This document is a Task Work Order Amendment Form for Professional Services issued by the State of Florida Department of Transportation (FDOT). The amendment involves HDR Engineering, Inc., located at 315 E. Robinson Street, Suite 400, Orlando, FL, under Contract No. C-9W83. The document specifically relates to Amendment No. 1 to Task Work Order No. 5 for the North Lake Trail, Phase 3 project from County Road 450.

The amendment extends the time for completion of services through 7/31/2019, with no change to the previous compensation amount of $228,113.29. The method of compensation is a lump sum paid based on percentage of completion. The total authorizations to date, including this amendment, are $1,098,228.55. The amendment is signed by Heather S. Garcia, Planning & Corridor Development Manager for FDOT, and Christine Kefauver, Vice President of HDR Engineering, Inc., indicating mutual agreement to the time extension for the North Lake Trail project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER AMENDMENT FORM

FOR PROFESSIONAL SERVICES

375-030-26

PROCUREMENT

02/17

7/31/2019 .

recovered is $ .

Subtotal Check if

Estimate

$228,113.29

$0.00

$0.00

$0.00

$0.00

$0.00

$228,113.29

$0.00

$228,113.29

Attachments:

Distribution:

Payment FM No. (must be the same as original Task Work Order):

441626-1-12-01

Check all applicable Terms:

North Lake Trail, Phase 3 from CR 450 - Time Extension

315 E. Robinson Street, Suite 400, Orlando, FL 32801-1949

HDR Engineering, Inc.

Address:

Consultant:

Date (To be entered upon execution of Task Work Order Amendment):Contract No.:

C-9W83

Purpose of Amendment:

Amendment No.

to Task Work Order No.

$1,098,228.55

(Name) (Title) Signature

Heather S. Garcia Planning & Corridor Development Manager

Consultant Acceptance:

(Title)

Christine Kefauver, AICP

Signature

Vice President

(Name)

Compensation Element

Description

This Amendment

Amount

North Lake Trail $0.00

Previous

Amount

$228,113.29

Method of Compensation

(LS2) Lump sum paid based on % of completion against this task work order beyond the date of execution of this amendment. The following amount is the remaining work order balance to be recovered

The time for completion of services for the subject task work order is extended thru

The total amount for services performed under this task work order is increased by $

The total amount for services performed under this task work order is decreased by $

The decrease in funds will be allocated to the following compensation elements described below.

elements are described below.

from this task work order $ . Note: for Prof. Serv. Task Work Order Amendments, the encumbrance line should never be closed

The subject task work order is hereby closed. Final payment for the task work order has been paid. No additional services or charges are authorized

(Status 50) by Financial Services staff based on this selection.

The subject task work order is hereby canceled (no work has been performed and no payment is due). The total amount of the task work order which is

The additional funds will be allocated to the following compensation elements described below.

There is no increase/decrease in the task work order amount, funds are only redistributed between compensation elements. Revised compensation

$0.00

$0.00

$0.00

Departmental Approval:

Total authorizations to date (including this one):

Other Notes:

Page 1 subtotal

Page 2 thru 6 Subtotal

Total

DocuSign Envelope ID: 6FE872FA-879A-4C1B-9F9F-EFDED3E70994

File details come from the government source that posted it. Updated .