CN-550000-BE626-00030000.pdf
PDF 294 KB Posted
- Contract number
- C9144
- Issued by
- Florida
About this file
This document is a Letter of Contract Term Extension from the Florida Department of Transportation (FDOT), signed by Nicola A. Liquori, CPA, SunRail Chief Executive Officer, and addressed to Jim Klimis, Operations Manager of Seminole Equipment, Inc. located in Tarpon Springs, Florida. The letter pertains to Contract Number BE626 and is dated July 31, 2019.
The letter extends the original contract term from August 30, 2019, to September 30, 2019, acknowledging that delays in completing services or work were beyond Seminole Equipment's control. The extension does not include additional compensation and explicitly maintains the Department's right to assess Liquidated Damages as originally specified in the contract. All other terms of the original contract and its supplements remain in full force and effect. The contract extension required execution by both parties on or before August 30, 2019, to be valid.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-C9144-00020000.pdf | ||
| CN-550000-C9144-00030000.pdf | ||
| CN-550000-C9144.pdf | ||
| CN-550000-C9144-00050000.pdf | ||
| CN-550000-C9144-S0010000.pdf | ||
| CN-550000-C9144-00040000.pdf | ||
| CN-550000-C9144-00060000.pdf | ||
| CN-550000-C9144-S0020000.pdf | ||
| CN-550000-C9371-00100000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Transportation
RON DESANTIS
GOVERNOR
719 S. Woodland Boulevard DeLand, Florida 32720-6834
KEVIN J. THIBAULT, P.E.
SECRETARY
www.fdot.gov
Mr. Jim Klimis, Operations Manager Seminole Equipment, Inc.
204 Tarpon Industrial Drive Tarpon Springs, Florida 34689
RE: Contract Term Extension #2 Contract Number: BE626
Dear Mr. Klimis, Pursuant to the previous “Letter of Contract Term Extension,” the Term of the Contract terminates on August 30, 2019. The Department recognizes that the delay in completing the services and/or the Work within the Initial Contract Term was beyond control of Seminole Equipment, Inc.
The Department hereby extends the Contract Term until September 30, 2019. All other terms of the subject Contract and any supplements thereof will remain in full force and effect. It is noted that this “Letter of Contract Term Extension” (hereinafter “Letter”) does not include any additional compensation. The extension of the Contract Term as outlined in this Letter shall in no way impact the Department’s ability to assess Liquidated Damages as provided for in and pursuant to the Contract.
Please acknowledge receipt of this letter and agreement to the extension of Contract Term and other conditions of this Letter by signing and dating this Letter below.
This “Letter of Contract Term Extension” must be executed on or before August 30, 2019 to be in full force and effect.
Sincerely, Jim Klimis
Operations Manager Nicola A. Liquori, CPA SunRail Chief Executive Officer Date:________________________
DocuSign Envelope ID: 7643A694-2983-4F05-B8C3-30F3D960FBA5
7/30/2019 | 2:21 PM PDT
7/31/2019 | 7:22 AM EDT
File details come from the government source that posted it. Updated .