CN-550000-CA457-00110000.pdf

PDF 185 KB Posted

Attached to
Master Agreement FL|ASL37|338451b45e25f4cabefbec2d80f1c1f2
Contract number
ASL37
Issued by
Florida

About this file

This document is a Task Work Order Amendment #3 from the Florida Department of Transportation (FDOT) involving Kimley-Horn and Associates, Inc. for professional services under Contract CA457, specifically for the District Four Office of Modal Development (OMD). The amendment is associated with FM #437049-2-32-01 and was executed on 8/30/2021, involving technical support services for multimodal transportation planning.

The amendment adds additional funding to continue professional technical support services and introduces a Design Intern rate to the existing task work order. The services will include technical document reviews, meeting support, training, SUNTrail program support, park-and-ride assistance, multimodal studies, grant application development, technical assistance, and cost estimates for multimodal improvements. Specifically, Kimley-Horn will help FDOT staff create and maintain Long Range Estimate (LRE) data for multimodal projects. The services will be provided on a maximum limiting amount basis and are to be completed on or before July 8, 2024, with a total authorization of $1,053,926.94 to date, and this amendment adding $95,267.58 to the task work order.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract CA457

FM # 437049-2-32-01

Kimley-Horn and Associates, Inc.

Scope of Work – Task Work Order # 01 – Amendment #3

Office of Modal Development Technical Support

The District Four Office of Modal Development (OMD) desires to utilize Consultant support to assist in delivering a multimodal transportation system and Complete Street support to the Florida Department of Transportation

(FDOT) District 4 Project Manager and the OMD staff.

On February 7, 2020, FDOT authorized CA457 Task Work Order # 01 for Office of Modal Development Technical

Support services.

On September 10, 2020, FDOT authorized Amendment #1 to CA457 Task Work Order # 01 for Office of Modal

Development Technical Support services.

On March 31, 2021, FDOT authorized Amendment #2 to CA457 Task Work Order # 01 for Office of Modal

Development Technical Support services.

The purpose of Amendment #3 of this task work order is (1) to add additional funding to the Technical Support

Task Work Order # 01 to continue providing ongoing professional assistance technical support to the FDOT

District Four Office of Modal Development, and (2) to add the Design Intern rate to the task work order.

Professional assistance technical support may include but not be limited to the following: technical document reviews, meeting support, training, SUNTrail program support, park-and-ride support, multimodal studies, developing grant applications, technical assistance, and cost estimates for multimodal improvements.

The following requirements and tasks comprise the services that the Consultant will perform to accomplish the purpose of this task work order.

Deliverables

Kimley-Horn, Marlin, via planning, and Cambridge Systematics will continue to assist FDOT staff on multimodal planning issues through various support. The technical support may include all items from the original task work order, all items from Amendment #1, all items from Amendment #2, plus the following addition.

" Kimley-Horn will assist FDOT staff to create and maintain Long Range Estimate (LRE) data for multimodal projects.

The Consultant shall be entitled to rely on the completeness and accuracy of all information provided by the

Department. The Department shall provide information requested by the Consultant during the project.

Services for this task work order will be provided on a maximum limiting amount basis in accordance with the provisions in the overall contract. The detailed budget for the work effort is contained in Attachment A.

The services will be provided as determined by the Department’s Project Manager. All services are to be completed on or before July 8, 2024.

File details come from the government source that posted it. Updated .