CN-550000-CAI75-00110000.pdf

PDF 56 KB Posted

Attached to
Master Agreement FL|ASQ66|14fdeb8d0c86c6c0fd0052c9b5d40106
Contract number
ASQ66
Issued by
Florida

About this file

This document is a Task Work Order for Professional Services issued by the State of Florida Department of Transportation (FDOT) to HDR Engineering, Inc., located in Orlando, FL. The task work order is associated with Contract No. CAI75 and has a specific Payment FM No. of 449288-1-22-01, identifying it as a professional service engagement between the state agency and the consulting firm.

The task work order is for the Orange Camp Road - MLK roundabout project in collaboration with American Structurepoint, with a total authorized compensation of $30,731.54. The compensation will be calculated using (LA4) units worked at loaded billing rates specified in Table 6, with all services to be completed by 8/30/2024. The total authorizations to date, including this task work order, amount to $2,615,854.00. The document notes that an independent assessment has been performed, confirming the staff hours and quantities as fair, reasonable, and competitive. The task work order is signed and approved by Steven Buck, P.E., Planning & Environmental Management Administrator, and accepted by Katie S. Duty, PE, ENV SP, Vice President | Area Manager of HDR Engineering.

View the file

Other files

File Type Posted
CN-550000-ASQ66.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

8/30/2024

*Limiting or Estimating/Budgeted Amount.

Distribution:

Consultant Acceptance:

Signature

HDR - PLEMO - D5-Procurement

Vice President | Area Manager

$30,731.54

$0.00

(name) (title)

Katie S. Duty, PE, ENV SP

$30,731.54

Total authorizations to date (including this one):

Departmental Approval:

$30,731.54 Estimate

Orange Camp Road - MLK roundabout - American Structurepoint

HDR Engineering, Inc.

315 E. Robinson St. Suite 400 Orlando, FL, 32801-1949

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$30,731.54

(LA4) Units worked at loaded billing rates in Table 6

Page 1 Total

Page 2 thru 6 Subtotal

Total

Orange Camp Road - MLK roundabout -

American Structurepoint

$2,615,854.00

(name) (title) Signature

Steven Buck, P.E. Planning & Environmental Management Administrator

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Task Work Order No.:

Contract No.: Payment FM No.:

CAI75 449288-1-22-01

File details come from the government source that posted it. Updated .