CN-550000-C9X07-S0020000.pdf
PDF 62 KB Posted
- Contract number
- ASF03
- Issued by
- Florida
About this file
This document is an Amendment (Amendment No. 2) to a Standard Professional Services Agreement between the State of Florida Department of Transportation and Parsons Transportation Group, Inc. The original contract was executed on October 27, 2017, with this amendment dated December 11, 2018. The agreement is associated with Financial Project No. 42551926201 and Federal Aid Project No. D317 036 B, specifically covering CEI (Construction Engineering and Inspection) Services for State Road 97 over Sandy Hollow Creek Bridge No. 480018 in Escambia County.
The amendment increases the contract's compensation by adding $114,098 for Salary Related Costs and $1,548 for Premium Overtime, bringing the Total Maximum Limiting Amount to $532,321. Additionally, the amendment extends the end date for completion of services by two months. The contract compensation breakdown includes Salary Related Costs, Premium Overtime, Miscellaneous Direct Expenses for Field Office Rent and Utilities, and Survey Services. The primary purpose of this amendment is to provide additional funding and additional time to complete the professional services related to the bridge project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-ASF03.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 2 Amendment No. 2 C9X07
State of Florida Department of Transportation
AMENDMENT
TO
STANDARD PROFESSIONAL SERVICES AGREEMENT
Amendment No.: 2 Execution Date: .
Original Contract No.: C9X07 Original Execution Date: October 27, 2017 .
Consultant Name: Parsons Transportation Group, Inc .
FM Number(s): 42551926201 FAP No.: D317 036 B .
Agreement Description: CEI Services for SR 97 over Sandy Hollow Creek Bridge No. 480018 in
Escambia County .
Purpose of Amendment: Add additional funds and extend completion of services .
The terms of the original agreement, referenced above, are hereby amended as follows:
The Contract Compensation Summary for “Exhibit B”, Method of Compensation, of the original Agreement is amended as follows:
For Financial Project No. 42551926201, Salary Related Cost (LA 4) is increased by $114,098 and Premium Overtime (LA 4) is increased by $1,548 bringing the Total Maximum Limiting Amount established for this Agreement to $532,321.
Compensation is to be paid in accordance with Exhibit B of the original agreement, except as specified above, and in Contract Compensation Summary, attached hereto and made a part hereof.
This amendment also serves to extend the end date for completion of services by two months.
Except as hereby modified, amended, or changed, all of the terms and conditions of said original agreement and any amendments thereto will remain in full force and effect.
The following attachments are hereby incorporated into this agreement:
Contract Compensation Summary, Page 2
Parsons Transportation Group, Inc STATE OF FLORIDA
DEPARTMENT OF TRANSPORTATION
By: By: .
Authorized Signature Authorized Signature
Name: Name: Jared Perdue, P. E
Title: Title: Director of Transportation Development
Professional Services Review: Legal Review:
DocuSign Envelope ID: EB5D1CE0-0E77-4BAA-8B88-BE8AE044C57B
Vice President
Keith Travis
December 11, 2018
Page 2 of 2 Amendment No. 2 C9X07
Original Agreement (Executed 10/27/17) and Amendment No. 1 (Executed 11/20/17):
Amendment No. 2:
Original Agreement (Executed 10/27/17), Amendment No. 1 (Executed 11/20/17) and Amendment No. 2:
Contract Compensation Summary Table
Financial Project No. 42551926201 Estimate or Limit
F.A.P. No. D317 036 B
Salary Related Costs (LA 4) $373,440 E Premium Overtime (LA 4) $5,304 E Miscellaneous Direct Expenses for Field Office Rent and Utilities (LA 5) $8,141 E Survey Services (LA 4) $29790
TOTAL MAXIMUM LIMITING AMOUNT: $416,675
Contract Compensation Summary Table
Financial Project No. 42551926201 Estimate or Limit
F.A.P. No. D317 036 B
Salary Related Costs (LA 4) $114,098 E Premium Overtime (LA 4) $1,548 E Miscellaneous Direct Expenses for Field Office Rent and Utilities (LA 5) - E Survey Services (LA 4) - E
TOTAL $115,646
Contract Compensation Summary Table
Financial Project No. 42551926201 Estimate or Limit
F.A.P. No. D317 036 B Salary Related Costs (LA 4) $487,538 E Premium Overtime (LA 4) $6,852 E Miscellaneous Direct Expenses for Field Office Rent and Utilities (LA 5) $8,141 E Survey Services (LA 4) $29,790 E
TOTAL MAXIMUM LIMITING AMOUNT: $532,321