CN-550000-C9Y52-00110000.pdf

PDF 195 KB Posted

Attached to
Master Agreement FL|ASU98|8bd63eda3615e7b3d66fdeb0e8154c8d
Contract number
ASU98
Issued by
Florida

About this file

This document is a Task Work Order Amendment from the Florida Department of Transportation (FDOT) for professional services, specifically a Strategic Intermodal System (SIS) Planning Consultant contract. The primary consultant is HDR Engineering, Inc., located in Jacksonville, Florida, with Contract No. C9Y52. The amendment is for Task Work Order No. 1, Amendment No. 2, and involves supporting the department's Strategic Intermodal System program.

The amendment increases the task work order amount by $351,568.90, bringing the total amended amount to $703,467.40, with a completion date of 02/27/2023. The scope of services includes updating SIS highway and multimodal cost feasible plans, maintaining SIS work programs and needs plans, developing SIS documents, providing staff support services, implementing updated designation criteria, assessing funding eligibility frameworks, and offering on-site policy and technical support. The consultant will provide various deliverables such as technical notebooks, executive summaries, plans, brochures, web page updates, and supporting documentation. Staffing will involve multiple HDR Engineering personnel across various roles, including chief engineers, planners, project managers, and specialists, who will be authorized to charge their time to this task work order at their current hourly rates.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Note: for Prof. Serv. Task Work Order Amendments, the encumbrance line should never be closed

(Status 50) by Financial Services staff based on this selection. Additional Note: Please be sure you want to close out before marking. Premature close outs that must be corrected in CITS may require programmer time and costs borne by the program office.

As directed by the FDOT Task Manager.

As directed by the FDOT Task Manager.

As directed by the FDOT Task Manager.

As directed by the FDOT Task Manager.

As directed by the FDOT Task Manager.

As directed by the FDOT Task Manager.

As directed by the FDOT Task Manager.

As directed by the FDOT Task

Manager.

Estimated completion: Ongoing

Estimated completion: December 2018

Estimated completion: March 2019

Estimated completion: within 30 days following FDOT’s review

Estimated completion: April 2019

Estimated completion: within 30 days following FDOT’s review

As directed by the FDOT Task Manager.

Estimated completion: May 2019

As directed by the FDOT Task Manager.

Estimated completion: June 2019

As directed by the FDOT Task Manager.

Estimated completion: June 2019

As directed by the FDOT Task Manager.

Estimated completion: August 2019

As directed by the FDOT Task Manager.

Estimated completion: September 2019

As directed by the FDOT Task Manager.

Estimated completion: November 2019.

Estimated completion: November 2019.

As directed by the FDOT Task Manager. Estimated completion: Ongoing

As directed by the FDOT Task Manager. Estimated completion: Ongoing

HDR Engineering, Inc. (Office) –

HDR Engineering, Inc. (FIELD) –