This document is a Notice to Proceed (NTP) issued by the Florida Wildlife Commission (FWC) to Southeastern Marine Group, located in Vero Beach, FL, for the Three Lakes – Sunset Ranch Boardwalk Project. The project is identified by FWC Purchase Order No. 24261 and has a project number of 7334.017. Michael Cottingham is designated as the Contract Manager for FWC, and the document authorizes the contractor to mobilize on site and commence construction as of April 28, 2025.

The contract establishes specific project timelines, with a Notice to Proceed date of 04/28/2025, Substantial Completion set for 90 days from the NTP (07/28/2025), and Final Completion scheduled for 15 calendar days after substantial completion (08/12/2025). The document provides formal authorization for Southeastern Marine Group to begin construction work on the boardwalk project, subject to the conditions outlined in the contract documents. The project appears to be a marine infrastructure development, with precise completion milestones and oversight by the FWC contract management team.

View the file

Other files

File Type Posted
CN-770000-24261.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notice to Proceed with Construction

April 28, 2025

Reggy King Southeastern Marine Group 4495 81st St.

Vero Beach, FL 32967

RE: FWC PO No 24261 Three Lakes – Sunset Ranch Boardwalk Project 7334.017 Notice to Proceed with Construction

Dear Reggy:

Please consider this as your formal NOTICE TO PROCEED WITH CONSTRUCTION. You may now mobilize on site and proceed with construction subject to the conditions of the contract.

The official commencement date for this project will be the date of this Notice to Proceed (NTP) and subsequent Substantial Completion and Final Completion dates will be as established in the contract documents.

Notice to Proceed - 04/28/2025 Substantial Completion - 90 days from NTP with Construction 07/28/2025 Final Completion - 15 calendar days from substantial 08/12/2025

Contract Manager for FWC will be Michael Cottingham

Sincerely, Michael Cottingham, FWC Contract Manager