CN-550000-CAP44-W0040000.pdf

PDF 420 KB Posted

Attached to
Master Agreement FL|CAU07|c1b6769864581c9f0e4f0a479c811ef5
Contract number
CAU07
Issued by
Florida

About this file

This document is a Task Work Order (TWO) issued by the Florida Department of Transportation (FDOT), District Three, to Michael Baker International, Inc. under Contract No. CAP44. The task work order involves a professional services contract for districtwide traffic operational studies, safety studies, access management, and minor design consulting, specifically focused on a Joint Participation Agreement (JPA) Lighting Design project.

The task work order authorizes Michael Baker International to design lighting systems for three corridors in Escambia and Leon Counties, utilizing Highway Safety Improvement Program (HSIP) funding for fiscal year 2025. The total compensation for this scope of work is $273,303.68, paid as a lump sum based on percentage of completion. The project involves developing lighting design analysis reports, creating conceptual design plans, performing field reviews, preparing cost estimates, and coordinating with utility companies for installation. The project is scheduled to last 10 weeks, with a design phase of 6.5 weeks, followed by a 3-week review period and a 3-week final deliverable submission period. The lighting design will cover specific roadway segments in SR 292, SR 291, and US 90, with the goal of providing detailed installation instructions for local utility companies.

View the file

Other files

File Type Posted
CN-550000-CAU07-W0020000.pdf PDF
CN-550000-CAU07-W0010000.pdf PDF
CN-550000-CAU07-00010000.pdf PDF
CN-550000-CAU07.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

6/25/2025

*Limiting or Estimating/Budgeted Amount.

Distribution:

Consultant Acceptance:

Signature

Jimmy Smith Michael Lewis Alaina Webb Kim Toole PSU-Richards Financial Services Consultant

Vice President

$273,304.00

$0.00

(name) (title)

Jeff Roberts

$273,304.00

Encumber by Task

Total authorizations to date (including this one):

Departmental Approval:

$273,304.00 Limit

Districtwide Traffic Operations Studies and Minor Design - JPA Lighting Design, Districtwide (See Attached Scope)

Michael Baker International, Inc. d/b/a Michael Baker International, LLC's Engineering Segment 12740 Gran Bay Parkway West, Suite 2110, Jacksonville, FL 32258

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$273,304.00

(LS2) Lump sum paid based on % of completion

Page 1 Total

Page 2 thru 6 Subtotal

Total

Basic Services

$747,274.00

(name) (title) Signature

Jason Peters, P.E. Director of Transportation Operations

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Task Work Order No.:

Contract No.: Payment FM No.:

CAP44 43661293201

Docusign Envelope ID: 12480DF2-C575-4477-A087-1104F0C10B45

03/14/2025

EXHIBIT A

TASK WORK ORDER (TWO)

SCOPE OF SERVICES

FOR

DISTRICTWIDE TRAFFIC OPERATIONAL STUDIES,

SAFETY STUDIES, ACCESS MANAGEMENT,

AND MINOR DESIGN CONSULTANT (CAP44)

DISTRICT THREE

FINAL

3/5/2025

TWO Information:

TASK WORK ORDER (TWO): 04

DESCRIPTION JPA Lighting Design, Districtwide

FDOT FINANCIAL ID(S): Varies

FEDERAL PROJECT NO. n/a

Est. Notice-to-Proceed (NTP): 3/17/2025

Est. Schedule: 6.5 weeks

Scope of Services Date: 3/5/2025 TWO 04: JPA Lighting Design, Districtwide Contract CAP44

Consultant: Michael Baker International

Lighting Design Concepts for JPA Installation

Limits: Districtwide

Purpose This Task Work Order is for the Consultant to design lighting systems for three additional corridors within District 3. This design shall be sufficient to deliver to local utility companies for installation of the lighting using a JPA. These three projects are programmed for FY 25 using HSIP funding.

Locations

County Roadway Name From To Section BMP EMP Length JPA

Escambia

SR 292

(Barrancas Ave) Manchester St SR 292

48050000 17.470 18.808 1.338 FPL

Escambia

SR 291 (N

Davis Hwy)

US 98 Bus/SR 30 (E Gregory St)

Denton Rd

48070000 0.000 8.672 8.672 FPL

Leon

US 90

(Tennessee St) Aenon Church Rd

SR 20

(Blountstown St) 55060000 2.484 4.300 1.816 COT

Work tasks to be performed include:

1. Lighting Design Analysis Report (LDAR) - The Consultant shall prepare LDAR to include the cutsheets of fixtures used in the design and photometric calculations from Visual or AGI showing all calculation zones and how they compare to FDOT Design Manual lighting criteria.

2. Reference and Master Design File - The Consultant shall develop conceptual level design plans that clearly shows all installation instructions for the utility companies. Aerial photography shall be used as a base and existing features shall be drawn in such as side street names, edge of travel, edge of pavement, sidewalk, crosswalks, existing lighting, existing utility poles, and any other existing features needed to analyze lighting levels.

3. Lighting Quantities - The Consultant shall quantify the number of luminaires, poles, and other relocation or removal items identified in the design. These quantities are to be used for the project cost estimating task. FDOT pay items and EQR are not required.

4. Cost Estimate - The Consultant shall develop a cost estimate for the lighting installation in conjunction with the utility company that will be performing the installation. This shall be done to ensure appropriate funding is in place to execute the JPA agreement. Unit or lump sum costs to be provided by utility company.

5. Field Review - The consultant shall perform a field review of each location to confirm that all existing features are shown properly on the plans and to ensure that all proposed features are constructable.

6. Technical Meetings - The Consultant shall attend meetings with FDOT staff and the utility

Contract CAP44

Consultant: Michael Baker International companies to discuss progress and to coordinate installation details.

7. Lighting Plans - The Consultant shall develop plan sheets and a key sheet as part of the deliverable. The plan sheets shall be drawn at a 1”=50’ scale. The plans shall show call outs for installation instructions including fixture type, wattage, arm length, and mounting height. New pole locations and removals or relocations shall also be detailed in the plans. Plans shall also clearly show side street names and other features that can be used to identify the locations in the field.

8. Quality Assurance/Quality Control

9. Supervision

10. Coordination

Deliverable: Conceptual design plan set and LDAR for each of the three locations.

Schedule: The Consultant's services shall commence work upon direction from the DPM. The design phase will commence immediately and will last 6.5 weeks. Draft plans and LDAR will then be delivered for a review period of 3 weeks. Final deliverables will be submitted 3 weeks after for a total project length of 10 weeks.

Method of Compensation

Compensation for this scope of work will be a lump sum amount of $273,303.68.

Contract CAP44

Consultant: Michael Baker International

Exhibit B – Manhour and Fee Estimate

(See Attached Staff Hour Estimate)

Project

Manager 3

Home

Engineer 2

Home

Engineer 1

Home

Engineering

Intern Home Totals

Task 1: Lighting Design Analysis Report (LDAR) 8 110 110 96 324

Task 2: Reference and Master Design File 0 35 285 292 612

Task 3: Lighting Quantities 2 100 80 60 242

Task 4: Cost Estimate 2 24 4 0 30

Task 5: Field Review 0 24 24 24 72

Task 6: Techincal Meetings 4 4 8 8 24

Task 7: Lighting Plans 0 40 60 104 204

Task 8: QA/QC 40 20 5 0 65

Task 9: Supervision 40 40 5 0 85

Task 10: Coordination 8 20 20 15 63

104 417 601 599 1721

$316.30 $206.27 $150.57 $106.68

$32,895.20 $86,014.59 $90,492.57 $63,901.32

MBI Project Subtotal: $273,303.68

$273,303.68

Exhibit B - Manhour and Fee Estimate

Florida Department of Transportation - District Three

JPA Lighting Design, Districtwide

Task Work Order (TWO): 04

Item/Task Description

Total Fee:

Total Hours:

Rate/Hour:

Total Labor:

Exhibit B: 1 of 1 3/5/2025