CN-550000-C9W91-S0030000.pdf

PDF 133 KB Posted

Attached to
Master Agreement FL|ASO08|5ad133cacd20cba7dfe449278e040507
Contract number
ASO08
Issued by
Florida

About this file

This document is an Amendment (No. 6) to a Standard Professional Services Agreement between the State of Florida Department of Transportation and Chipola Engineering Group, Inc., originally executed on October 30, 2017. The agreement involves a transportation design project for State Road 75 (US 231) located in Jackson County, Florida, specifically covering the section from north of State Road 73 to north of County Road 162 (Jacob Road).

The amendment serves to remove residual funds from Financial Project No. 43972213201, decreasing Survey Services (LA 4) by $7,066.13 and Plans Update Services by $6,366.00, for a total reduction of $13,432.13. This adjustment brings the Total Maximum Limiting amount for the project to $711,273.87. The contract covers various professional services including Basic Services with Direct Expenses, Survey Services, Plans Update Services, and Post Design Services. The agreement remains in full force and effect through completion of all required services or for a 10-year term from the original execution date, with Nick Grosso from Chipola Engineering Group and Jason Peters from the Florida Department of Transportation signing the amendment on October 5, 2020.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of Florida Department of Transportation

AMENDMENT

TO

STANDARD PROFESSIONAL SERVICES AGREEMENT

Amendment No.: 6 Execution Date:

Original Contract No.: C-9W91 Original Execution Date: October 30, 2017 Consultant Name: Chipola Engineering Group, Inc.

Agreement Description: Design of SR 75 (US 231) from North of State Road 73 to North of County Road 162 (Jacob Road) in Jackson County.

Purpose of Amendment: Remove Residual Funds

The terms of the original agreement, referenced above, are hereby amended as follows:

This Amendment No. 6 serves to remove residual funds from Financial Project No. 43972213201.

For Financial Project No. 43972213201, Survey Services (LA 4) is decreased by $7,066.13 and Plans Update is decreased by $6,366.00 for a total decrease of $13,432.13. This decrease brings the Total Maximum Limiting amount established for this project and said Agreement to $711,273.87.

Compensation is to be paid in accordance with Exhibit “B” of the original agreement, except as specified above and in the Contract Compensation Summary, attached hereto and made a part hereof.

The provisions of this Agreement and any amendments thereto, will remain in full force and effect through completion of all services required of the Consultant or a 10 year term from the original date of execution of this Agreement.

The following attachments are hereby incorporated into this agreement:

Contract Compensation Summary, Page 2

CHIPOLA ENGINEERING GROUP, INC. STATE OF FLORIDA

DEPARTMENT OF TRANSPORTATION

BY: BY:

Jason Peters, P.E.

(Name) (Name)

Director of Transportation Operations (Title) (Title)

Professional Services Review: Legal Review:

Original Agreement (Executed 10/30/2017); Amendment No. 1 (Executed 10/22/2018);

Amendment No. 2 (Executed 11/7/2018); (Amendment No. 3 (Executed 2/25/2019);

Amendment No. 4 (Executed 6/6/2019); Amendment No. 5 (Executed 2/18/2020):

Financial Project No. 43972213201 Estimate or

F.A.P. No. N/A Limit

Basic Services including Direct Expenses (LS 2) $604,260.00 L

Survey Services (LA 4) $81,182.00 L

Plans Update Services $6,366.00 L

Post design Services (LA 4) $32,898.00 L

Total Maximum Limiting Amount $724,706.00

Amendment No. 6:

Financial Project No. 43972213201 Estimate or

F.A.P. No. N/A Limit

Basic Services including Direct Expenses (LS 2) $0.00 L

Survey Services (LA 4) -$7,066.13 L

Plans Update Services -$6,366.00 L

Post Design Services (LA 4) $0.00 L

Total Maximum Limiting Amount -$13,432.13

Original Agreement (Executed 10/30/2017); Amendment No. 1 (Executed 10/22/2018);

Amendment No. 2 (Executed 11/7/2018); (Amendment No. 3 (Executed 2/25/2019);

Amendment No. 4 (Executed 6/6/2019); Amendment No. 5 (Executed 2/18/2020);

Amendment No. 6:

Financial Project No. 43972213201 Estimate or

F.A.P. No. N/A Limit

Basic Services including Direct Expenses (LS 2) $604,260.00 L

Survey Services (LA 4) $74,115.87 L

Plans Update Services $0.00 L

Post Design Services (LA 4) $32,898.00 L

Total Maximum Limiting Amount $711,273.87

Contract Compensation Summary

Contract Compensation Summary

Contract Compensation Summary