This document is a Notice to Proceed with Construction issued by the Florida Wildlife Commission (FWC) on June 6, 2025, for the Hilochee Hydrologic Restoration Project, specifically Phases III, IV, and V, with the project number 7207.014. The contract is addressed to Allie and managed by Michael Cottingham, the FWC Contract Manager.

The Notice to Proceed authorizes construction mobilization with a project start date of June 10, 2025. The project timeline includes a Substantial Completion date of November 7, 2025 (150 calendar days after the Notice to Proceed) and a Final Completion date of November 22, 2025 (15 calendar days after substantial completion). While specific contract details such as pricing, option periods, or total contract value are not included in this document, it serves as an official authorization to begin work on the hydrologic restoration project, subject to the conditions outlined in the contract documents.

View the file

Other files

File Type Posted
CN-770000-24287.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notice to Proceed with Construction

June 6, 2025

RE: Notice to Proceed with Construction FWC 24287 Hilochee Hydrologic Restoration Phase III, IV, V - 7207.014

Dear Allie, Please consider this as your formal NOTICE TO PROCEED WITH CONSTRUCTION. You may now mobilize on site and proceed with construction subject to the conditions of the contract.

The official commencement date for this project will be the date of this Notice to Proceed (NTP) and subsequent Substantial Completion and Final Completion dates will be as established in the contract documents.

Notice to Proceed - 06/10/2025 Substantial Completion - 150 calendar days after NTP 11/07/2025 Final Completion - 15 calendar days after substantial 11/22/2025

Contract Manager for FWC will be Michael Cottingham

Sincerely, Michael Cottingham, FWC Contract Manager

Notice to Proceed - 06/10/2025