CN-550000-ASH51-W0020000.pdf
PDF 176 KB Posted
- Contract number
- AS819
- Issued by
- Florida
About this file
This document is a Railroad Change Order No. 2 issued by the State of Florida Department of Transportation involving CSX Transportation, Inc. for a project located in Hillsborough County, Florida. The change order is associated with Financial Project Number 447041-1-57-01 and relates to work on State Road 600 (S Dale Mabry Highway), referencing a Master Agreement dated 8/7/1972.
The change order authorizes preliminary engineering for a turn-key design involving maintenance of traffic (MOT), crossing replacement, and dynamic envelope markings at a specific railroad crossing. The work includes removing the existing concrete/asphalt crossing and replacing it with an MBM concrete tub and new pavement markings, along with associated flagging and construction engineering inspection (CEI). The total estimated cost for this change order is $590,365.00, with the work being reimbursable under the Force Account Method. The project has a beginning date of 04/10/2020 and an ending date of 12/31/2050, with the contract type classified as a railroad crossing preliminary engineering and installation agreement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ContractBudgetExport.csv | CSV file | |
| CN-550000-AS819-W0010000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
725-090-04B
RAIL
OGC – 03/15
RAILROAD CHANGE ORDER NO. 2
Financial Project Number Road Name or Number County Name Parcel & R/W Number FAP Number
447041-1-57-01 SR 600 (S Dale
Mabry
HILLSBOROUGH 1(10130-6544) N/A
A. 1. The CSX Transportation, Inc Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:
Preliminary Engineering for Turn Key design for MOT, crossing replacement, add Dynamic Envelope markings on SR 600 S Dale Mabry Hwy at NGCN: # 626346J, RRMP A887.37, Hillsborough County, FL., Remove old
Concrete/Asphalt crossing, materials and replace with MBM concrete tub and new pavement markings.. This includes flagging, CEI and any other work deemed necessary for this project.
2. Exhibit A is attached to the Railroad Change Order and made a part of the Original Railroad Agreement.
3. The items of work covered by this Change Order are referenced to an Master Agreement of record dated 8/7/1972 and no supplemental Agreement is required.
Master Type: Crossing Surface Signals Preliminary Engineering
B. 1. The Railroad Relocation Work is to conform to that shown by the railroad adjustment plans as:
a. X ATTACHED
b. INCLUDED IN THE HIGHWAY CONTRACT PLANS
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule
Chapter 14-57 as:
a. NONREIMBURSABLE – Section .011(2)
b. X REIMBURSABLE – Section .011(2)
(1) X Force Account Method
(2) Lump Sum Method
(3) Third Party Contract Method
C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER
ITEM
NO.
ITEM UNIT UNIT
PRICE
WORK ELIMINATED (-)
QTY AMOUNT
ADDITIONAL WORK (+)
QTY AMOUNT
Replace Concrete/asphalt 20,000.00 590,365.00 Crossing with MBM Tub
Sub-Totals ………………………………………………………………… $ $590,365.00
Net Cost of Construction Changes, this order ………………………... $ $570,365.00
Cost of Construction Changes, previously ordered ………………….. $ $20,000.00
Net Total Cost of Construction Changes, to date…………………………………………….. $590,365.00
Contract Amount ………………………………………………………………………………… $
Estimated Cost of Work Authorized, to date………………………………………………….. $590,365.00
Examined as to provisions and participating items of cost:
Recommended:
Approved:
Approved:
Date
Kenneth Madden District Rail Coordinator
Richard Moss Director of Transportation
Development
Division Administrator N/A
Federal Highway Administration
DocuSign Envelope ID: 54FE46C4-485E-4419-99AF-83ABAD07EE19
7/29/2020 | 1:06 PM EDT 7/29/2020 | 1:28 PM EDT
725-090-04B
RAIL OFFICE
OGC – 03/15
EXHIBIT A
The Company shall:
1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and
2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
ASH51
7/23/2020
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 7/23/2020
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55074010706
Expansion Option: A5
Object Code: 563000
Amount: $570,365.00
Financial Project: 44704115701
Work Activity (FCT): 127
CFDA:
Fiscal Year: 2021
Budget Entity: 55150200
Category/Category Year: 088716/21
Amendment ID: W002
Sequence: 00
User Assigned ID: CO#2
Enc Line (6s)/Status: 0002/04
Total Amount: $570,365.00
Contract: ASH51
Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)
Vendor Name: CSX TRANSPORTATION, INC.
Vendor ID: F546000720022
Beginning Date of This Agreement: 04/10/2020
Ending Date of This Agreement: 12/31/2050
Contract Total/Budgetary Ceiling:
Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT
Description: Preliminary Engineering, design and install Crossing
Page1 of 1
To: Ta'rika.Green@dot.state.fl.us
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as:
File details come from the government source that posted it. Updated .