This document is a Florida Department of Transportation (FDOT) Professional Services Advertisement and Selection Results for a roadway design project in Broward County, specifically covering SR-5/US-1 from South of Atlantic Boulevard to North of Sample Road. The procurement involves District 4 of FDOT, with the solicitation issued on 10/24/2022 for professional engineering services. Three firms were shortlisted and ranked for the project: Johnson, Mirmiran & Thompson, Inc. (ranked 1st), Core Engineering Group, LLC (ranked 2nd), and CHA Consulting, Inc. (ranked 3rd).

The contract is for a Resurfacing, Restoration, and Rehabilitation (3R) project with a total contract amount of $875,765.00. The 3.1-mile project spans the Cities of Pompano Beach and Lighthouse Point, involving roadway redesign, bike lane improvements, drainage system assessment, pedestrian safety enhancements, and signalization upgrades. Key project elements include widening bike lanes, addressing pavement design and drainage issues, reconstructing substandard curb ramps and sidewalks, and potentially implementing Pedestrian Hybrid Beacons (PHBs) at high-risk intersections. The project has a negotiation period from 1/13/2023 to 3/31/2023 and includes requirements for Disadvantaged Business Enterprise (DBE) and Small Business participation.

View the file

Other files

File Type Posted
CN-550000-CAN00-00010000.pdf PDF
CN-550000-CAY20-00020000.pdf PDF
CN-550000-CAN00-00030000.pdf PDF
CN-550000-CAN00-00040000.pdf PDF
CN-550000-CAN00.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Procurement Office Home Page (http://www.fdot.gov/procurement/)

Pursuant to Section 120.57(3), Florida Statutes, and Rule Chapter 28-110, Florida Administrative Code, any person adversely affected by the agency decision or intended decision shall file with the agency both a notice of protest in writing and bond within 72 hours after the posting of the notice of decision or intended decision, or posting of the solicitation with respect to a protest of the terms, conditions, and specifications contained in a solicitation and will file a formal written protest within ten days after the filing of the notice of protest. The required notice of protest and bond, and formal written protest must each be timely filed with the Florida Department of Transportation, Clerk of Agency Proceedings, 605 Suwannee St, Mail Station 58, Tallahassee FL 32399-0458. Failure to file a notice of protest or formal written protest within the time prescribed in section 120.57(3), Florida Statutes, or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120 Florida Statutes.

IMPORTANT NOTICE !!

All Prime Consultants and all Subvendors/subconsultants/subcontractors must register with the State's web-based e-Procurement system -"MyFloridaMarketPlace." (http://dms.myflorida.com/mfmp) Professional Services acquired in accordance with Chapter 287.055 Florida Statutes, are exempt from the 1% transaction fee. You can also sign up to attend a vendor registration training session or call 1-866-352-3776 for assistance.

10/24/2022 04:32 PM

Advertisement

Professional Services Advertisement - 23459

Project Threshold : Project is greater than or equal to $500,000.00 (Technically Prequalified & Unlimited Audit required)

District : 04

Major Work :

3.2— Major Highway Design

Minor Work :

3.1— Minor Highway Design

4.1.1— Miscellaneous Structures

7.1— Signing, Pavement Marking & Channelization

7.2— Lighting

7.3— Signalization

8.1— Control Surveying

8.2— Design, Right of Way, Construction Surveying

8.3— Photogrammetric Mapping

8.4— Right of Way Mapping

9.1— Soil Exploration

9.2— Geotechnical Classification Lab Testing

15.0— Landscape Architect

Under-Utilized Work Groups :

GROUP 4 — Highway Design - Bridges

GROUP 7 — Traffic Operations Design

Selection Method : Letter of Response and Abbreviated Technical Proposal

Professional Liability Insurance : $500,000.00

Page 1 of 3Procurement Development Application - Ad Detail

10/24/2022https://pdaexternal.fdot.gov/Pub/AdvertisementPublic/AdDetail/04/12337/PS/A/P

Project Description :

SR-5/US1 from South of Atlantic Blvd to North of Sample Road

Project Manager : Haiyan Ou

Number of contracts that may be awarded from this advertisement : 1

Contract Amount/Limit : $875,765.00

TRC Members (Subject to Change) :

Haiyan Ou

James Hughes

Vandana Nagole

See Standard Notes List :

Type Note

Standard

Note 8

Standard Note 8 - Under-Utilization Goal for DBEs and Small Businesses - The goal of the Department’s Under-

Utilization strategy is to encourage and promote use of Disadvantaged Business Enterprises (DBE) and Small

Businesses in areas of work where they have been under-used. Under-Utilization is defined by FDOT as 25% or less utilization level in a Work Group, which may vary by district. The specific Under-Utilized Work Groups are identified in the advertisement. Consultants are strongly encouraged to propose a DBE or Small Business to perform services for each Under-Utilized Work Group identified in the advertisement. DBEs or Small Businesses can be proposed at either the Prime or Sub-level for the Under-Utilized Work Group(s). Use of Under-Utilized

DBEs or Small Businesses for Consultant teaming is a shortlist consideration factor for projects referencing this

Standard Note. Consultants are requested to indicate your firm's proposed use of DBEs and/or Small Business primes or subconsultants to meet Under-Utilization goals on the table within the Professional Services Letter of

Response form (as designated in the advertisement) by checking the box under the Under-Utilization (UU) column.

Failure to list DBEs and/or Small Business prime or subconsultants on the response form shall indicate no proposed utilization. Please refer to the advertisement for other submittal directions. Reports are available at the following locations to validate status of firms as Small Businesses and DBEs (Check DBE & Small Business columns for status): DBE listing for Professional

Services:https://www.fdot.gov/procurement/InternetReports.shtm#qual Small Business listing for Professional

Services: https://www.fdot.gov/procurement/InternetReports.shtm#qual Additionally, firms will submit the

Professional Services Commitment form as required by the advertisement when selecting from Expanded Letters of Response, otherwise it will be required with the Request for Proposal.

Notes :

Type Note

Advertisement

Description Resurfacing of SR-5/US1 from South of Atlantic Blvd to North of Sample Road

Audit Package

Please be advised if you are awarded this contract the cutoff date for the Professional Services Audit package and payroll registers shall be due on the Negotiation Period Begin date as referenced on the Advertisement

Schedule. Firms that are interested in competing are advised of these deadlines. The awarded Consultant shall also provide Professional Liability Insurance (PLI) by conclusion date for negotiation or earlier.

Financial

Management

Number(s)

448401-1-32-01

Page 2 of 3Procurement Development Application - Ad Detail

Type Note

Advertisement tentative date note

Advertisement Tentative Dates

Shortlisted Firms will be provided with the RFP. Shortlisted firms must consult the RFP for actual Due Dates and Times.

Tentative Forms, Org Chart or Staffing Chart, Resumes Due Date: 12/12/2022

AFP Due Date: 01/20/2022

Scope of Services / Attachments :

Scope of Services .pdf

Schedule - The times displayed are automatically adjusted for the time zone of your system :

Type Date - Time

Advertisement Date 10/24/2022

Response Deadline Date/Time 11/07/2022 05:00 pm

Longlist Date/Time 11/15/2022 11:15 am

Shortlist Selection Date/Time 11/28/2022 09:15 am

Technical Review Committee Meeting 1 Date/Time 12/19/2022 11:00 am

Final Selection Date/Time 1/09/2023 09:15 am

Negotiations Period Begin Date 1/13/2023

Negotiations Period Ending Date 3/31/2023

Note: Oral Presentations and Consultant Interviews are exempt meetings. Times will be available in the RFP issued to

Shortlisted firms.

Respond To :

Attn.: Kereisha Ottey

Submittals must be sent to: d4.profserv@dot.state.fl.us

Phone: 954-777-4685

Physical Address:

3400 West Commercial Blvd.

Fort Lauderdale , FL 33309

BACK TO TOP

Service Desk:

fdot.servicedesk@dot.state.fl.us (mailto:fdot.servicedesk@dot.state.fl.us?subject=Procurement Development Application

(PDA) Question)

Or call 1-866-955-4357(HELP)

Accessibility Statement (http://www.fdot.gov/agencyresources/notices/accessibility.shtm) Grid Help Web Policies &

Notices (https://www.fdot.gov/agencyresources/webpoliciesandnotices.shtm) MyFlorida.com (http://www.myFlorida.com)

Page 3 of 3Procurement Development Application - Ad Detail

Procurement Office Home Page (http://www.fdot.gov/procurement/)

Pursuant to Section 120.57(3), Florida Statutes, and Rule Chapter 28-110, Florida Administrative Code, any person adversely affected by the agency decision or intended decision shall file with the agency both a notice of protest in writing and bond, where applicable, within 72 hours after the posting of the notice of decision or intended decision, or posting of the solicitation with respect to a protest of the terms, conditions, and specifications contained in a solicitation and will file a formal written protest within ten days after the filing of the notice of protest. The required notice of protest and bond, and formal written protest must each be timely filed with the Florida Department of Transportation, Clerk of Agency Proceedings, 605 Suwannee St, Mail Station 58, Tallahassee FL 32399-0458. Failure to file a notice of protest or formal written protest within the time prescribed in section 120.57(3), Florida Statutes, or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120 Florida Statutes.

IMPORTANT NOTICE !!

All Prime Consultants and all Subvendors/subconsultants/subcontractors must register with the State's web-based e-Procurement system - "MyFloridaMarketPlace." (http://dms.myflorida.com/mfmp) Professional Services acquired in accordance with Chapter 287.055 Florida Statutes, are exempt from the 1% transaction fee. You can also sign up to attend a vendor registration training session or call 1-866-352- 3776 for assistance.

01/09/2023 09:48 AM

Advertisement Selection Results

Professional Services - 23459

District :

Project Description :

SR-5/US1 from South of Atlantic Blvd to North of Sample Road

Schedule - The times displayed are automatically adjusted for the time zone of your system :

Type Date - Time Advertisement Date 10/24/2022 Response Deadline Date/Time 11/07/2022 05:00 pm Longlist Date/Time 11/15/2022 11:15 am Shortlist Selection Date/Time 11/28/2022 09:15 am Shortlist Posting Date/Time 11/28/2022 10:56 am Technical Review Committee Meeting 1 Date/Time 12/19/2022 11:00 am Final Selection Date/Time 1/09/2023 09:15 am Final Selection Post Date/Time 1/09/2023 09:48 am Negotiations Period Begin Date 1/13/2023 Negotiations Period Ending Date 3/31/2023

Note: Oral Presentations and Consultant Interviews are exempt meetings. Times will be available in the RFP issued to Shortlisted firms.

Final Selection :

Rank Firm

1 JOHNSON, MIRMIRAN & THOMPSON, INC.

2 CORE ENGINEERING GROUP, LLC

3 CHA CONSULTING, INC.

http://www.fdot.gov/procurement/ http://dms.myflorida.com/mfmp

BACK TO TOP

Service Desk:

fdot.servicedesk@dot.state.fl.us (mailto:fdot.servicedesk@dot.state.fl.us?subject=Procurement Development Application (PDA) Question)

Or call 1-866-955-4357(HELP)

Accessibility Statement (http://www.fdot.gov/agencyresources/notices/accessibility.shtm)

Grid Help

Web Policies & Notices (https://www.fdot.gov/agencyresources/webpoliciesandnotices.shtm)

MyFlorida.com (http://www.myFlorida.com) mailto:fdot.servicedesk@dot.state.fl.us?subject=Procurement%20Development%20Application%20(PDA)%20Question http://www.fdot.gov/agencyresources/notices/accessibility.shtm https://www.fdot.gov/agencyresources/webpoliciesandnotices.shtm http://www.myflorida.com/

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

PROFESSIONAL SERVICES LETTER OF RESPONSE

375-030-22

PROCUREMENT

04/18

Advertisement No.: 23459 DOT FM Number: 448401-1-32-01

Submittal Date: 11/7/2022 Project Name: SR-5/US1 from South of Atlantic Blvd to North of Sample Road (FDOT Project Manager: Haiyan Ou, P.E.)

Consultant’s Name: Johnson, Mirmiran & Thompson, Inc.

(Firm must use the name shown on the Consultant’s qualification letter.)

Street Address: 2400 E Commercial Blvd, #800

City: Fort Lauderdale State: Florida Zip: 33308

Office Location: Fort Lauderdale Contact person: DanDan Zhao, PE

Phone: 954-492-9921 Contact email: dzhao@jmt.com By submittal of this letter the Consultant certifies that all information provided in the letter is true and accurate. The Consultant further certifies that staff proposed are currently employed by the firm(s) identified, or the Consultant shall provide a statement indicating when staff will become employed by the identified firm(s).

The Letter of Response should address the following information:

• Proposed approach and understanding of critical issues.

• Relevant project experience – Similar type of work experience.

• Other content provided by firm.

• Proposed key personnel and their proposed roles (do not include resumes).

Consultants: Please be aware that all font (including font in graphics, tables, and captions on photos) must be standard Arial Narrow, 11 point, single line spacing with no modification of font or spacing allowed. ½” clear margin on all sides must be maintained on all pages. It is the Consultant’s responsibility, due to font and format restrictions within this form, to work within the constraints of the form and its format. Character styling such as use of color, bold, and italics is allowed. Use of a table is recommended for text boxes. The page layout may be modified to add columns, tables, graphics, and photos. All graphics and photos must be created in a clean, blank word document and the “text wrapping square” option applied before cutting and pasting into this form. Consultants may add their logo at the top of the first page (directly underneath the header), however, the Consultant shall not extend the form beyond the pages allocated for the Letter to accommodate insertion of the logo. Consultants are not permitted to insert any other information in the header other than the logo. After pasting your letter into this form, highlight all text and ensure the font size of Arial Narrow, 11 point was retained. Once your content is inserted, delete any additional blank pages that are generated by pressing your delete key after the last word in the Letter of Response. Recreation of the form in another software application to modify the form format is not permitted. This form works best when saved with a .docx extension. *Please retain the source document as it may be requested at a later date in the procurement, to verify adherence with aforementioned restrictions. Note: You may begin typing on this page.

PROJECT UNDERSTANDING: Johnson, Mirmiran & Thompson (JMT) is excited for the opportunity to provide design services for the Resurfacing, Restoration, and Rehabilitation (3R) along SR-5/US-1 from S of SR-814/Atlantic Blvd (MP 8.756) to N of SR-834/Sample Rd (MP 11.863), a Federally-funded 3.1-mile project in the Cities of Pompano Beach (S of NE 24 St) and Lighthouse Point (N of NE 24 St), Broward County (County). Project Overview: SR-5 is a 6-lane north-south “urban principal arterial - other”, with a design/posted speed of 45/45 MPH and AADT of 42,000 to 51,000. The Project Level Context Classification (PLCC) is C4-Urban General. Land use is generally commercial adjacent to SR-5 with residential neighborhoods immediately behind the fronting commercial.

KEY PROJECT ISSUES: Roadway/Typical Section: Existing: In each direction, the last resurfacing project (227391-1; FY01; metric) established three 11’ to 12’ travel lanes, a 4’ bike lane (except from Atlantic Blvd to NE 4 St), Type F curb & gutter, and a 6’ to 10’ sidewalk divided by a 19.5’ to 28’ landscaped Type F curb median. Proposed: Per the 4/2022 memo from D4 OMD we anticipate using a target speed of 40 MPH and reducing the posted speed to 40 MPH. To accommodate buffered/wider bike lanes, we will coordinate with the DDE to restripe the typical section, as described below. JMT recommends making the Sample Rd intersection a milling exception as it was recently resurfaced under FM 434695-1. Bike Lanes: Widen existing bike lanes as follows: NE 18 to Copans Rd – reduce existing 11.5’ lanes to 11’ to provide 5.5’ bike lanes. NE 4 St to Sample Rd - reduce existing 12’ lanes to 11’ to provide 7’ buffered bike lanes.

Atlantic Blvd to NE 4 St - Bike lanes are absent and cannot be accommodated due to restricted pavement width/ROW; therefore, a DV for lack of bicycle facilities will be required for this segment. Pavement Design: The pavement design for milling and resurfacing will specify 1.25” minimum lifts for FC to avoid density concerns and potential shortening of the pavement life associated with 1” lifts. A pavement design for reconstruction is also anticipated to address subbase failures caused by leaking drainage pipes. Drainage: Several sections of roadway within the project limits have sunken and have been patched. We recommend inspecting the existing system and/or requesting maintenance records to identify pipe deterioration and collaborating with the D4 Drainage office to determine locations

375-030-22

PROCUREMENT

requiring pipe lining or replacement. To prevent further settling, we recommend either full depth excavation to replace the subbase with clean soil that meets FDOT specifications (as designed by JMT on FM 437834-1) or inserting flowable fill into the soil (requested by Lighthouse Point PWD, as it has been used by their city and helps reduce construction duration). There is a documented flooding complaint at the intersection of SR-5 and NE 2 St. As-builts indicate that the intersection was intended to be a high point in the drainage basin. Surveyed elevations will be used to determine if the current intersection elevation deviates significantly from its original design.

The proposed intersection elevation can be altered slightly while resurfacing to address the flooding issue. Additionally, a spread analysis and hydraulic analysis of the existing pipes will be performed to determine if more inlets and/or larger pipes are required. This project will be exempt from requiring an ERP, a SWPPP will be required if the area of full depth reconstruction exceeds one acre. We will prepare the Mini-Drip Memorandum, PIF and PRM during design. Pedestrians/ADA/ Transit: Substandard curb ramps and sidewalks will be reconstructed to meet ADA and detectable warning requirements. JMT will plan to prepare exhibits for the removal of several abandoned driveways. BCT Route 10 runs along the corridor; several stops will be upgrading to provide proper boarding/alighting areas. JMT has identified several intersections where Pedestrian Hybrid Beacons (PHBs) may be warranted to address ped issues, including multiple fatalities along the corridor, in line with the FDOT Target Zero initiative. Based on injury crashes and fatalities, potential PHB locations are (1) between 6th St and 10th St, which runs along the park/amphitheater/sports complex; (2) NE 25 St; and (3) NE 31 St. The usage/locations will be discussed with Traffic Ops prior to incorporating into the scope. Adjacent Projects: There are several overlapping/adjacent FDOT projects (FM Nos 445625-1 Intersection Lighting; 447672-1 SR-844 3R; 440086-2; and 439891-5 SR-869 TSM&O Smart Work Zone) and County “Penny for Transportation” projects (CPD03 Atlantic Blvd Design Study; A17 Sample Rd Adaptive Signals; and F18: Hillsboro F/O Network). We will coordinate construction schedules and harmonize the project limits with adjacent projects as necessary. Design Variations (DVs): Anticipated DVs include intersection sight distance, cross slope (outside 3R range), lateral offset (signals in control zones) and unobstructed sidewalk at some signal facilities. S&PM: All substandard signs will be upgraded, and pavement markings replaced, including school crossings. Signalized intersection crosswalks will be upgraded to high emphasis, eliminating the existing patterned pavement. We will coordinate with Pompano Beach regarding the Airpark Shared Use Path (SUP) parallel to SB SR-5; at side street crossings, the SUP markings/path terminals should be harmonized with the FDOT sidewalk/curb ramps, which will likely require an off-system agreement with the City. Missing “Signal Ahead” signs will be added where required, and existing signs with poor reflectivity will be replaced. R1-5b signs will be added for all right turn crosswalk approaches at the signals, and green markings added to bicycle keyhole lanes. Arterial wrong way driving countermeasures will be incorporated in the signing and pavement marking design in accordance with FDM 230.4.3. “Bike lane end” signage will be added SB approaching NE 4 St. Signalization & Misc.

Structures: There are 12 signalized intersections, all with video detection. NE 24 St has strain pole signal supports; the rest have painted mast arms. We noted 33 deficient pedestrian signals and 60 deficient pedestrian detectors to be brought to current standards. The NW mast arm at NE 14 St is damaged and will be evaluated to document its condition and provide repair recommendations. Structural evaluations will also be performed for mast arms where additional loading has been recommended due to the addition of vehicular signal heads (i.e., Copans and Sample) and signs. There are seven locations where sidewalk clear width is <48” min. There are also six signal supports that violate the 48” min. offset from the face of curb. Our roadway and sidewalk design will bring these areas into compliance. One tricky aspect of design will be to maintain the existing elevations around the mast arm bases while reconstructing the ped ramps to meet ADA. Survey should include elevations around all mast arm bases. Lead Pedestrian Intervals (LPI) were recommended for the intersections of Atlantic Blvd and Sample Rd. We will coordinate the LPIs with BCTED. We will also send BCTED a list of maintenance items for their attention, such as mast arms with peeling paint and the faded/broken internally illuminated street name signs. Low-hanging utility lines which block signal visibility or that rest on the signal supports at NE 2 St and at Sample Rd will be reported to the UAOs and their adjustment included in the UWSs. We will discuss upgrading the NE 24 St span wire to mast arms with Traffic Ops, as it is within the Mast Arm Boundary Map; it may also be done under a DW or CSC task to save 3R funds. Temp.

Traffic Control Plan (TTCP): A Level 1 TTCP will be developed in accordance with FDM, FDOT Standard Plans 102-600, and the SOS.

Pedestrian detour plan details will be provided per Index 102-660. We will also specify/quantify longitudinal channelizing devices (LCD) where sidewalk closures are needed and will coordinate with Pompano Beach to detour peds to the Airpark SUP. We will maintain access to driveways, side streets, and bus stops and be mindful of the school crossings. Specific information regarding lane closures, anticipated construction start dates for the TTCP will be identified and discussed in the Community Awareness Plan (CAP) and Public Workshop at a minimum. FAA Coord: Pompano Beach Airpark is adjacent to the corridor. Using the FAA’s Notice Criteria Tool, we determined that Notice to FAA is required. Lighting: Existing decorative ped lighting from Atlantic Blvd. to NE 2 St will remain. A combination of HPS and LED lighting exists throughout the corridor. Proposed lighting retrofit is anticipated at 10 signals. From NE 16 St to Copans Rd, corridor lighting is proposed on the east side. Poles will be placed at the back of sidewalk, within the R/W. Conflict poles or spread footings may be considered as needed. The HPS lighting in these limits (west side) will be upgraded to LED. FDOT lighting compensation to the local agencies is a set amount per luminaire per year; the Cities maintain the existing lighting and therefore it is imperative that we coordinate immediately with both the County and the Cities to ensure they accept LT1 at the beginning of the project, as the proposed lighting will require a metered service. Utilities: There are 14 UAOs within the project corridor. Key issues include early requests for utility test holes (SUE) if required and identifying conflicts between buried facilities and proposed features. We will develop conflict matrixes and assist the UAOs in developing Utility Work Schedules, and all contacts and exchange of files will be made in the PSEE

Utility Coord. Module. Landscaping: JMT will coordinate with D4 Maint. and the D4 District LA, Bann Williams, regarding existing median and sidewalk tree canopies that require trimming to improve visibility of regulatory/street name signs and improve lighting uniformity; tree roots requiring pruning and root barriers to address uplifted sidewalk flags; and MMOAs with the Cities. Lighthouse Point requested sleeving/protecting the 3” reuse irrigation line in the medians in areas of curb/pavement reconstruction, as this line was damaged by FM 434695-1 north of Sample Rd. Maintenance: We will provide a memo of issues we noted in the field that can be resolved by D4 Maint.

well before construction, such as cracked or uplifted sidewalk trip hazards, damaged inlet grates and tops, and overgrown trees.

PROJECT MANAGEMENT: JMT begins every contract by developing a Project Management Plan (PMP) to be adopted by the Team.

The PMP is a living document customized to the District’s modus operandi as related to scope, schedule, budget, responsibilities, QA/QC, communications, document management, technology/software, risk/change management, and safety. Our internal and external project coordination will employ MS Teams, file sharing with ProjectWise; timely distribution of meeting minutes; regular progress meetings with dated action items/responsible party; and workload planning with using a 30, 60, and 90-day schedule look-ahead. The JMT Team is familiar with the District’s procedures and applications including: Phase Submittals/Checklists; coordinating with the TREV committee for timely TSP and DV approval (JMT recently coordinated lowering posted speed on FM 447678-1 SR-838); NEXGEN plans using ORD; use of PSEE for schedule updates, DARs, utility coordination, submittals, and Design Documentation; properly formatted ERC responses; AASHTOWare for pay items; task-specific progress reports/invoices with payout curves; and web-based Spec Packages.

Public Involvement: Major stakeholders include both Cities, the County/MPO, Pompano Beach Airpark, and 8 nearby schools. A Level 2 CAP will be developed and updated throughout the project life. A Public Workshop and meetings with key stakeholders are anticipated.

The public meeting will have a hybrid option using virtual platforms (ex. “Go-To Meeting” or “Go-To Webinar”).

SCHEDULE & BUDGET: We will maintain positive float in our PSEE schedule via a clear understanding of the SOS and recognizing which critical activities can derail the schedule, such as wants or needs from the Cities or County (ex. wider sidewalks for shared paths requested in the MMSC) for items not covered by the 3R project (ex. decorative sidewalk features). We will meet early with stakeholders to inform them of the project’s scope and 3R funding limitations. If they wish to fund additional scope, we will provide a timeline of milestones that must be met. Milestones include a written declaration of the intent to enter into a Locally Funded Agreement (LFA), the date an executed LFA would be required, and the date that funds must be transferred to FDOT, mindful of: (1) time needed to draft the LFA, (2) legal reviews by both entities, and (3) placement on a City Commission meeting agenda for approval/signature. Other closely monitored elements include driveway closures, executed agreements (ex. UWHC, off-system, maintenance, JPAs, license agreements), right-of-way maint. maps, and proprietary products. We strive for early completion of critical path items and focus on staff/resource assessment using our firm’s workload forecasting software, understanding this project is a candidate for Advanced Production. Our goal is not just to meet Production, but to guarantee to Ms. Ou an organized and seamless journey from NTP to letting, where all milestones are met, and schedule activities are updated in PSEE as they occur (not just the 1st week of each month). LRE updates will be prepared at project submittals and for each Work Program Update Cycle (WPUC), along with the EQ Report.

QUALITY CONTROL: Our QA/QC Team includes constructability reviews by our CEI experts, incorporating “lessons learned”. We are registered with the Contact Management /E-Updates and Contact Mailer database to stay current with FDOT information/training. We coordinate directly with ERC reviewers to ensure comments are properly interpreted. We also develop a hyperlinked Excel table that allows simple navigation between the plans and ERC comments, providing Ms. Ou with an efficient tool for comment verification.

KEY STAFF/ PROVEN EXPERIENCE: Ms. Zhao, PE has 11 years of District 4 transportation design, management, and CEI experience.

At NTP, Ms. Zhao will be 85% available, enabling her to maintain the highest degree of thoroughness and quality in the management of this project. Ms. Zhao’s recent District 4 experience includes being Deputy PM/Lead Highway Engineer on: SR-5/US-1 3R from N.

of George Bush Blvd to the C-16 Canal (FM 437834-1, D4 PM: Thuc Le, PE) which had similar drainage and pavement concerns and required considerable municipal coordination; SR-5 bike lane restriping over the Roosevelt Bridge to provide 7’ buffered bike lanes (FM 438345-1, D4 PM: Henry Oaikhena); and SR-9336 3R from SW 192 Ave to SR-5 with off-system agreements for a new SUP (FM 445992- 1, D6 PM: Ivette Funtanellas; 305-470-5270). JMTs D4 experience includes SR-811/NE 4 Ave (431657-1, FTBA Best in Construction;

National Roadway Safety Award; PM H. Arrieta) and SR-5/US1 (229744-3, “complete street” project nominated for FICE “Outstanding Roadway Project”; PM J. Hughes). In addition to roadway, drainage and S&PM, JMT will provide any required survey and SUE under WG 8.1 and 8.2. The JMT Team includes Civil Works, Inc. (CWI) (DBE/SBE), for Signalization; VN Engineers, Inc.

(VN) (DBE), who has worked with Ms. Ou on projects 439841-1 and 229744-4, for lighting, utility coordination, and misc. structures, under-utilized WG 4.1.1; Quest (DBE/SBE) for Public Involvement;

Tierra South Florida, Inc. (TSF) (DBE) for Geotechnical; Miller Legg (ML) (SBE) for Landscaping; and GPI for Photogrammetry.

The JMT Team has jointly worked on 25+ D4 3R projects.

KEY STAFF – NAME (FIRM) TASK/ROLE %AVL YRS

Dan Dan Zhao, PE (JMT) Project Manager 85 11 Mike Priory, PE (JMT) QA/QC Lead 70 32 Joshua Baimel, PE (JMT) Roadway/TTCP 70 23 Robert Dvorak, PE (JMT) Drainage/Permitting 75 37 David Stickles, PSM (JMT) Survey & SUE 85 28 Ryan Bogan, PE (JMT) S&PM/Safety 70 11 Linda Bell, PE (CWI) Signalization

85 30 Tracy Kaplan, PE (VN) Lighting/Utilities 75 19 Mike Murdoch, PE (VN) Misc. Structures 75 13 Nanette Rodiguez (QUEST) Public Involement 80 31 Raj Krishnamsamy, PE (TSF) Geotech. Analysis 50 33 Brian Shore, RLA, PE (ML) Signalization 75 33 Frank Paruas, PSM (GPI) Photogrammetry 60 24

Prequalification of Prime Consultant and any proposed Subconsultants by advertised type(s) of work:

Consultant Name Project Advertised Major & Minor Work Types

3.2 3.1 4.1.1 7.1 7.2 7.3 8.1 8.2 8.3 8.4 DBE SB UU

Prime Johnson, Mirmiran & Thompson, Inc.

Su bc on su lta nt s

Civil Works, Inc.

V N Engineers, Inc.

Quest Corporation of America, Inc.

Tierra South Florida, Inc.

GPI Geospatial, Inc.

Miller Legg & Associates, Inc.

SB = Small Business UU = Under-utilized work type; subconsultant is a professional services firm and is prequalified in the Under-Utilized Work Group. Refer to the advertisement for applicability.

My firm has submitted a Bid Opportunity List through the Equal Opportunity Compliance System for this project.

https://fdotwp1.dot.state.fl.us/EqualOpportunityCompliance/Account.aspx/LogIn?ReturnUrl=%2fEqualOpportunityCompliance

Prequalification of Prime Consultant and any proposed Subconsultants by advertised type(s) of work:

Consultant Name Project Advertised Major & Minor Work Types

9.1 9.2 15.0 DBE SB UU

Prime Johnson, Mirmiran & Thompson, Inc.

Su bc on su lta nt s

Civil Works, Inc.

V N Engineers, Inc.

Quest Corporation of America, Inc.

Tierra South Florida, Inc.

GPI Geospatial, Inc.

Miller Legg & Associates, Inc.

SB = Small Business UU = Under-utilized work type; subconsultant is a professional services firm and is prequalified in the Under-Utilized Work Group. Refer to the advertisement for applicability.

My firm has submitted a Bid Opportunity List through the Equal Opportunity Compliance System for this project.

https://fdotwp1.dot.state.fl.us/EqualOpportunityCompliance/Account.aspx/LogIn?ReturnUrl=%2fEqualOpportunityCompliance

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

PROFESSIONAL SERVICES - RFP

November 29, 2022

ESierra@CHACompanies.com asequeira@ourcoregroup.com dzhao@jmt.com

Re: Request for Proposal - AD#23459: Resurfacing of SR-5/US1 from South of Atlantic Blvd to North of Sample Road

Dear Consultant:

I am pleased to advise you that your firm has been shortlisted for the AD#23459: Resurfacing of SR-5/US1 from South of Atlantic Blvd to North of Sample Road contract. To enable the Department to complete the evaluation of your firm, you are requested to prepare a Technical Proposal, resumes, and organization chart or staffing chart. The Technical Proposal, resumes and organization chart or staffing chart must be prepared in accordance with the enclosed information, which includes a scope of services. Technical Proposal, resumes, organization chart or staffing chart, and required forms shall be e-mailed to d4profserv@dot.state.fl.us. All documents are due by

3:00 PM, December 12, 2022.

Note: All times listed in this letter and attached documents are Eastern Time Zone unless specifically noted otherwise.

Sincerely, Attachments CC: Haiyan Ou, P.E.

Dave, DeJean Dave DeJean, Senior Cotract Specialist

Procurement Office

Request For Technical Proposals

For

AD#23459: Resurfacing of SR-5/US1 from South of Atlantic Blvd to North of Sample Road

1. Purpose:

2. Scope of Consultant Services:

3. Length of Consultant Services:

4. Contract Restrictions & Proposed Method of Compensation:

5. Staffing Requirements:

6. Scope of Services Meeting:

7. Deadline for Questions:

8. Resumes, Organization Chart or Staffing Chart, Required Certification, and Forms:

9. Technical Proposals:

10. Consultant Selection:

11. Contract Negotiations:

12. Schedule:

Attachment A – Scope of Services

Attachment B – Standard Professional Services Agreement Terms

Attachment C – Technical Proposal Evaluation Form

Attachment D – Required Certifications

Request For Proposals

1. Purpose:

The Florida Department of Transportation requires professional services for the project known as AD#23459: Resurfacing of SR-5/US1 from South of Atlantic Blvd to North of

Sample Road. Additional information is necessary to complete the evaluation of each shortlisted consultant’s ability to provide the desired services. As a result, each shortlisted consultant is requested to provide a Technical Proposal, resumes, organization chart or staffing chart, and required certifications and forms.

Shortlisted Consultants:

CHA Consulting, Inc

CORE Engineering Group, LLC Johnson, Mirmiran & Thompson, Inc.

2. Scope of Consultant Services:

For a detailed description of the required consultant services, refer to Attachment A, Scope of Services.

3. Length of Consultant Services:

The consultant services are scheduled for a maximum period of 2 years. The consultant services shall begin only upon the receipt of written notice (i.e. Task Work Order) from the Department. The term of the contract is 10 years.

4. Contract Restrictions & Proposed Method of Compensation:

A standard consultant contract will be executed with the selected consultant for this project. The standard contract terms are provided as Attachment B. The following additional information is furnished to the consultant firm for consideration:

4.1 Professional Liability Insurance Requirement: $500,000.00. For purposes of contracting, only Professional Liability Insurance from a company or companies authorized to do business in the State of Florida is acceptable. The selected prime consultant shall submit proof of Professional Liability Insurance coverage in the minimum threshold amount designated above, prior to contracting. The policy/ies and coverage described herein may be subject to a deductible. Pay all deductibles as required by the policy. The Department shall be notified in writing within ten days of any cancellation, notice of cancellation, lapse, renewal, or proposed change to any policy or coverage described herein. The Department’s approval or failure to disapprove any policy/ies, coverage, or ACORD Certificates shall not relieve or excuse any obligation to procure and maintain the insurance required herein, nor serve as a waiver of any rights or defenses the Department may have. No policy/ies or coverage described herein may contain or be subject to a Retention or a Self-Insured Retention. A commitment letter from a financial institution is also not acceptable for purposes of contracting.

4.2 Computer Usage: The selected Consultant firm may desire to use the Department's mainframe computer (not CADD) for project related tasks.

Requested computer services will be considered during the contract negotiations.

4.3 Subconsultant Services: Services assigned to subconsultants must be approved in advance by the Department. Subconsultants performing the standard types of work covered by Rule Chapter 14-75, F.A.C., must be technically prequalified with the Department or have an application for prequalification under review at the time that they are proposed.

Subconsultants with fees less than $500,000, and/or performing specialty services (non-standard types of work), a self-certified overhead statement may be accepted. These overhead statements must be sent to Central Office for review and approval.

Private attorney services may not be utilized on Department contracts without advance approval from the Attorney General’s Office. The advance approval may only be requested by Agency General Counsel (FDOT), and not the consultant firm. Since approval cannot be assumed, consultant firms shall refrain from proposing legal firms as part of the professional services consultant team in their procurement response and proposal documents. As referenced in Section 287.059(3), F.S.:

“An agency requesting approval for the use of private attorney services shall first offer to contract with the Department of Legal Affairs for such attorney services at a cost pursuant to mutual agreement. The Attorney General shall decide on a case-by-case basis to accept or decline to provide such attorney services as staffing, expertise, or other legal or economic considerations warrant. If the Attorney General declines to provide the requested attorney services, the Attorney General’s written approval shall include a statement that the private attorney services requested cannot be provided by the office of the Attorney General or that such private attorney services are cost-effective in the opinion of the Attorney General. The Attorney General shall not consider political affiliation in making such decision. The office of the Attorney General shall respond to the request of an agency for prior written approval within 10 working days after receiving such request. The Attorney General may request additional information necessary for evaluation of a request. The

Attorney General shall respond to the request within 10 working days after receipt of the requested information.”

When universities or colleges are needed to perform services, the http://www.fdot.gov/procurement/pdf/Rule%2014-75.pdf

Department’s Project Manager shall procure such services by means of either a University Master Agreement task work order, a governmental agency contract, or a competitive solicitation for contractual services, as appropriate (reference Section 287.057(21), F.S.). Universities proposed as subconsultants will not be added to the professional services contract.

4.4 DBE/Small Business Participation:

The Department encourages DBE and small business firms to compete for professional services projects, and also encourages all other firms to use DBE and small business consultants as subconsultants. However, use of DBE and small business subconsultants is not mandatory and no preference points will be given during the selection process for DBE and/or small business participation.

Consultants shall complete Form No. 375-030-83 to indicate commitments anticipated for the project.

Federal law requires states to maintain a database of all firms that are participating or attempting to participate in DOT-assisted contracts. To assist the Department in this endeavor, consultants should have already submitted their Bid

Opportunity List through the Department’s Equal Opportunity Compliance System found at the following link (https://fdotwp1.dot.state.fl.us/EqualOpportunityCompliance/Account.aspx/LogIn?

ReturnUrl=%2fEqualOpportunityCompliance). If you have not yet completed your bid opportunity list through this online application, please do so at this time.

Prime Consultants can obtain access to the new EOC system by filling out the

Contractors and Consultants New Users Access Form. Please complete the form and submit it to EOOHelp@dot.state.fl.us.

Consultants please be reminded that if you are selected on this project, you need to enter your subconsultant commitments of each task work order in the Equal Opportunity website after invoice has been paid in CITS. Also, if you are awarded amendments to task work orders, the subconsultant commitments will also need to be reported after the respective invoice has been paid.

4.5 Method of Compensation:

This will be a task assignment type contract. A fee and method of compensation will be negotiated for each task assignment.

4.6 Public Entity Crimes: A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid, proposal, or reply on a contract to provide any goods or services to a public entity; may not submit a bid, proposal, or reply on a contract with a public entity for the construction or repair of a public building or public work; may not submit bids, proposals, or replies on leases of real property to a public entity;

may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity; and may not transact business https://pdl.fdot.gov/api/form/downloadAttachment/10980573 https://fdotwp1.dot.state.fl.us/EqualOpportunityCompliance/Account.aspx/LogIn?ReturnUrl=%2fEqualOpportunityCompliance https://fdotwp1.dot.state.fl.us/EqualOpportunityCompliance/Account.aspx/LogIn?ReturnUrl=%2fEqualOpportunityCompliance https://gcc01.safelinks.protection.outlook.com/?url=https%3A%2F%2Ffdotwww.blob.core.windows.net%2Fsitefinity%2Fdocs%2Fdefault-source%2Fequalopporunity%2Feoc-rcs-user-manual%2Feoc-system-access-request-form.pdf%3Fsfvrsn%3D899539b3_0&data=02%7C01%7CKelly.Walls%40dot.state.fl.us%7C72c061ab81c841be0eb408d703d68c8a%7Cdb21de5dbc9c420c8f3f8f08f85b5ada%7C0%7C0%7C636982092320368962&sdata=KYy0%2FLjCiK5oF%2F2PSqs662Qm%2BB%2F63Kw7%2BzUYl%2BDqe0Q%3D&reserved=0 mailto:EOOHELP@dot.state.fl.us with any public entity in excess of the threshold amount provided in s. 287.017 for CATEGORY TWO ($35,000) for a period of 36 months following the date of being placed on the convicted vendor list.

4.7 Vendor Registration through E-PROCUREMENT: As per Rule 60A-1.030, all consultants doing business with the State shall register in the MyFloridaMarketPlace system. Information about the registration process is available, and registration may be completed by linking to the following web address: https://vendor.myfloridamarketplace.com

NOTE: Contracts procured under s. 287.055, Florida Statutes are exempt from the 1% transaction fee. Interested persons lacking internet access may request assistance from MyFloridaMarketPlace Customer Services at (866) FLA-EPRO (352-3776) or State Purchasing, 4050 Esplanade Drive, Suite 300, Tallahassee, Florida 32399.

4.8 Inspector General: The Consultant agrees to comply with section 20.055(5), Florida Statutes, and to incorporate in all subcontracts the obligation to comply with section 20.055(5), Florida Statutes.

5. Staffing Requirements:

After submittal of Letters and up through contract execution, proposed subconsultants/subcontractors/sub-vendors, teaming arrangements, or key staff of the Consultant cannot be changed or substituted except in instances of force majeure or in the event of circumstances that cannot reasonably be anticipated and/or are beyond the control of the prime consultant. In such cases, changes or substitutions are subject to the discretion of the Department, and cannot be made without written approval of the Department. All such requests made during the procurement must be routed and coordinated through PSU only, as the official point of contact during contract procurement. After contract execution, subconsultant/subcontractor/sub-vendor, teaming arrangement, or key staff changes/substitutions require pre-approval of the

Department’s Project Manager before implementing. All qualification/certification requirements of the original advertisement shall govern, where applicable.

6. Scope of Services Meeting:

A Scope of Services meeting is not required for this project.

7. Deadline for Questions:

Any technical or administrative questions shall be addressed to the following:

Dave DeJean, Procurement Office Phone:

E-mail address: Dave.DeJean@dot.state.fl.us https://vendor.myfloridamarketplace.com/

NOTE: The shortlisted consultant teams shall not have any conversations concerning this project with the project manager, technical review committee, selection committee, or any other persons regarding issues related to this project other than the specified procurement office personnel identified above.

The deadline for technical questions is December 9, 2022.

There is no deadline for contract or administrative questions.

8. Resumes, Organization Chart or Staffing Chart, Required Certification, and

Forms:

The firms being considered for this project are required to electronically submit resumes, organization chart or staffing chart, required certification, and forms.

Resumes must be no longer than 2 pages per resume. The organization chart or staffing chart is limited to a one page chart which can be either 8 ½” x 11” or 11” x 17”, at the discretion of the Consultant. Font size of 11, with ½ inch margins are recommended for clarity, for Consultant submittals. Note: The Technical Proposal has a required font size and margin as specified in section 9 of this RFP. The Consultant firm may elect to submit an organization chart OR staffing chart, not both. Examples of acceptable and unacceptable content for organization charts, staffing charts, staff hour estimate charts, and a link to the Construction Training and Qualification Program

(CTQP) system can be found at this link. Organization, staffing, or staff hour estimate charts containing extra narrative content (not in conformance with examples) will be deemed unacceptable, at the sole discretion of the Procurement Office, and will not be passed on to the Technical Review Committee for review and evaluation with the other submittals.

Resumes and organization chart or staffing chart shall include sufficient information to enable the Department to evaluate the technical capability of the firms to provide the desired services. Resumes shall be included only of persons who will actually be playing key roles in the project, if selected. Resumes and organization chart or staffing chart shall not contain links to other web pages that would provide additional technical content.

8.1 Other Information & Required Certifications:

• Organization Chart or Staffing Chart and Resumes (including Subconsultants): Consultant shall include the names and levels of key personnel (including Project Manager), names of subconsultant staff (if any). Resumes are limited to 2 pages in length.

• Form No. 375-030-30, Truth in Negotiation Certification-Attachment D

• Form No. 375-030-83, Professional Services Commitment Form– Attachment D http://www.fdot.gov/procurement/SubmittalExamples.shtm

• Form No. 375-030-32, Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion for Federal Aid Contracts – Attachment D

• Form No. 375-030-33, Certification for Disclosure of Lobbying Activities on Federal-Aid Contracts – Attachment D

• Form No. 375-030-34, Disclosure of Lobbying Activities – Attachment D If this form is not applicable for your firm, please sign your firm name and write N/A on the top of the form.

• Form No. 375-030-60, Vendor Certification Regarding Scrutinized Companies Lists – Attachment D

• Form No. 375-031-06, E-Verify – Attachment D

• Construction Training and Qualification Program (CTQP) printouts may also be submitted, if applicable.

The forms provided in Attachment D shall be executed by an officer of the consultant firm submitting the proposal.

8.2 Copyrighted Material:

Copyrighted material will be accepted as part of a technical proposal only if accompanied by a waiver that will allow the FDOT to make paper or electronic copies necessary for the use of Department staff and agents. It is noted that copyrighted material is not exempted from the Public Records Law, Chapter 119, Florida Statutes. Therefore, such material will be subject to viewing by the public, but copies of the material will not be provided to the public.

8.3 Submittal of resumes, organization chart or staffing chart, required certification, and forms:

The resumes, organization chart or staffing chart, required certification, and forms shall be submitted as an attached, single computer file via e-mail. PDF (Adobe Acrobat) is the preferred format, but a Word file is acceptable. Please do not include cover sheets or dividers. The Department has a 20 MB limit on e-mail attachments. The file shall be sent to d4profserv@dot.state.fl.us. Deadline for FDOT receipt of file is 3:00 PM on December 12, 2022. All submittals may be subject to public records requests.

9. Technical Proposals:

Consultants under consideration for this project will be required to submit a Technical Proposal to be reviewed by the Technical Review Committee (TRC). The Technical

Proposal is due by 3:00 PM, on December 12, 2022.

The firms being considered for this project are required to electronically submit a written technical proposal. The proposal is not to exceed 5 single-sided, letter sized (8 ½ x 11) pages, and minimum font size of 11, with ½ inch margins. Please be aware that all font

(including graphics, tables, and captions on photos) is limited to 11 point font. Font must not be condensed. The page limit does not include resumes, organization chart or staffing chart, and required certifications and forms.

This is the start of the file's text. The full file is on GovTribe.