About this file

This document is a Utility Work Order Change No. 2 issued by the State of Florida Department of Transportation (FDOT) for a utility relocation project in Palm Beach County. The project involves Florida Power & Light Company (FPL) and references an original agreement dated 2/28/1972. The document is associated with Financial Project ID 446832-1-56-01 and relates to State Road No. 80.

The utility work is nonreimbursable and involves additional costs of $1,121.00, which brings the total net cost of construction changes to $9,621.00. The utility relocation work is to conform to utility adjustment plans, which are either attached or included in the highway contract plans. The change order was processed and signed on 8/10/2021 by key FDOT personnel, including the District Utility Coordinator and District Utility Engineer/Administrator, with approval from the Federal Highway Administration.

View the file

Other files

File Type Posted
CN-550000-BE640-W0010000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

710-010-04

UTILITIES

04/10

UTILITY WORK ORDER CHANGE NO. 2

Financial Project ID: 446832-1-56-01 Federal Project ID:

County: Palm Beach State Road No.: 80

District Document No: ASN54

Utility Agency/Owner (UAO): Florida Power & Light, Co.

A.

1. The Agency is hereby authorized to observe the following changes in the plans and/or specifications to the subject Utility

Agreement, and to perform such work accordingly, further described as:

Utility Relocation

2. The items of work covered by this Work Order Change are referenced to an Agreement of record dated 2/28/1972, and no Supplemental Agreement is required.

B.

1. The Utility Relocation Work is to conform to that shown by the utility adjustment plans as:

a. ATTACHED.

b. INCLUDED IN THE HIGHWAY CONTRACT PLANS.

2. The cost of this Utility Work is:

a. NONREIMBURSABLE

b. REIMBURSABLE

(1) Force Account Method

(2) Lump Sum Method

(3) Third Party Contract Method

C.

ESTIMATED COST OF WORK DUE TO THIS CHANGE:

ITEM NO. ITEM UNIT UNIT

PRICE

WORK ELIMINATED (-) ADDITIONAL WORK (+)

QUANTITY AMOUNT QUANTITY AMOUNT

Add'l Costs $1,121.00

Sub-Totals............................................................................................... $1,121.00

Net Cost of Construction Changes, this order......................................... $1,121.00

Cost of Construction Changes, previously ordered................................. $8,500.00

Net Total Cost Construction Changes to Date.................. ...................... $9,621.00

Contract Amount...................................................................................... $9,621.00

Estimated Cost of Work Authorized to Date............................................ $9,621.00

Recommended: Approved: Approved:

Date Date Date

District Utility Coordinator District Utility Engineer/Administrator Division Administrator

Federal Highway Administration

Kelly Armstrong Arleen Dano for Kadian McLean

Typed Name Typed Name Typed Name

File details come from the government source that posted it. Updated .