This document is an Amendment to a Standard Professional Services Agreement between the Florida Department of Transportation (FDOT) District Five and Tetra Tech, Inc., with additional sub-consultants including Dannick Engineering Consultants, Quest Corporation of America, Traffic Engineering Data Solutions, and Maser Consulting P.A. The amendment is for Financial Project No. 441020-1-32-01, specifically concerning the SR 519 (Fiske Boulevard) project in Brevard County, spanning from the I-95 northbound ramps/Barnes Boulevard to SR 520 (King Street).

The amendment increases the total contract amount by $32,866.00, bringing the total maximum limiting amount to $2,205,135.00. The additional funds and scope are to incorporate improvements requested by the City of Cocoa for Provost Park, including adding curb and gutter along southbound lanes, relocating driveways, and reconfiguring parking areas. Additionally, FDOT's Brevard Operations requested reconstruction of pavement sections experiencing base failure. The amendment requires Tetra Tech to develop new pavement designs, typical sections, drainage analyses, traffic control plans, and update various project documentation. The work is to be completed by June 1, 2020, within the existing project schedule, with Tetra Tech receiving the bulk of the additional funding ($32,866.00) for these expanded design services.

View the file

Other files

File Type Posted
CN-550000-CA229-00010000.pdf PDF
CN-550000-CA229-00030000.pdf PDF
CN-550000-CA229-00050000.pdf PDF
CN-550000-CA229.pdf PDF
CN-550000-CA229-00040000.pdf PDF
ContractBudgetExport.csv CSV file
CN-550000-CA229-00020000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

District Five Professional Services Office, 719 South Woodland Blvd. MS 4-524, Deland, Florida 32720, (386) 943-5526, www.fdot.gov

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

AMENDMENT TO

STANDARD PROFESSIONAL SERVICES AGREEMENT

375-030-97

PROCUREMENT

08/18

Amendment Number: 1 Amendment Execution Date:

Original Agreement No.: CA229 Original Agreement Execution Date: 1/22/2019

Consultant Name: Tetra Tech, Inc.

FM Number(s): 441020-1-32-01

Agreement Description: SR 519 from I-95 NB Ramp/ Barnes Blvd. (MP 0.460) to North of SR 520 (MP 4.604), Brevard County

Purpose of Amendment: Add Funds, Incorporate attachments to the contract

The terms of the original agreement referenced above are hereby amended:

The total maximum limiting amount of $2,172,269.00 for all services required under the original agreement and all supplements and amendments thereto is herein increased by $32,866.00. The revised total maximum limiting amount for all services is $2,205,135.00. The services specified in Exhibit “A”, Scope of Services of the original agreement are amended and attached as Exhibit "A".

The following attachments are hereby incorporated into this Amendment:

Exhibit “A”, Scope of Services, pages A-1 to A-3 Attachment No. 1: Summary of Contract Fees

Except as hereby modified, amended, or changed, all of the terms and conditions of said original agreement and any supplements and amendments thereto will remain in full force and effect.

IN WITNESS WHEREOF, the parties hereto have caused these presents to be executed, the day and year first above written.

CONSULTANT STATE OF FLORIDA

DEPARTMENT OF TRANSPORTATION

Tetra Tech, Inc.

Name of Consultant

BY: BY:

Name: Name: Loreen Bobo, P.E.

Title: Title: Director of Transportation Development

District Five

FOR DEPARTMENT USE ONLY

PROCUREMENT OFFICE REVIEW: LEGAL OFFICE REVIEW:

Procurement Office Legal Office

DocuSign Envelope ID: 74AEA6D8-60AF-4D2F-B48F-BE52C49B535D

Vice President

Lawrence E. Jenkins

2/27/2020 | 12:49 PM EST

SCOPE OF SERVICES

SR 519 (Fiske Blvd.) from I-95 NB Ramp/Barnes Blvd. to SR 520 (King St.)

Financial Project ID No. 441020-1-32-01

1.0 BACKGROUND

Tetra Tech (CONSULTANT) was originally retained by the Florida Department of

Transportation District Five (DEPARTMENT) under Contract CA229 to provide construction plans for the resurfacing of SR 519 (Fiske Boulevard) from the I-95 northbound ramps/Barnes

Boulevard to SR 520 (King Street) in Brevard County (FPID 441020-1-32-01).

At a local agency coordination meeting, the City of Cocoa stated that they were planning improvements to Provost Park, which is at the north end of the SR 519 project limits. The improvements included adding curb and gutter along the southbound lanes, relocating and consolidating the driveways, and reconfiguring the parking areas. The City of Cocoa requested that the curb and gutter and driveway modifications be included in the SR 519 project to enhance the safety of pedestrians since the park improvements are not funded and will not be constructed prior to the SR 519 project.

In addition, FDOT’s Brevard Operations office noted that they have been repairing sections of the SR 519 pavement within the project limits on a regular basis as a result of base failure. They requested that these pavement sections be reconstructed as part of this project instead of being resurfaced.

2.0 PURPOSE

The purpose of this Supplemental Amendment is to provide authorization for additional design services to incorporate the proposed improvements to Provost Park and reconstruction of the pavement that has experienced base failure into the construction plans for SR 519. This Scope of

Work provides additional compensation to the CONSULTANT’s design contract.

3.0 SERVICES TO BE PERFORMED

A. Roadway

1. Develop a pavement design for reconstruction of SR 519 in the following areas that have experienced base failure, and revise the Pavement Design Report accordingly:

Exhibit "A"

A-1

DocuSign Envelope ID: 74AEA6D8-60AF-4D2F-B48F-BE52C49B535D

a. Sta. 523+50 to Sta. 527+05, Left

b. Sta. 534+80 to Sta. 535+35, Right

c. Sta. 536+50 to Sta. 537+80, Right

d. Sta. 567+80 to Sta. 570+00, Right

e. Sta. 568+55 to Sta. 570+00, Left

2. Develop an additional typical section showing reconstruction of SR 519.

3. Develop an additional typical section showing curb and gutter along the SR 519 southbound travel lanes.

4. Perform design analysis to develop a gutter grade, ensuring that the minimum

0.3% grade is provided, and tie the proposed back-of-sidewalk elevation to the existing ground.

5. Revise the design file to reflect the reconstruction areas, include curb and gutter and a bike lane, to relocate the driveway to Provost Park, and to replace the existing sidewalk with a 6-ft sidewalk.

6. Develop a temporary traffic control plan that provides the required phasing for reconstruction of the pavement and construction of the curb and gutter, including the necessary details.

7. Revise the pay item quantities and cost estimate.

8. Incorporate the proposed revisions into the roadway plan sheets, cross sections, temporary traffic control plans, utility adjustment sheets, and summary of quantities sheets.

B. Drainage

1. Review existing permits and the design of the existing storm system.

2. Perform design analysis to provide inlets along the proposed curb and gutter and tie them into the existing 30-inch trunk line.

3. Perform a culvert service life estimator analysis to identify optional pipe materials.

4. Develop additional drainage structure cross sections and update the Summary of

Drainage Structures

5. Incorporate the proposed drainage structures into the Erosion Control Plan Sheets, and SWPPP.

4.0 SCHEDULE

The tasks described in this Supplemental Agreement will be performed within the existing project schedule with a Production Date of June 1, 2020.

A-2

5.0 CONSULTANT AND DEPARTMENT RESPONSIBILITIES

All services and requirements as outlined in the Original Agreement, including any

Supplemental Amendments to date, shall remain in full force and effect.

A-3

DESIGN SERVICES Financial Project No. 441020-1-32-01

Original

Agreement

This

Amendment

No. 1

Revised

Contract

Totals

LUMP SUM

Tetra Tech, Inc. $611,636.00 $32,866.00 $644,502.00

Dannick Engineering Consultants, Inc. $64,246.00 $0.00 $64,246.00

Quest Corporation of America, Inc. $13,376.00 $0.00 $13,376.00

Traffic Engineering Data Solutions, Inc. $255,601.00 $0.00 $255,601.00

R/W Control Map (LS-2)

Maser Consulting P.A. $107,107.00 $0.00 $107,107.00

Terrestrial Mobile LiDAR (LS-2)

Maser Consulting P.A. $71,257.00 $0.00 $71,257.00

Subtotal Lump Sum Amount $1,123,223.00 $32,866.00 $1,156,089.00

LIMITING AMOUNT

Maser Consulting P.A. $948,311.00 $0.00 $948,311.00

Supplemental Design & R/W Survey Services (LA-4)

Maser Consulting P.A. $30,670.00 $0.00 $30,670.00

Supplemental Mapping (LA-4)

Maser Consulting P.A. $18,133.00 $0.00 $18,133.00

Geotechnical Services (LA-4)

Ardaman & Associates, Inc. $51,932.00 $0.00 $51,932.00

Subtotal Limiting Amount $1,049,046.00 $0.00 $1,049,046.00

TOTAL MAXIMUM LIMITING AMOUNT $2,172,269.00 $32,866.00 $2,205,135.00

Survey Services (LA-4)

Basic Services (LS-2)

ATTACHMENT NO. 1: Summary of Contract Fees

CA229 Amendment No. 1