This document is a Railroad Change Order Number 1 for a Preliminary Engineering Review, issued by the Florida Department of Transportation (FDOT) and CSX Transportation, Inc., referencing a Master Agreement originally dated September 15, 1998. The project is located in Pasco County, Florida, specifically along US 98/US 301/SR 35/SR 700 from north of Long Avenue to south of US 98, with a railroad crossing number 622704C.
The change order authorizes preliminary engineering review of plan sets for a resurfacing project within CSX right-of-way, with a total authorized amount of $30,000.00. The work is to be reimbursed using the Force Account Method under state funds (DDR - District Dedicated Revenue), with a project beginning date of July 30, 2024, and an ending date of December 31, 2050. The contract is classified as AC - RR CROSSING-PE/INSTAL (RR-XING/PE), and includes specific requirements such as E-Verify usage, Buy America compliance, and Title VI non-discrimination assurances. The funding is 100% state-funded and does not involve federal funds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CA358-00110000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
RAILROAD CHANGE ORDER NUMBER 1
725-090-04A
RAIL
OGC – 12/23
Financial Project ID Roadway Description County Roadway ID Contract ID
451236-1-57-01 US 98/US 301/SR 35/SR 700 FROM
N OF LONG AVE TO S OF US 98
Pasco 14050000
14050001
AT060
A. 1. The CSX Transportation Inc Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:
Preliminary Engineering Review of Plan Sets for Resurfacing Project Within CSX ROW Crossing # 622704C - RRPM: S 824.68
2. Exhibit A, Exhibit B, and Exhibit C are attached to the Railroad Change Order and made part of the below referenced Railroad Agreement.
3. The items of work covered by this Change Order are referenced to the Master Agreement of record dated 09/15/1998 and no Supplemental Agreement is required.
Agreement Type: Preliminary Engineering g
B. 1. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 Section .011(2) as:
a. ☐ NONREIMBURSABLE
b. ☒ REIMBURSABLE
(1) ☒ Force Account Method
(2) ☐ Lump Sum Method
(3) ☐ Third Party Contract Method
C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER
CHANGE
ORDER DESCRIPTION
PREVIOUSLY
AUTHORIZED WORK
AMOUNT(S)
NEW AUTHORIZED
WORK AMOUNT
1 PE Review $ $30,000.00
Total amount of work previously authorized………………………………………………………… $ Total amount of new work authorized by this change order…………………………………………………………………… $30,000.00 Total amount of work authorized under agreement for this Financial Project ID……………………………………… $30,000.00 PROJECT TOTAL AMOUNT OF WORK AUTHORIZED TO DATE……………………………………………………………………… $30,000.00
Examined as to provisions and participating items of cost:
Recommended: ____________________ Approved: ____________________ Date Date
Kenneth Madden
District 7 Rail Administrator Justin Hall
Director of Transportation Development
Docusign Envelope ID: B32A60FD-AD2D-4FE1-9438-6A8B53B72086
08/27/2024 | 8:19 AM EDT 08/27/2024 | 9:50 AM EDT
725-090-04A
RAIL
OGC – 12/23
EXHIBIT A
The Company shall:
1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and
2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.
OGC – 12/23
EXHIBIT B
The Company shall:
1. adhere to all Buy America requirements (23 CFR 635.410) to ensure that all manufacturing processes of steel and iron occur in the United States; and
2. ensure that prefabricated items that contain steel must also comply with Buy America; and
3. provide Buy America certifications that include correct language, project information, and the material’s delivery date.
OGC – 12/23
EXHIBIT C
The Company understands:
1. that while FHWA1273 does not apply to force account work performed by rail companies, FHWA-assistance is subject to Title VI (42 U.S.C. § 2000d et seq); and
2. requires appropriate assurances by providing an executed Title VI / Nondiscrimination Assurance, including Appendices A and E.
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
AT060
8/5/2024
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR JASON ADANK, CPA, COMPTROLLER ON 8/5/2024
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55074010706
Expansion Option: A8
Object Code: 563000
Amount: $30,000.00
Financial Project: 45123615701
Work Activity (FCT): 127
CFDA:
Fiscal Year: 2025
Budget Entity: 55150200
Category/Category Year: 088797/25
Amendment ID: W001
Sequence: 00
User Assigned ID: CO#1
Enc Line (6s)/Status: 0001/04
Total Amount: $30,000.00
Contract: AT060
Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)
Vendor Name: CSX TRANSPORTATION, INC.
Vendor ID: F546000720022
Beginning Date of This Agreement: 07/30/2024
Ending Date of This Agreement: 12/31/2050
Contract Total/Budgetary Ceiling:
Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT
Description: CO#1 PE For Resurfacing Project Within CSX ROW FPID 451236-1
Page1 of 1
To: Michael.Pokers@dot.state.fl.us
622704C / RRMP: S
824.68
Project Location Map 451236-1
CSX TRANSPORTATION – NEW PROJECT INITIATION FORM
Please provide the following information so that CSXT is able to accurately and appropriately process the project setup and billing.
Is this project associated with
Federal funds?
Is this project associated with
State funds?
Please describe the funding source for this project (i.e. INFRA, Section 130, State, County, Private, etc.).
Project Requirements:
Buy America
Additional procurement restrictions (Please describe below)
State Suspended and Debarred (Note - All federally funded projects are already monitored against the federal sus/deb listings)
Davis-Bacon (Please only check this box if this is a construction project that may be performed by an outside party)
CSX is subject to a state single audit as a recipient or subrecipient of funds (The only states that should apply here are FL or NC. FL must provide completed form DFS-A2-NS.)
Other If you selected Other, please describe below. Only complete this section if this project is associated with
Federal and/or State funds.
Project Sponsor - "Bill To" Information
Agency - Sponsor:
Billing Address:
Contact Name:
Phone:
E-mail:
Invoice Delivery Method:
Project Location:
Project Description:
Sponsor Project Ref.
Number (If applicable)
Signature of Applicant* Please sign, and e‐mail this form to the authorized CSX representative.
Name and Title of
Applicant
Signature of Applicant Date:
*By signing this form you are authorizing CSXT to incur costs and bill against this project. Should the project be canceled, CSXT will bill the Project Sponsor for the incurred costs. In the event the Project Sponsor is unresponsive for 90 days or more, the project will be closed;
and the Project Sponsor will be final billed for all project costs incurred.
Form Revision 7/18/23
If Email or Mail & Email is selected, please enter Email address(es) here:
Note: this is the agency that will be paying the invoice.
Note: this is the address to send the invoice for payment.
DDR - District Dedicated Revenue - State Funds 100%
Florida Department of Transportation
11201 N. McKinley Drive; MS 7-501, Tampa, Florida 33612
Kenneth Madden
813-975-6407
Kenneth.Madden@dot.state.fl.us
D7RailInvoices@dot.state.fl.us
US 98/US 301/SR 35/SR 700 FROM N OF LONG AVE TO S OF US 98
Milling & Resurfacing
451236-1
Kenneth Madden - Rail Administrator
No
Yes
08/27/2024 | 8:19 AM EDT