This document is a Task Work Order Amendment Form issued by the State of Florida Department of Transportation, specifically Amendment No. 3 to Task Work Order No. 17. The amendment involves Dunkelberger Engineering & Testing, Inc., located in Port St. Lucie, Florida, with a contract number of C8N74. The document was dated 6/28/2013 and received on 6/28/2013, with a follow-up received stamp on 7/1/2013.

The primary purpose of this amendment is a time extension for the existing work order, extending the completion of services through 11/30/2013. The amendment is associated with Payment FM No. 41971626201 and does not involve any changes to financial compensation, as all subtotal and total amendment amounts are listed as $0.00. The document is approved by Mr. Ronald D. Arcalas, District Laboratory Operations Engineer, and accepted by Mr. Craig E. Dunkelberger, Principal Engineer, with distribution to Professional Services, Financial Services, and the Project Manager.

View the file

Other files

File Type Posted
00010000-81842.pdf PDF
CN-550000-C8N74-00020000.pdf PDF
CN-550000-C8N74-S0050200.pdf PDF
CN-550000-C8N74-00030000.pdf PDF
CN-550000-C8N74-00050000.pdf PDF
CN-550000-C8N74-00060000.pdf PDF
CN-550000-C8R59-00120000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REC'O JUN 282013

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 375-030-26

PROCUREMENTTASK WORK ORDER AMENDMENT FORM 02/05

FOR PROFESSIONAL SERVICES

Consultant:

Dunkelberger Engineering & Testing, Inc.

Address:

607 NW Commodity Cove, Port St. Lucie, FI 34986

Contract Number:

C8N74

(To be entered upon execution of Task Work Order Amendment) Date: 6/2812013

Amendment No. to Task Work Order No. 173 Payment FM No. (must be the same as original Task Work Order):

41971626201

Purpose of Amendment:

Time extension of work order. .~-

I~ C~~ Chock ,II ,ppnrnb~ te~" I JU -:;;;

181 The time for completion of services for the subject task work order is extended thru 11/30/2013 ~ 012013 D The subject task work order is hereby closed. Final payment for the task work order has been paid. No ad~S~1 services or charges are authorized against this task work order beyond the date of execution of this amendment. The following amoUA~emaining work order balance to be recovered from this task work order $ .

D The subject task work order is hereby canceled (no work has been performed and no payment is due).

D The total amount for services performed under this task work order is increased by $

The additional funds will be allocated to the following compensation elements described below.

D The total amount for services performed under this task work order is decreased by $ ________

The decrease in funds will be allocated to the following compensation elements described below. .

D There is no increase/decrease in the task work order amount, funds are only redistributed between compensa~~lelne1ts~~j!l{iSed compensation elements are described below. '. '.• I J

Compensation Element Description

Method of Compensation

Previous Amount

This Amendment Amount

Subtotal Check if Estimate

$O.OC D

$O.OC D

If\

$0.00 D

~~.,\oO\ jJ $0.00 D

$0.00 D

$0.00 D o Other Notes:

Page 1 subtotals

Page 2 through 5 subtotals

$O.OC $0.00

This Amendment Total

$O.OC

T.w.O.

Total

$0.00

Attachments:

Total Contract Authorizations to Date Including this Amendment

Departmental Approval:

Mr. Ronald D. Arcalas, P.E. Dist. Laboratory Operations Engineer

(name) (title)

Consultant Acceptance:

Mr. Craig E. Dunkelberger, P.E. Principal Engineer

(name) (title)

Distribution: Professional Services , Financial Services