This document is a Railroad Change Order No. 2 from the State of Florida Department of Transportation involving CSX Transportation Inc. The change order is associated with Financial Project Number 447027-4-57-01, covering multiple state roads in Hernando County, including SR 50, 50A, SR 45, and SR 700. The document is referenced to a Master Agreement dated 08/07/1972 and relates to railroad crossing surface signals and preliminary engineering work.

The change order authorizes additional funds totaling $23,716.00 to cover Preliminary Engineering (PE), Construction Engineering and Inspection (CE&I), and Flagging Services for Dynamic Envelope treatments at various railroad crossings. The work includes services at Cortez Blvd, SR 50, SR 50A, SR 45/US 41, and SR 700/US 98. The funding is 100% from the agency (Florida Department of Transportation), with no railroad contribution. The project is considered reimbursable under Administrative Rule Chapter 14-57 and will be executed using the Force Account Method. The agreement runs from 03/25/2020 to 12/31/2050, with the primary purpose of reviewing design plans and providing inspection services for railroad crossing installations.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

725-090-04B

RAIL

OGC – 03/15

RAILROAD CHANGE ORDER NO. 2

Financial Project Number Road Name or Number County Name Parcel & R/W Number FAP Number

447027-4-57-01 SR 50, 50A, SR 45,

SR 700 Hernando Various N/A

A. 1. The CSX Transportation Inc. Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:

Additional funds to cover PE, CE&I, and Flagging Services for Dynamic Envelope treatments at Cortez Blvd (625307P / S 787.32), SR 50 (624906G / SR 799.12), SR 50A (624896D / SR 797.84), SR 45/US 41 (624911D / SR 806.00), and SR 700/US 98 (624893H / SR 797.30) and any other activities associated with this project.

2. Exhibit A is attached to the Railroad Change Order and made a part of the Original Railroad Agreement.

3. The items of work covered by this Change Order are referenced to an Master Agreement of record dated 08/071972 and no supplemental Agreement is required.

Master Type: Crossing Surface Signals Preliminary Engineering

B. 1. The Railroad Relocation Work is to conform to that shown by the railroad adjustment plans as:

a. ATTACHED

b. X INCLUDED IN THE HIGHWAY CONTRACT PLANS

2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule

Chapter 14-57 as:

a. NONREIMBURSABLE – Section .011(2)

b. X REIMBURSABLE – Section .011(2)

(1) XXXX Force Account Method

(2) Lump Sum Method

(3) Third Party Contract Method

C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER

ITEM

NO.

ITEM UNIT UNIT

PRICE

WORK ELIMINATED (-)

QTY AMOUNT

ADDITIONAL WORK (+)

QTY AMOUNT

Preliminary Engineering Review 7,935.00 31,651.00 Flagging & CEI

Sub-Totals ………………………………………………………………… $7,935.00 $31,651.00 Net Cost of Construction Changes, this order ………………………... $0.00 $23,716.00 Cost of Construction Changes, previously ordered ………………….. $7,935.00 $7,935.00 Net Total Cost of Construction Changes, to date…………………………………………….. $31,651.00 Contract Amount ………………………………………………………………………………… $ Estimated Cost of Work Authorized, to date………………………………………………….. $31,651.00

Examined as to provisions and participating items of cost:

Recommended: Approved: Approved:

Date

Steve C. Love District Rail Administrator

Richard Moss, PE Director of Transportation

Development

Division Administrator N/A

Federal Highway Administration

DocuSign Envelope ID: 388DEC09-9570-4871-AC5D-9622A9A00F83

11/9/2020 | 4:07 PM EST 11/9/2020 | 5:00 PM EST

725-090-04B

RAIL OFFICE

OGC – 03/15

EXHIBIT A

The Company shall:

1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and

2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.

FLORIDA DEPARTMENT OF TRANSPORTATION

FUNDS APPROVAL

ASH34

11/6/2020

CONTRACT INFORMATION

FUNDS APPROVAL INFORMATION

FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 11/6/2020

Action: Task Work Order

Reviewed or Approved: APPROVED

Organization Code: 55310000933

Expansion Option: AW

Object Code: 563000

Amount: $23,716.00

Financial Project: 44702745701

Work Activity (FCT): 127

CFDA:

Fiscal Year: 2021

Budget Entity: 55100500

Category/Category Year: 088808/21

Amendment ID: W002

Sequence: 00

User Assigned ID: CO #2

Enc Line (6s)/Status: 0002/04

Total Amount: $23,716.00

Contract: ASH34

Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)

Vendor Name: CSX TRANSPORTATION, INC.

Vendor ID: F546000720022

Beginning Date of This Agreement: 03/25/2020

Ending Date of This Agreement: 12/31/2050

Contract Total/Budgetary Ceiling:

Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT

Description: PE design plans review, flagging, CEI for installation of DEat railroad crossings.

Page1 of 1

To: Stephen.Anderson@dot.state.fl.us

ACCT. CODE : 709 - FL2632 Form Revision 09/25/20

BUY AMERICA

ESTIMATE SUBJECT TO REVISION AFTER: 10/9/2021 DOT NO.: Various

CITY: COUNTY: Hernando STATE: FL

ZONE: Florida SUB-DIV: Brooksville / Wildwood MILE POST: Various

AGENCY PROJECT NUMBER: FDOT# 447027-4-57-01

PRELIMINARY ENGINEERING:

212 Contracted & Administrative Engineering Services 6,474$

Subtotal 6,474$

CONSTRUCTION ENGINEERING/INSPECTION:

212 Contracted & Administrative Engineering Services 9,800$

Subtotal 9,800$

FLAGGING SERVICE: (Contract Labor) 70 Labor (Conductor-Flagman) 0 Days @ 350.00$ -$ 50 Labor (Foreman/Inspector) 10 Days @ 504.00$ 5,040$ 70 Additive 137.00% (Transportation Department) -$ 50 Additive 148.00% (Engineering Department) 7,459$

Subtotal 12,499$

SIGNAL & COMMUNICATIONS WORK: -$

TRACK WORK: -$

PROJECT SUBTOTAL: 28,773$

900 CONTINGENCIES: 10.00% 2,877$

PROJECT TOTAL: ***************************************************** 31,651$

CURRENT AUTHORIZED BUDGET: ***************************************************** 7,935$ TOTAL SUPPLEMENT REQUESTED: ***************************************************** 23,716$

DIVISION OF COST:

Agency 100.00% 23,716$ Railroad 0.00% -$

NOTE: Estimate is based on FULL CROSSING CLOSURE during work by Railroad Forces.

Office of Chief Engineer Public Projects--Jacksonville, Florida

Benesch - CDS Approved by: KSW CSXT Public Project Group

DATE: 10/09/20 REVISED: 01/00/00 DATE: 10/13/20

Various DESCRIPTION: PE, CE&I, and Flagging Services for Dynamic Envelope treatments at Cortez Blvd (625307P / S

787.32), SR 50 (624906G / SR 799.12), SR 50A (624896D / SR 797.84), SR 45/US 41 (624911D / SR 806.00), and SR 700/US 98 (624893H / SR 797.30).

Estimated prepared by:

This estimate has been prepared based on site conditions, anticipated work duration periods, material prices, labor rates, manpower and resource availability, and other factors known as of the date prepared. The actual cost for CSXT work may differ based upon the agency's requirements, their contractor's work procedures, and/or other conditions that become apparent once construction commences or during the progress of the work

_____ Other

*By signing this form you are authorizing CSXT to incur costs and bill against this project. Should the project be canceled, CSXT will bill the Project Sponsor for the incurred costs. In the event the Project Sponsor is unresponsive for 90 days or more, the project will be closed;

and the Project Sponsor will be final billed for all project costs incurred.

Project Location:

Sponsor Project Ref.

Number (If applicable)

Signature of Applicant Date:

Project Description:

SignatureofApplicant*
Pleasesign,ande‐mailthisformtotheauthorizedCSXrepresentative.
Onlycompletethissectionifthis
projectisassociatedwith
Federaland/orStatefunds.

CSX is subject to a state single audit as a recipient or subrecipient of funds (The only states that should apply here are FL or NC. FL must provide completed form DFS-A2-NS.)

If you selected Other, please describe below.

Name and Title of Applicant

Please describe the funding source for this project (i.e. INFRA, Section 130, State, County, Private, etc.).

Contact Name:

Phone:

E-mail:

State Suspended and Debarred (Note - All federally funded projects are already monitored against the federal sus/deb listings)

Davis-Bacon (Please only check this box if this is a construction project that may be performed by an outside party)

Project Sponsor Bill To Information

Agency - Sponsor:

Billing Address:

Project Requirements:

CSX TRANSPORTATION – NEW PROJECT INITIATION FORM

Please provide the following information so that CSXT is able to accurately and appropriately process the project setup and billing.

Is this project associated with Federal funds?

Is this project associated with State funds?

Additional procurement restrictions (Please describe below)

Buy America

Form Revision 9/6/19

NO

YES

DPTO - State - PTO

Florida Department of Transportation District 7

11201 N. NcKinley Drive MS 7-500, Tampa, Fl 32612-6456

Steve Love, District Rail Administrator

813-975-6402

Steve.Love@dot.state.fl.us

SR 50, 50A, SR 45, SR 700

PE, CE&I, and Flagging Services for Dynamic Envelope treatments at Cortez Blvd (625307P / S 787.32), SR 50 (624906G / SR 799.12), SR 50A (624896D / SR 797.84), SR 45/US 41 (624911D / SR 806.00), and SR 700/US 98 (624893H / SR 797.30) and any other activities associated with this project.

Steve Love, District Rail Administrator

11/9/2020 | 4:07 PM EST

447027-4 - Change Order #2 DE Hernando - Complete
FL2632 CEI Flag FAE KSW 20201013.pdf
Project Summary Sheet

Master Agreement Signals 8-7-72 - Nice Copy

File details come from the government source that posted it. Updated .