This document is an Amendment to a Standard Professional Services Agreement between the State of Florida Department of Transportation and Michael Baker International, Inc., doing business as Michael Baker International, LLC's Engineering Segment. The amendment is for a design project on State Road 20 in Walton County, with the original contract executed on May 24, 2023, and this first amendment dated August 17, 2023.
The amendment adds $32,302 to the contract specifically for Survey Services (LA4), bringing the total contract value from $4,155,398 to $4,187,700. The scope of work involves establishing and updating project horizontal and vertical primary and secondary control for the SR 20 design project from West of City Hall to Black Creek Boulevard. The funds are allocated under Financial Project ID 220635832301, and the contract maintains a limiting amount structure with various service categories including basic services, survey, geotechnical, permitting, public involvement, and optional services plan updates.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-AT135-W0010000.pdf | ||
| CN-550000-AT135-00010000.pdf | ||
| CN-550000-AT135-00020000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Florida Department of Transportation
AMENDMENT TO
STANDARD PROFESSIONAL SERVICES AGREEMENT
Amendment No.: 1 Execution Date:
Original Contract No.: CAN88 Original Execution Date: May 24, 2023 Consultant Name: Michael Baker International, Inc.
d/b/a Michael Baker International, LLC’s Engineering Segment Agreement Description: Design SR 20 from West of City Hall to Black Creek Blvd.
in Walton County Purpose of Amendment: Add Funds
The terms of the original agreement, referenced above, are hereby amended as follows:
This amendment serves to add funds as follows: For Financial Project ID 22063583201, Survey Services (LA4) is increased by $32,302. This total increase brings the total for this project and agreement to $4,187,700.
Compensation is to be paid in accordance with Exhibit B of the Original Agreement, except as specified above and in Contract Compensation Summary, attached hereto and made a part hereof.
Except as hereby modified, amended, or changed, all of the terms and conditions of said original agreement and any amendments thereto will remain in full force and effect.
The following attachments are hereby incorporated into this Amendment:
Scope of Services, Page 2 Contract Compensation Summary, Page 3
Michael Baker International, Inc. STATE OF FLORIDA d/b/a Michael Baker International, LLC’s DEPARTMENT OF TRANSPORTATION Engineering Segment
By: By:
Authorized Signature Authorized Signature
Name: Name: Jason Peters, P.E.
Title: Title: Director of Transportation Operations
Professional Services Review:
DocuSign Envelope ID: D49A40C8-2FF5-4576-A7DE-BF604F19F615
Vice President
Brian Russell
08/17/2023
Scope of Services Supplemental No. 01 SR 20 (Walton Co.) FPID 220635-8-32-01
1.0 PURPOSE
The purpose of this Supplemental Agreement is to amend the existing contract to incorporate control survey performed by CONSULTANT.
2.0 WORK TO BE PERFORMED
The original scope of services for Contract CAN88 required the DEPARTMENT to provide the project control survey. This Supplemental Agreement provides for the CONSULTANT Surveyor of Record to establish the survey control for the overall design project.
Project Activity 27: Survey
Services include survey for establishing / updating project horizontal and vertical primary and secondary control to the current datums.
3.0 METHOD OF COMPENSATION
Project Activity 27, as identified above, will be compensated by a Limiting Amount as identified in Exhibit A.
Limiting Amount = $32,301.81
Services above those identified will be determined as out of scope, which will require additional compensation.
CAN88
Amendment No. 1
Original Agreement (Executed 05/24/2023):
Contract Compensation Summary
Financial Project No. 22063583201 Estimate/ Limit Federal Aid Project No. D322-008-B
Basic Services Including Direct Expense (LS2) $2,769,425 L
Survey Services (LA4) $505,204 L
Geotechnical Services (LA4) $826,559 L
Permitting Services (LA4) $39,263 L
Public Involvement (LA5) $4,687 L
Optional Services Plans Update $10,260 L Total Maximum Limiting Amount $4,155,398 L
Amendment No. 1:
Limit Federal Aid Project No. D322-008-B
Basic Services Including Direct Expense (LS2) $0 L
Survey Services (LA4) $32,302 L
Geotechnical Services (LA4) $0 L
Permitting Services (LA4) $0 L
Public Involvement (LA5) $0 L
Optional Services Plans Update $0 L Total Maximum Limiting Amount $32,302 L
Original Agreement (Executed 05/24/2023) and Amendment No. 1:
Limit Federal Aid Project No. D322-008-B
Basic Services Including Direct Expense (LS2) $2,769,425 L
Survey Services (LA4) $537,506 L
Geotechnical Services (LA4) $826,559 L
Permitting Services (LA4) $39,263 L
Public Involvement (LA5) $4,687 L
Optional Services Plans Update $10,260 L Total Maximum Limiting Amount $4,187,700 L