reservoir Layer 62 CY 052 201102A Bioretention Soil Media 1,212 CY 053 201108A Impermeable Liner 3,027 SY 054 202004 Iron Sulfate 1,020 LB

4/26 1-2b PART 1/COUNTY

BASE BID SCHEDULE - Continued

Item No. Item Code Item Description Estimated Quantity 055 202006 Soil Amendment 5 CY 056 202031A Perform Agricultural Soils Test and Percolation Tests LS 057 202037 Organic Fertilizer 1,537 LB 058 202038 Packet Fertilizer 8,478 EA 059 204035 Plant Group A 3,909 EA 060 204039A Plant Furnished Oak (60" Box) 6 EA 061 204041A Plant Furnished Oak (5 Gal) 50 EA 062 204042A Plant Furnished Oak (D-4) 30 EA 063 204043A Plant Furnished Oak (24" Box) 21 EA 064 204099 Plant Establishment Work LS 065 205034 Decomposed Granite 58,568 SQFT 066 205035A Wood Mulch 215 CY 067 205062 Root Barrier 360 SF 068 206400 Check and Test Existing Irrigation Facilities LS 069 206559 Control and Neutral Conductors (Armor-Clad) LS 070 206562 1" Remote Control Valve 21 EA 071 206565 2" Remote Control Valve 1 EA 072 206922 Two-Wire Irrigation Controller 1 EA 073 206930A RCV Decoder 16 EA 074 206931A Flow Sensor Decoder 1 EA 075 206932A Low Voltage Wiring Grounding 20 LF 076 208440 Backflow Preventer Enclosure 1 EA 077 208442 Flow Sensor 1 EA 078 208445 Tree Well Sprinkler Assembly 103 EA 079 208446 Riser Sprinkler Assembly (Gear Driven) 456 EA 080 208561A Pull Box (Irrigation) 27 EA 081 208574 1 1/2" Gate Valve 50 EA 082 208588 3" Gate Valve 12 EA 083 (F) 208594 3/4" Plastic Pipe (Schedule 40) (Supply Line) 7,016 LF 084 (F) 208595 1" Plastic Pipe (Schedule 40) (Supply Line) 34 LF 085 (F) 208596 1 1/4" Plastic Pipe (Schedule 40) (Supply Line) 35 LF 086 (F) 208605A 1.5" Plastic Pipe (Class 315) (Supply Line) 100 LF 087 (F) 208605 2" Plastic Pipe (Class 315) (Supply Line) 565 LF 088 (F) 208607 3" Plastic Pipe (Class 315) (Supply Line) 5,936 LF 089 (F) 208612A 1 1/4" Plastic Pipe (Schedule 40) (Wire Conduit) 6,166 LF 090 (F) 208613A 3/4" Plastic Pipe-UVR On-Grade (Schedule 40) (Supply Line) 4,338 LF 091 (F) 208614A 1" Plastic Pipe-UVR On-Grade (Schedule 40) (Supply Line) 1,016 LF 092 208649 Quick Coupling Valve 30 EA 093 (F) 208691A 6" PVC Pipe Conduit (Sleeve) (Schedule 40) 985 LF 094 (F) 208693A 4" PVC Pipe Conduit (Sleeve) (Schedule 40) 55 LF 095 (F) 208694A 3" PVC Pipe Conduit (Sleeve) (Schedule 40) 900 LF 096 (F) 208695A 2" PVC Pipe Conduit (Sleeve) (Schedule 40) 180 LF 097 210252 Bonded Fiber Matrix 15,000 SQFT 098 210430 Hydroseed 95,000 SQFT 099 260203 Class 2 Aggregate Base 3,224 CY 100 390132 Hot Mix Asphalt (Type A) 3,462 TON 101 390136 Minor Hot Mix Asphalt 460 TON 102 390137 Rubberized Hot Mix Asphalt (Gap Graded) 2,393 TON 103 394073 Place Hot Mix Asphalt Dike (Type A) 3,583 LF 104 394076 Place Hot Mix Asphalt Dike (Type E) 15 LF 105 394090 Place Hot Mix Asphalt (Miscellaneous Area) 26 SY 106 398201A Cold Plane Asphalt Concrete Pavement 9,824 SY 107 490605 36" Cast-In-Drilled-Hole Concrete Piling 650 LF 108 490682A 36" Cast-In-Drilled-Hole Concrete Piling (Rock Socket) 400 LF 109 500001 Prestressing Cast-In-Place Concrete LS

4/26 1-2c PART 1/COUNTY

Item No. Item Code Item Description Estimated Quantity 110 (F) 510051 Structural Concrete, Bridge Footing 230 CY 111 (F) 510053 Structural Concrete, Bridge 431 CY 112 (F) 510054 Structural Concrete, Bridge (Polymer Fiber) 147 CY 113 510086 Structural Concrete, Approach Slab (Type N) 130 CY 114 510090 Structural Concrete, Box Culvert 72 CY 115 510092 Structural Concrete, Headwall 68 CY 116 510094 Structural Concrete, Drainage Inlet 79 CY 117 510502 Minor Concrete (Minor Structure) 240 CY 118 519100 Joint Seal, (MR 2") 141 LF 119 (F) 520102 Bar Reinforcing Steel (Bridge) 360,000 LB 120 (F) 520115 Bar Reinforcing Steel (Galvanized) 600 LB 121 568062 Pedestrian Barricade 1 EA 122 600091 Access Opening, Soffit 1 EA 123 650311 18" Reinforced Concrete Pipe (Class III) 711 LF 124 650316 24" Reinforced Concrete Pipe (Class III) 407 LF 125 650320 30" Reinforced Concrete Pipe (Class III) 87 LF 126 650411 18" Reinforced Concrete Pipe (Class IV) 209 LF 127 650416 24" Reinforced Concrete Pipe (Class IV) 248 LF 128 650424 36" Reinforced Concrete Pipe (Class IV) 245 LF 129 650432 48" Reinforced Concrete Pipe (Class IV) 469 LF 130 680905 8" Perforated Plastic Pipe Underdrain 2747 LF 131 680906A 8" Non-Perforated Plastic Pipe Underdrain 80 LF 132 707448A 24" Precast Concrete Cleanout 2 EA 133 720110 Small-Rock Slope Protection 43 CY 134 721420 Concrete (Ditch Lining) 82 CY 135 723030 Rock Slope Protection (1/2 T, Class VII, Method A) 435 CY 136 723050 Rock Slope Protection (1/4 T, Class V, Method B) 55 CY 137 723095 Rock Slope Protection (20 lb, Class I, Method B) 373 CY 138 723180 Concreted-Rock Slope Protection (60 lb, Class II, Method B) 88 CY 139 723190 Concreted-Rock Slope Protection (20 lb, Class I, Method B) 20 CY 140 729901A Articulated Concrete Block 1,904 SY 141 729011 Rock Slope Protection Fabric (Class 8) 1,265 SY 142 729902A Articulated Concrete Block (Concrete Anchors) 50 CY 143 729903A Articulated Concrete Block (Concrete Cutoff Walls) 75 CY 144 729904A Concrete Armor Unit 590 EA 145 731503 Minor Concrete (Curb) 159 LF 146 731504 Minor Concrete (Curb & Gutter) 18 CY 147 731512A Minor Concrete (Concrete Inlet Apron) 13 CY 148 731516 Minor Concrete (Driveway) 13 CY 149 731521 Minor Concrete (Sidewalk) 1 CY 150 731623 Minor Concrete (Curb Ramp) 32 CY 151 750501 Miscellaneous Metal (Bridge) 2,439 LB 152 782120 Relocate Mailbox 18 EA 153 800001 Fence (Type BW, Metal Post) 1,213 LF 154 800055A Rural Fence 898 LF 155 800060A Split Rail Wood Fence 63 LF 156 800065A Three-Rail Wood Fence 594 LF 157 800066A Three-Rail Wood Fence W/Wire Mesh 239 LF 158 800103 Temporary Fence (Type CL-6) 4,457 LF 159 800310 Chain Link Fence (Type CL-3.5) 385 LF 160 800360 Chain Link Fence (Type CL-6) 1,023 LF 161 800631 Chain Link Fence (Type CL-6, Vinyl-Clad) 1,414 LF 162 802510 5' Chain Link Gate (Type CL-6) 3 EA 163 802580 12' Chain Link Gate (Type CL-6) 1 EA

4/26 1-2d PART 1/COUNTY

Item No. Item Code Item Description Estimated Quantity 164 802601 14' Chain Link Gate (Type CL-6) 3 EA 165 802620 16' Chain Link Gate (Type CL-6) 1 EA 166 802640 18' Chain Link Gate (Type CL-6) 3 EA 167 803020 Remove Fence 4,514 LF 168 803100 Reconstruct Fence 47 LF 169 803115A Reconstruct Horse Corral 1 EA 170 803190 Relocate Gate 3 EA 171 810170 Delineator (Class 1) 12 EA 172 810230 Pavement Marker (Retroreflective) 600 EA 173 820750 Furnish Single Sheet Aluminum Sign (0.063"-Unframed) 285 SQFT 174 820840 Roadside Sign - One Post 42 EA 175 839521 Cable Railing 237 LF 176 839635A Actuated Crash Cushion System 2 EA 177 839719 Concrete Barrier (Type 732SW) 130 LF 178 839741 Concrete Barrier (Type 836) 90 LF 179 839742 Concrete Barrier (Type 836A) 40 LF 180 839752 Remove Guardrail 483 LF 181 840504 Thermoplastic Pavement Marking 2,600 SQFT 182 847194 Paint Traffic Stripe (2-Coat) 38,000 LF 183 846020 Remove Painted Traffic Stripe 9,500 LF 184 846025 Remove Painted Pavement Marking 654 SQFT 185 870136 Electric Service for Irrigation LS 186 872002 Temporary Signal System LS 187 872133 Modifying Signal and Lighting Systems LS 188 995100 Water Meter Charges LS 189 995200 Irrigation Water Service Charges LS 190 999990 Mobilization LS

ADDITIVE ALTERNATE 1 BID SCHEDULE (JOINT UTILITY TRENCH)

Item No. Item Code Item Description Estimated Quantity 001 Joint Utility Trench LS 002 SDG&E Utility Joint Trench (Materials) LS 003 SDG&E Utility Joint Trench (Retaining Walls) LS

ADDITIVE ALTERNATE 2 BID SCHEDULE (VCMWD WATERLINE WORK)

Item No. Item Code Item Description Estimated Quantity 001 Excavation Support System LS 002 Sawcut, Excavate and Dispose Existing Asphalt Concrete Pavement 4,500 SF 003 Abandon Existing Water Service 22 EA 004 Abandon Existing Fire Hydrant 3 EA 005 Abandon Existing Air Vac 5 EA 006 Water Main Connection per Detail A on Sheet 3 LS 007 Water Main Connection per Detail B on Sheet 3 LS 008 Water Main Connection per Detail C on Sheet 3 LS 009 Water Main Connection per Detail D on Sheet 3 LS 010 16-inch Diameter C900 PVC (CL305), North and South of Bridge 170 LF 011 16-inch Diameter C900 PVC (CL305) at Storm Drain Crossing 6 EA 012 16-inch Diameter C900 Fusible Pipe 100 LF 013 16-inch Flex Tend 2 EA 014 Pre-Cast Vault and Concrete Wedge 2 EA 015 1-inch Water Service, W-3 11 EA

4/26 1-2e PART 1/COUNTY

ADDITIVE ALTERNATE 2 BID SCHEDULE (VCMWD WATERLINE WORK) – Continued

Item No. Item Code Item Description Estimated Quantity 016 1-inch Water Service, W-3A 1 EA 017 1.5-inch Water Service, W-4 1 EA 018 2-inch Water Service, W-4 1 EA 019 2-inch Water Service Manifold, W-6 1 EA 020 3-inch Water Service Manifold, W-6 1 EA 021 16-inch Butterfly Valve 2 EA 022 2-inch Air Vacuum Assembly 6 EA 023 6-inch Fire Hydrant 4 EA 024 Temporary Water Main LS 025 Rock Allowance LS 026 Unanticipated Obstructions 20 EA

ADDITIVE ALTERNATE 3 BID SCHEDULE (SDG&E TRANSMISSION ELECTRIC WORK)

Item No. Item Code Item Description Estimated Quantity 001 SDG&E Transmission Electric Work LS

Work to be Done: Consists in general of roadway construction, drainage improvements, bridge construction, traffic signal installation, irrigation and planting installation, utility work, and green street infrastructure construction. The project will also include but not limited to installing best management practices (BMPs), demolition, clearing and grubbing, signage and striping, decomposed granite path construction, fencing and gate construction, and temporary traffic control.

Location: The project is Countywide, in the vicinity of Valley Center in the unincorporated areas of the County of San Diego, State of California.

Contract Documents: Including Plans, Specifications, and Proposal Forms are available to be downloaded, free of charge, from the Department of Purchasing and Contracting BuyNet website at:

https://sdbuynet.sandiegocounty.gov

Full-size plans for this project are not available for purchase.

Work schedules and supplemental drawings, if applicable for this project, are included in Part 6 of these Contract Documents.

4/26 1-2f PART 1/COUNTY

The following reports are available for review at and may be downloaded from the County of San Diego BuyNet website at https://sdbuynet.sandiegocounty.gov. These reports are provided for informational purposes only and is not part of this Contract.

Name of Report Preparer Date

1-STA 135+82 and 138+87 Structures Record Drawings County of San Diego 1962 and 2009

2-RWQCB Draft NOI Memo Ninyo and Moore 5/7/2026 3-Geotechnical Evaluation Ninyo and Moore 10/2/2012 4-Supplemental Geotechnical Evaluation Ninyo and Moore 6/12/2014 5-Foundation Report Keyes Creek Tributary Crossing Ninyo and Moore 5/8/2015 6-Geotechnical Design Report Keyes Creek Tributary Crossing Ninyo and Moore 5/8/2015 7-Hydraulic Analysis for Cole Grade Road Crossings Chang Consultants 10/3/2022 8-Additional Hydraulic Analyses for Cole Grade Road Crossings Chang Consultants 12/3/2020 9-Groundwater Dewatering Study Ninyo and Moore 6/21/2023 10-Groundwater Resources Investigation Report Ninyo and Moore 6/21/2023 11-Addendum to Foundation Report Ninyo and Moore 3/14/2022 12-Geotechnical Data Report WSP USA 11/18/2024 13-Draft Geotechnical Report WSP USA 8/16/2024 14-Final Dewatering Mitigation Plan Geosyntec 10/27/2025 15-AT&T Temporary Pole Relocation Plans AT&T 4/15/2025 16-Mediacom Temporary Pole Relocation Plans Mediacom 7/11/2024 17-SDG&E Transmission TL 6926 Permanent UG Electric Relocation SDG&E 1/31/2024 18-SDG&E Transmission TL 683 Permanent OH Pole Relocation SDG&E 5/5/2023 19-SDG&E Distribution Temporary OH and UG Relocations Plans SDG&E 7/9/2025 20-SDG&E Transmission TL 6926 Permanent UG Electric Relocation Jack and Bore Asbuilt SDG&E 1/1/2023

A package of existing cross sections (31 sheets) used in the design of this project is available for review at and may be downloaded from the County of San Diego BuyNet website at https://sdbuynet.sandiegocounty.gov. These cross sections are provided for informational purposes only, and are not part of this Contract.

4/26 1-2g PART 1/COUNTY

Firms Associated with Project: The County of San Diego engaged the following Architect-Engineering firm with its subcontractors, or other firms to provide the Plans, Specifications, and Engineers Estimate (PS&E) and other related supporting technical documents or services for this construction procurement.

Firm Contact Name Type of Work Parsons Transportation Group Inc. Daniel Kachi Roadway Design Nasland Engineering Jarrett Linn Storm Drain Design and Drainage Study Geoysntec Consultants James Gonzales Dewatering Mitigation Ninyo & Moore Stephan Beck Geotechnical and Dewatering Studies SKS Engineering, Inc. Samson Engeda Bridge Design Chang Consultants Wayne Chang Hydraulics Study

The firms listed above have been associated with this project and are provided for informational purposes only. This list is not intended to be relied on for purposes of compliance with any conflict of interest rules or applicable laws or regulations affecting this project. The Contractor is solely responsible for due diligence in identifying and avoiding all potential conflicts of interest related to contracting for, and construction of, this project.

Standard Specifications: The Standard Specifications of the State of California, Department of Transportation, dated 2015 for Division I and dated 2025 all remaining Divisions.

The State Department of Transportation publication "Labor Surcharge and Equipment Rental Rates" in effect the date the work is accomplished, is incorporated by reference into these Contract Documents.

Bid Security: In the form of cash, or a certified or cashier's check, or a Bidder's Bond for at least ten percent of the bid amount executed by a company duly authorized to issue bonds in the State of California and certified by the U.S. Department of the Treasury shall accompany the bid.

Performance and Payment Bonds: The successful bidder will be required to furnish a Performance Bond for one hundred percent, and a Payment Bond for one hundred percent of the Contract amount executed by a company duly authorized to issue bonds in the State of California and certified by the U.S. Department of the Treasury.

State Prevailing Wage Rates: This project is a "public work" in accordance with Labor Code § 1720, et seq.

It is the sole responsibility of the Contractor to ensure that all workers employed in the execution of the contract are paid the correct prevailing wage rate of wages.

The Owner has obtained from the Director of the Department of Industrial Relations said Director's General Prevailing Wage Determinations for the locality in which the work is to be performed. Said determinations are on file and available for review at the Department of Purchasing and Contracting, 5560 Overland Avenue, Suite 270, San Diego, California 92123-1204 and are available from the Department of Industrial Relations at:

http://www.dir.ca.gov/DLSR/PWD

Not less than these rates shall be paid to all workers employed on the project.

Federal regulations and reporting requirements applicable to the proposed work must be complied with for this project.

AB 219 Notice: Adds Labor Code Section 1720.9. Ready-mix haulers and entities that deliver ready-mixed concrete to public works projects are considered subcontractors under Labor Code Section 1722.1 and must register as specified in Labor Code Section 1725.5.

4/26 1-2h PART 1/COUNTY

SB 854 Notice: County public works projects are subject to compliance monitoring and enforcement by the Department of Industrial Relations (DIR) in accordance with Labor Code Section 1771.4(a)(1). As part of this program, Contractors and Subcontractors on Public Works Projects are required to be registered with DIR in accordance with Labor Code Section 1725.5. Unregistered contractors are not qualified to bid on, be listed in a bid proposal, listed as a Subcontractor, or engage in the performance of any Public Works Contract, all as more particularly described in Labor Code Section 1771.1(a). The prime Contractor shall be required to post the job site with all notices required by regulations per Labor Code Section 1771.4(a)(2), whether or not the County also posts.

Labor Code Compliance: Contractor shall comply with the provisions of the Labor Code requiring the payment of prevailing wages on public works, commencing with Section 1720. In accordance with Labor Code, Section 1775, the Contractor shall forfeit an amount, as determined by the Labor Commissioner, for each worker paid less than the applicable prevailing wage rate for the work or craft in which that worker is employed for any work done under Contract by Contractor or by any Subcontractor. Contractor agrees to pay the difference between the prevailing wage rate and amount paid to each worker in accordance with Labor Code, Section 1775 (a)(2)(E).

Pursuant to Labor Code, Section 1770, the Director of the Department of Industrial Relations has ascertained the general prevailing rate of per diem wages and a general prevailing rate for legal holiday and overtime work for each craft required for execution of the Contract.

In accordance with Labor Code, Section 1773.2, copies of the prevailing rate of per diem wages are on file and can be viewed during normal business hours at the County Department of Purchasing and Contracting, located at 5560 Overland Avenue, Suite 270, San Diego, CA 92123-1294. Contractor shall post a copy of the applicable prevailing wage rates at the job site.

Wage rates set forth are the minimum that may be paid by the Contractor. Nothing herein shall be construed as preventing the Contractor from paying more than the minimum rates set. No extra compensation whatsoever will be allowed by the County due to the inability of the Contractor to hire labor at minimum rates, nor for necessity for payment by the Contractor of subsistence, travel time, overtime, or other added compensations, all of which possibilities are elements to be considered and ascertained to the Contractor’s own satisfaction in preparing its Proposal.

If it becomes necessary to employ crafts other than those listed in the General Prevailing Wage Rate, the Contractor shall obtain a wage rate determination. The rates thus determined shall be applicable as minimum from the time of initial employment. The Contractor shall be responsible for paying the applicable rate.

The Contractor and each Subcontractor shall keep and make available accurate payroll record in accordance with Labor Code, Section 1771.4(a)(3) and Section 1776. The record shall contain the names, addresses, social security numbers, work classifications, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by the Contractor and/or Subcontractor in connection with the Work. Payroll records shall be certified and shall be on forms provided by the Division of Labor Standards Enforcement, or shall contain the same information as those forms. A copy of all payrolls shall be submitted weekly to the Engineer in accordance with Section 7-1.01A(3) “Payroll Records” of the Standard Specifications. The Contractor’s and Subcontractor's certified payroll records shall be available for inspection at the principal office of the Contractor, or at the job site should the principal office be located outside of San Diego County.

Nothing in this section shall limit or modify Contractor’s obligations to comply with the Working Families Ordinance as set forth above.

Apprentices: The Contractor and each Subcontractor shall comply with the requirements of Labor Code, Section 1777.5, and any related regulations regarding the employment of registered apprentices. Properly registered apprentices shall be employed in the execution of the Work at the ratios required, but in no case shall the ratio be less than one hour of apprentice work for every five hours of journeyman work. Every apprentice shall be paid the standard wage paid to apprentices under the regulations of the craft or trade at which the apprentice is employed, and shall be employed only at the work of the craft or trade to which the apprentice is registered. The Contractor shall be responsible for compliance to Labor Code, Section 1777.5 for all apprenticeable occupations. More information available at:

http://www.dir.ca.gov/DAS/DASApprenticesOnPublicWorksSummaryOfRequirements.htm

4/26 1-2i PART 1/COUNTY

Contractors Licensing Laws: Attention is directed to the Contractors State License Law, Section 7000 and following of the Business and Professions Code concerning the licensing of contractors. Any bidder or contractor not properly licensed may be subject to the penalties provided and will not be considered for award of this Contract. Contractors are required by law to be licensed and are regulated by the Contractors State License Board. Any questions concerning a contractor may be referred to the Registrar, Contractors State License Board, 9821 Business Park Drive, Sacramento, CA, 95827. Contractors are required to be properly licensed in California on the date bids are submitted (Bus. & Prof. Code, § 7028.15), unless federal funds are involved. If federal funds are involved, the bidder shall be properly licensed in California at the time the contract is awarded (Pub. Contract Code, § 20103.5). In this case, failure of the bidder to obtain proper and adequate licensing for an award of this Contract shall constitute a failure to execute the Contract and shall result in the forfeiture of the security of the bidder.

Bid Submittal Envelope: Each Bid must be submitted in a sealed envelope bearing on the outside the name of the bidder, the bidder’s address, the name of the project for which the bid is submitted, and the appropriate State Contractor's License designation held by the bidder. If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed to:

County of San Diego, Department of Purchasing and Contracting

RFB 13199 – COLE GRADE ROAD IMPROVEMENT PROJECT - PHASE 1

5560 Overland Avenue, Suite 270 San Diego, CA 92123-1294

It is the responsibility of the bidder to ensure the bid is properly received at the identified date and time and designated location.

The Board reserves the right to reject any or all bids and to waive any informality or irregularity in the bids or bidding.

Withdrawal of bids shall not be permitted for a period of 75 days after the date set for the opening thereof.

Monies withheld by the Owner to ensure performance under the Contract may be released in accordance with Public Contract Code Section 22300 and these Contract Documents.

Electrician Certification and Labor Compliance: It is the sole responsibility of the contractor, if applicable, to ensure compliance with CA Labor Code 108-108.5 regarding electrician certification requirements. All General Electricians and Fire/Life Safety Technicians in the employ of C-10 contractors must be certified in order to perform electrical work in CA. Information on the electrician certification program may be obtained at the Division of Labor Standards Enforcement (DLSE) at:

https://www.dir.ca.gov/dlse/ecu/ElectricalTrade.html

Preliminary Notices and Stop Notices: Preliminary (Public Work) Notices and Stop Notices shall be filed, if applicable, in accordance with California Civil Code Section 8200 and 8044. For the Department of Public Works construction contracts notices shall be delivered to:

County of San Diego Operations Center Department of Public Works Construction Engineering, MS 0384 5510 Overland Avenue, Suite 370 San Diego, CA 92123-1248

Air Pollution Compliance: The Contractor shall be in compliance with all federal, state, and local laws and regulations applicable to the Contractor.

4/26 1-2j PART 1/COUNTY

INFORMATION FOR BIDDERS

The prospective bidder shall prepare the Proposal and Bond as provided therein, and failure to do so may be cause for rejection.

PREPARATION OF PROPOSAL FORMS

Preparation: The Owner invites proposals, on the forms posted on the Department of Purchasing and Contracting's BuyNet website under "Contract Documents,” and the links to forms located herein to be submitted on or before the time and place set for the opening of bids in the published "Notice to Contractors Inviting Bids.” Proposals not presented on forms so furnished will be disregarded. All downloaded and printed forms must be consistent and conform to the Department of Purchasing and Contracting official posted documents.

These Contract Documents on the Department of Purchasing and Contracting BuyNet website contain the Proposal forms (PART 2 – Documents to be Executed by Bidder), together with the Notice to Contractors, Contract and Special Provisions. PART 2 – Documents to be Executed by Bidder of these Contract Documents shall be returned in a sealed envelope bearing on the outside the name of the bidder, bidder’s address, the name of the project for which the bid is submitted, and the appropriate State Contractor’s License designation held by the bidder.

The Proposal must be executed in accordance with the instructions contained on the forms provided. If the bidder is an individual or a partner, the signature on the Proposal and the Bidder's Bond must be the same as the name of the bidder shown on other parts of these forms (showing the name as "J. E. Doe" and the signature as "John E. Doe" may be considered as an irregularity).

Modifications on the Submitted Proposal: Modifications, changes or additions to the Proposal may be considered an irregularity. Erasures or corrections in preparing the bids must be initialed by the person(s) signing the Proposal. Alternate proposals will not be considered unless called for.

Competency of Bidders: No award will be made to a Contractor who, in accordance with Chapter 9, Division 3, Business and Professions Code, is not properly licensed to do the described work.

Prospective bidders may be required to file with the Owner answers to questions contained in a questionnaire and a financial statement including a complete statement of their financial ability and experience in performing previous public works of a similar nature.

DOCUMENTS SUPPLEMENTING THE PROPOSAL

Bid Security: Each bid shall be accompanied by cash, a certified or cashier's check, or a bidder's bond executed by a corporation duly authorized to issue bonds in the State of California. Cash, check or bond shall be in the amount of not less than 10 percent of the maximum amount of the bid. Check or bond shall be made payable to the order of the Owner designated in the Notice to Contractors Inviting Bids. Said cash, check or bond shall be given as a guarantee that the bidder will, within the period specified after being requested to do so by the Owner, enter into a contract and provide the required bonds if awarded the work; if the bidder to whom the work has been awarded and to whom the request has been made refuses or fails to enter into said contract and provide the required bonds within the specified time, the cash or check shall be forfeited to the Owner or the principal and surety on the bond shall be liable to the Owner for the principal amount thereof in accordance with its terms. If the lowest responsible bid is not accepted by the Owner within the period specified following the date set for the opening of bids, or for such further period of time as may be agreed upon in writing between the Owner and the bidder concerned, or if the bidder to whom the contract is awarded executes and delivers to the Owner the required Contract Documents, the amount of the cash or certified or cashier's check will be returned to the bidder. Attention is directed to the requirement noted on the contract bonds that the Attorney-in-Fact shall attach a certified copy of the Power of Attorney.

4/26 1-3 PART 1/COUNTY

Designation of Subcontractor: The Business Name and Address, the Portion of Work, and License Number that will be done by each subcontractor are required at the time of bid submittal. An inadvertent error in listing the California contractor license number must be corrected by the prime contractor within 24 hours after bid opening by email to the Procurement Contracting Officer listed as contact for this RFB, provided the corrected contractor’s license number corresponds to the submitted name and location for that subcontractor, or else the bid may be determined non-responsive. The remainder of the information shall be submitted by all bidders within two business days of bid opening by e-mail to said Procurement Contracting Officer. If no subcontractors are to be designated, enter the word “NONE.”

The attention of the bidder is directed to Section 8-1.01, "Subcontracting,” of the Standard Specifications which requires the Contractor to perform with its own forces contracting work amounting to at least 50% of the total contract price, unless said percentage is changed in the Special Provisions of these Contract Documents.

AMENDMENTS AND INTERPRETATION OF CONTRACT UNIT

Addenda and Interpretations: The Owner will not be responsible for any oral interpretation of the meaning of the plans, specifications, or other pre-bid documents. Offerors shall direct requests for explanation regarding the RFB or related documents to the Contracting Officer in writing as a question (“Question”).

Questions should be submitted through BuyNet by sending a message to the Contracting Officer using the “Discussion” functionality. To be given consideration, questions must be received at least 10 days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be posted on the County BuyNet website at https://sdbuynet.sandiegocounty.gov. It is the responsibility of all prospective bidders to check the County BuyNet website for any updates to contract documents. All addenda so issued shall become part of the Contract Documents.

Interpretation of Estimated Quantities: An estimate of quantities of work to be done and materials to be furnished under these specifications is given in the Proposal, Special Provisions, or shown on the construction plans. It is given only as a basis for comparison of proposals and the award of the contract. The Owner does not expressly or by implication guarantee that the actual quantities involved will correspond exactly therewith. Payment to the Contractor will be made only for the actual quantities of work performed or materials furnished in accordance with the plans and specifications.

Rejection of Proposals: The Owner reserves the right to reject any or all proposals and the right to waive technicalities if such waiver is in its best interest and conforms to local laws and ordinances pertaining to the letting of construction contracts. Bids in which the prices are obviously unbalanced may be rejected.

AWARD AND EXECUTION OF THE CONTRACT

Notice of Intent: For…

This is the start of the file's text. The full file is on GovTribe.