This document is an Amendment (No. 5) to a Standard Professional Services Agreement between the State of Florida Department of Transportation and David H. Melvin, Inc., originally executed on February 14, 2017. The agreement pertains to the design of State Road 81 from State Road 20 to the Holmes County Line in Walton County, with the current amendment focused on providing additional post-design services.
The amendment increases compensation for Financial Project No. 43775313201 by $10,164.00 specifically for Post Design Services (LA 4), bringing the Total Maximum Limiting Amount for the project to $1,762,785.03. The contract compensation summary shows the incremental changes, with the Post Design Services (LA 4) line item increasing from $194,332.00 to $204,496.00. The amendment maintains the original agreement's terms and will remain in effect through completion of all required services or for a ten-year term from the original execution date, whichever occurs first.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-C9T05-00030000.pdf | ||
| CN-550000-C9T05-W0020000.pdf | ||
| CN-550000-C9T05-00020000.pdf | ||
| CN-550000-C9T05-W0010000.pdf | ||
| CN-550000-C9T05-W0030000.pdf | ||
| CN-550000-C9T05-W0040000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-C9T05-00050000.pdf | ||
| CN-550000-C9T05.pdf | ||
| CN-550000-C9T05-00040000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Florida Department of Transportation
AMENDMENT
TO
STANDARD PROFESSIONAL SERVICES AGREEMENT
Amendment No.: 5 Execution Date:
Original Contract No.: C-9T33 Original Execution Date: February 14, 2017 Consultant Name: David H. Melvin, Inc.
Agreement Description: Design of State Road 81 from State Road 20 to the Holmes County Line in Walton County Purpose of Amendment: Additional Post Design Services
This Supplemental Amendment provides compensation for additional Post Design Services on
FIN 43775313201.
The terms of the original agreement, referenced above, are hereby amended as follows:
Contract Compensation Summary of Exhibit “B”, Method of Compensation, of the original Agreement is amended as follows:
For Financial Project No. 43775313201, Post Design Services (LA 4) is increased by $10,164.00. This increase brings the Total Maximum Limiting Amount for this project and said agreement to $1,762,785.03.
Compensation is to be paid in accordance with Exhibit “B” of the original agreement, except as specified above.
The provisions of said Agreement, and any amendments thereto, shall remain in full force and effect through completion of all services required of the consultant or a ten (10) year term from the date of the execution of said agreement, whichever occurs first.
The following attachments are hereby incorporated into this agreement:
Contract Compensation Summary, Page 2
DAVID H. MELVIN, INC. STATE OF FLORIDA
DEPARTMENT OF TRANSPORTATION
BY: BY:
Tim Smith, P.E.
(Name) (Name)
Interim Dir. of Transportation Development (Title) (Title)
Professional Services Review: Legal Review:
DocuSign Envelope ID: 31B336F3-011F-4E99-9627-BD2AD327EB05
VP
Gene Nobles
June 24, 2020
Original Agreement (Executed 2/14/2017); Amendment No. 1 (Executed 2/4/2019);
Amendment No. 2 (Executed 3/14/2019); Amendment No. 3 (Executed 9/23/2019);
Amendment No. 4 (Executed 9/23/2019);
Financial Project No. 43775313201 Estimate or
F.A.P. No. 0711 009 P Limit
Basic Services Including Direct Expenses (LS 2) $1,148,768.00 Limit
Survey Services (LA 4) $326,661.42 Limit
Plans Update $5,016.61 Limit
Post Design Services (LA 4) $194,332.00 Limit
Post Design Services (LS 2) $77,843.00
Total Maximum Limiting Amount $1,752,621.03
Amendment No. 5:
Financial Project No. 43775313201 Estimate or
F.A.P. No. 0711 009 P Limit
Basic Services Including Direct Expenses (LS 2) $0.00 Limit
Survey Services (LA 4) $0.00 Limit
Plans Update $0.00 Limit
Post Design Services (LA 4) $10,164.00 Limit
Post Design Services (LS 2) $0.00 Limit
Total Maximum Limiting Amount $10,164.00
Original Agreement (Executed 2/14/2017); Amendment No. 1 (Executed 2/4/2019);
Amendment No. 2 (Executed 3/14/2019); Amendment No. 3 (Executed 9/23/2019);
Amendment No. 4 (Executed 9/23/2019); Amendment 5:
Financial Project No. 43775313201 Estimate or
F.A.P. No. 0711 009 P Limit
Basic Services Including Direct Expenses (LS 2) $1,148,768.00 Limit
Survey Services (LA 4) $326,661.42 Limit
Plans Update $5,016.61 Limit
Post Design Services (LA 4) $204,496.00 Limit
Post Design Services (LS 2) $77,843.00 Limit
Total Maximum Limiting Amount $1,762,785.03
Contract Compensation Summary
Contract Compensation Summary
Contract Compensation Summary
DocuSign Envelope ID: 31B336F3-011F-4E99-9627-BD2AD327EB05
File details come from the government source that posted it. Updated .