The document is a Construction Contract Change Order (CO #1) for the Tenoroc Shooting Range Sporting Clays Complex and Parking project, involving the Florida Fish and Wildlife Conservation Commission (Owner) and WestWind Contracting, Inc. (Contractor). The contract is associated with FWC Contract No. 22182 and Solicitation Number FWC 22/23-47C, located in Tallahassee, Florida.
The change order authorizes the creation of a +/- 1-acre stable storage area, including the purchase of 18 loads of additional Lime Rock (approximately 430 tons), transportation of materials, and site preparation work. The total cost for this change order is $13,192.00, which increases the original contract sum of $397,800.00 to a new contract sum of $410,992.00. The project's original substantial completion date was 05/29/2023, and the current change order adds 5 days, extending the new substantial completion date to 06/03/2023. The Notice to Proceed with Construction was issued on January 30, 2023, with John Soeder serving as the Contract Manager for the Florida Fish and Wildlife Conservation Commission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-17039.pdf | ||
| CN-770000-17039-TA4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FWC 22/23-47 Tenoroc Shooting Range Aporting Clays Complex & Parking CO#1: Build +/- 1 Acre Storage area.
WaldyP Polygon
NOTICE TO PROCEED WITH CONSTRUCTION
January 30, 2023
WestWind Contracting Inc.
3799 W Hallandale Beach Blvd.
Pembroke Park, Fl. 33023
RE: FWC 22/23-47C TENOROC SHOOTING RANGE SPORTING CLAYS COMPL
(Contract 22182) Click or tap here to enter text.
Notice to Proceed with Construction
Dear Waldy Polizzi, Please consider this as your formal NOTICE TO PROCEED FOR CONSTRUCTION of the contract based on the approval and upon issuance of the PERMITS by the jurisdiction of authority.
The official commencement date for this project will be January 30th, 2023, and subsequent Substantial Completion date will be established as 90 calendar days after the NTP per line 4 in the Supplementary Terms and Conditions in your Contract 22182 dated January 19, 2023. Final Completion will be 30 days after Substantial Completion. Contract Manager for FWC will be John Soeder.
Sincerely, John Soeder
cc. Samuel Brackman, Construction Projects Administrator II
| Notice to Proceed With Construction.pdf |
| NOTICE TO PROCEED WITH CONSTRUCTION |