This document is a Utility Work Order Change No. 1 issued by the Florida Department of Transportation (FDOT) for a project involving Florida Power & Light (FPL) in Palm Beach County. The utility work order pertains to a lighting safety project on State Road 9, specifically the I-95 segment from SR708/Indian Town Rd. to the Palm Beach County/Martin County line. The project involves extending a distribution service line to a load center, with FDOT as the primary agency and FPL as the utility agency/owner.
The utility work order authorizes two primary work requests: WR#10660704 involves installing one pole at approximately $3,500, and WR#10669808 involves underground work including approximately 750 linear feet of underground duct/cable via directional bore at roughly $30 per foot, totaling $22,500, with an additional PMTX installation estimated at $5,000. The total authorized cost for the work is $31,000, which will be paid as a lump sum reimbursement. The work is part of a broader infrastructure improvement project aimed at enhancing electrical distribution infrastructure along the specified road segment.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .