About this file
This is a Railroad Change Order No. 1 between the State of Florida Department of Transportation and CSX Transportation, Inc., located in Jacksonville, Florida. The document relates to a financial project (416735-1-57-01) involving State Road 50 (Cortez Boulevard) in Hernando County, referencing a master agreement originally dated September 15, 1998.
The change order authorizes preliminary engineering for a major construction project involving CSX rail, with an estimated cost of $30,000.00. The work is reimbursable under the Force Account Method and will be funded primarily by Federal Highway Administration (FHWA) funds, with 99% from Advance Construction NHPP federal funds and 1% from District Dedicated Revenue State Funds. The project has a beginning date of July 18, 2023, and an ending date of December 31, 2050. The change order includes specific requirements such as E-Verify usage, Buy America compliance, and adherence to Title VI non-discrimination assurances.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CA951-W0010100.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
RAILROAD CHANGE ORDER NO. 1
725-090-04B
RAIL
OGC – 1/21
Financial Project Number Road Name or Number County Name Parcel & R/W Number
FAP
Number
416735-1-57-01 SR 50 (Cortez Blvd) HERNANDO 08002-2502 1682 004 U
A. 1. The CSX Transportation Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:
Preliminary Engineering for Plans For a Major Construction Project involving CSX Rail. This Change Order includes any other work deemed necessary during this project.
NGCN 624906G RRMP: SR 799.12
2. Exhibit A, Exhibit B, and Exhibit C are attached to the Railroad Change Order and made part of the Original Railroad Agreement.
3. The items of work covered by this Change Order are referenced to an Master Agreement of record dated 9/15/1998 and no supplemental Agreement is required.
Master Type: Crossing Surface Signals Preliminary Engineering
B. 1. The Railroad Relocation Work is to conform to that shown by the railroad adjustment plans as:
a. X ATTACHED
b. INCLUDED IN THE HIGHWAY CONTRACT PLANS
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as:
a. NONREIMBURSABLE – Section .011(2)
b. X REIMBURSABLE – Section .011(2)
(1) X Force Account Method
(2) Lump Sum Method
(3) Third Party Contract Method
C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER
ITEM
NO.
ITEM UNIT UNIT
PRICE
WORK ELIMINATED (-)
QTY AMOUNT
ADDITIONAL WORK (+)
QTY AMOUNT
1 Preliminary Engineering 1 30,000.00
Sub-Totals ………………………………………………………………… $ $30,000.00 Net Cost of Construction Changes, this order ………………………... $ $30,000.00 Cost of Construction Changes, previously ordered ………………….. $ $ Net Total Cost of Construction Changes, to date…………………………………………….. $30,000.00 Contract Amount ………………………………………………………………………………… $ Estimated Cost of Work Authorized, to date………………………………………………….. $30,000.00
Examined as to provisions and participating items of cost:
Recommended: Approved: Approved:
Date Date Date
Kenneth Madden District 7 Rail Administrator
Justin Hall Director of Transportation
Development
Division Administrator N/A
Federal Highway Administration
DocuSign Envelope ID: DC712D01-2CFF-415C-AC75-F0BB0E94578F
08/03/2023 | 11:55 AM EDT 08/03/2023 | 4:40 PM EDT
725-090-04B
RAIL
OGC – 1/21
EXHIBIT A
The Company shall:
1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and
2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.
EXHIBIT B
The Company shall:
1. adhere to all Buy America requirements (23 CFR 635.410) to ensure that all manufacturing processes of steel and iron occur in the United States; and
2. ensure that prefabricated items that contain steel must also comply with Buy America; and
3. provide Buy America certifications that include correct language, project information, and the material’s delivery date.
EXHIBIT C
The Company understands:
1. that while FHWA1273 does not apply to force account work performed by rail companies, FHWA-assistance is subject to Title VI (42 U.S.C. § 2000d et seq); and
2. requires appropriate assurances by providing an executed Title VI / Nondiscrimination Assurance, including Appendices A and E.
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
ASX15
7/21/2023
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 7/21/2023
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55074010706
Expansion Option: A5
Object Code: 563000
Amount: $30,000.00
Financial Project: 41673515701
Work Activity (FCT): 127
CFDA:
Fiscal Year: 2024
Budget Entity: 55150200
Category/Category Year: 088716/24
Amendment ID: W001
Sequence: 02
User Assigned ID: CO#1
Enc Line (6s)/Status: 0001/04
Total Amount: $30,000.00
Contract: ASX15
Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)
Vendor Name: CSX TRANSPORTATION, INC.
Vendor ID: F546000720022
Beginning Date of This Agreement: 07/18/2023
Ending Date of This Agreement: 12/31/2050
Contract Total/Budgetary Ceiling:
Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT
Description: Funding for PE Review of Plans Involving CSX Crossing
Page1 of 1
To: Michael.Pokers@dot.state.fl.us
BROOKSVILLE
Highway Speed:
Crossing Angle:
Street Types:
Thru Lanes:
Aux Lanes:
Hazmat Route?
Emergency Services Route?
Emergency Notification Signs:
Crossbuck(4x4 post):
Stop Sign:
Yield Sign:
Low Ground Clearance Signs:
Exempt Signs:
Trespass Signs:
W10-1
W10-2
W10-3
W10-4
W10-11
W10-12
R3-1a
R3-2a
R8-8
R8-9
R8-10
R8-10a
R10-6
R10-6a
R11-2
R15-2P
R15-6
R15-6a
R15-7
R15-7a
R15-8
Pvt Crossing
Look Out
R8-8 w/Beacon
W3-1
W3-3
W8-1
W10-8
W10-9
W10-9P
W10-11a
W10-11b
W10-13P
W10-14P
W10-14aP
W10-15P
Slow
W10-1w/Beacon
LED Signs
Surface Installment Date:
Surface Type:
Surface Condition:
Approach:
Vehicle Reaction:
Driver Reaction:
Rail/Pad Movement:
Maintenance Responsibility:
Roadway Paved:
Tracks run down street?
Sidewalks on Crossing Approach?
Sidewalks Thru Crossing?
Crossing illuminated?
Commerical Power?
Alternative Power?
Number of Bells:
Post Mounted Flashing Lights:
Roadway Gate Count:
Pedestrian Gate Count:
Gates:
Cantilevered Flashing Over Traffic:
Cantilevered Flashing Not Over Traffic:
Intersecting Roadway?
Signalized?
Interconnection:
Preemption:
Traffic Pre-Signals?
8" Count:
12" Count:
LED Count:
Train Speed Range:
Max Time Table Speed:
Day Thru/Switch:
Night Thru/Switch:
Train Service:
Passenger Count/Day:
Train Count Date:
Main Tracks:
Train Signals?
Train Signal Proximity:
Train Detection:
Rank 2018:
Rank 2017:
Rank 2016:
SR No.:
CR No.:
US No.:
Latitude:
Longitude:
RR Company:
Division Name:
Subdivision Name:
Branch Name:
RR Milepost:
Recommended Warning Device:
Incident History:
IN CITY
PUBLIC AT GRADE Open Space
60-90 DEG
NO
YES
YES
NO
B = Vibrating
A = No reaction
A = Smooth
A = Smooth
ASPHALT
GOOD
SR-50
SR 805
799.12
BROOKSVILLE
JACKSONVILLE
CSX
25-25
NO
NO
Constant Warning Time
Not Interconnected
NO
YES
YES
NO
YES
NO
STATE
YES
NO
NO
NO
03/31/2011
District: 7RR Street: Roadway: CORTEZ BLVDCrossing No: 624906G County: Hernando
Crossbuck Sign: 4
Install - Upgrade: -- 03/26/1992 Pvmt Mrk:
24500 (2021)AADT:
Percent Trucks:
School Buses:
14 (2021)
28 (2023)
28.538300
-82.390000
CFL&G&P
Other Tracks:
2 Quad, Full Entrance, Median Gates
City: OPEN--TRACK ACTIVE
Event Recorder? N
Traffic Signals Controlling?
Backlights, LED
LED
Team Members:
Date:
Team Recommendations:
Field Review Comments:
Freight
HWY
NODoes traffic queue across the tracks?
If ther please describe here:
Not Applicable _____ Florida Single Audit _____ CSX is not subject to the Single Audit.
Federal Audit _____ (Florida Statute 215.97)
Single Audit Status ¹ ² :
CSFA # ³
5) Agency
*Phone:
Date:
Recipient. The Federal Sub-Recipient and Vendor Determination Checklist is enclosed for reference.
² CFDA Number: If CSX is subject to the Federal Single Audit, please provide the Catalog of Federal Domestic Assistance (CFDA) number.
³ CSFA Number: If CSX is subject to the Florida Single Audit, please provide the Catalog of State Financial Assistance (CSFA) number.
*Please Note: Per 2 CFR 200.425(a), CSXT can recover Federal Audit costs directly through this project.
For Audit related questions, contact GBCompliance@csx.com.
*4) Single Audit Type: Please advise if the project is subject to single audit requirements by completing the appropriate box below (complete only one box).
CSX TRANSPORTATION – GOVERNMENT BILLING DEPT
NEW PROJECT FORM
To ensure compliance with Federal requirements, please provide the following information so that CSXT may accurately and appropriately setup and handle the necessary accounting associated with the proposed project.
*1) Is the project Federally Funded?
*2) Funding Source: If the project is funded by multiple sources please provide the approximate anticipated percentage of the total project cost to be paid by each source.
*3) Project Requirements
Note: This audit is not related to the project specific audit performed by your agency.
Vendor (CFDA # Not Required)
Recipient (CFDA # )
Sub-Recipient (CFDA # )
Signature of Applicant:
Signature of Applicant Please sign, print , and e-mail this form to the authorized CSX representative
*Legal Address (1):
*Name: Federal Award #:
Date of Award:
08/03/2023 | 11:55 AM EDT
Page of
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as: