CN-550000-BED88-00020000.pdf
PDF 213 KB Posted
- Contract number
- CA948
- Issued by
- Florida
About this file
This document is a Time Extension Letter from the Florida Department of Transportation (FDOT) issued to Kyra Solutions, Inc. (formerly Kyra Info Tech., Inc.) on May 26, 2025, regarding Contract Number BED88. The letter is signed by Rudy Powell, Jr., P.E., Chief Engineer of Operations, and addresses a contract modification for the Roadside Unit Health Monitoring System.
The original contract was executed on June 3, 2022, with an initial completion date of June 2, 2025. Due to circumstances beyond the vendor's control, FDOT is extending the contract completion time until December 2, 2025. The letter explicitly states that this time extension does not include any additional compensation, and all other terms of the original agreement remain unchanged. The vendor, represented by Ryan Patel (Chief Operating Officer), acknowledged and agreed to the extension by signing the document on May 30, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CA948-A0010000.pdf | ||
| CN-550000-CA948-W0030000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-CA948-00020000.pdf | ||
| CN-550000-CA948-S0010000.pdf | ||
| CN-550000-CA948-W0040000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Transportation
RON DESANTIS
GOVERNOR
605 Suwannee Street
Tallahassee, FL 32399-0450
JARED W. PERDUE, P.E.
SECRETARY
www.fdot.gov
May 26, 2025
Kyra Solutions, Inc. (Formerly known as Kyra Info Tech., Inc.)
Attention: Ryan Patel, Chief Operating Officer 4454 Florida National Drive Lakeland, Florida 33813
RE: Modification No. 1 Time Extension No. 1 Contract Number: BED88
Dear Mr. Patel, The Department and the Vendor entered into an agreement on June 3, 2022, whereby the Department retained the Vendor to furnish certain services in connection with the Roadside Unit Health Monitoring System . The time allotted for the completion of services expires on June 2, 2025.
Due to circumstances beyond the Contract Vendor’s control, the Department has determined it necessary to extend the time allotted for completion of services until December 2, 2025. All other terms of subject agreement and any supplements thereof will remain in full force and effect. It is noted that this letter does not include any additional compensation.
Please acknowledge receipt of this letter and agreement to the extension of time by signing and dating in the designated area below.
This “Letter of Time Extension” must be executed on or before June 2, 2025, to be in full force and effect.
Sincerely, Rudy Powell, Jr., P.E.
Chief Engineer of Operations
This will acknowledge agreement to the above letter:
Procurement Office
Vendor Signature:
Title:
Date:
Docusign Envelope ID: 230C8068-5924-406E-A318-65F85E0D8629
Chief Operating Officer
05/30/2025 | 5:55 PM EDT