CN-550000-ASF88-W0070000.pdf
PDF 114 KB Posted
- Contract number
- ASU28
- Issued by
- Florida
About this file
This document is a Railroad Change Order No. 05 issued by the State of Florida Department of Transportation involving the Florida Midland Railroad, Inc. Company. The change order pertains to a project located at SR 555 at Spirit Lake Road in Polk County, Florida, and references a Master Agreement originally dated 2-22-1988. The document is associated with a railroad crossing project and involves federal highway administration oversight.
The change order authorizes additional funds of $17,966.00 for railroad support at Crossing #623053V, located at RRMP AW 846.80 on US 17 in Bartow, Polk County. The work is classified as reimbursable under the Force Account Method, with the funds covering necessary repairs and flagging coverage. The total estimated cost of construction changes to date is $946,966.00, with the current change order representing an incremental addition to the original project scope. The contract is set to run from 11/13/2019 to 11/13/2029, and the funding is approved for fiscal year 2024 under the contract type AC - RR CROSSING-PE/INSTAL.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
RAILROAD CHANGE ORDER NO. 05
725-090-04B
RAIL
OGC – 1/21
Financial Project Number Road Name or Number County Name Parcel & R/W
Number
FAP
Number
439826-1-57-01 SR 555 at Spirit Lake Road Polk 1(16030-6106) N/A
A. 1. The Florida Midland Railroad, Inc Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:
Additional Funds needed for Railroad support at Crossing #623053V, RRMP AW 846.80 at US 17, Bartow, Polk County, Florida, following necessary repairs and flagging coverage. This change order includes any other work deemed necessary for the project.
2. Exhibit A, Exhibit B, and Exhibit C are attached to the Railroad Change Order and made part of the Original
Railroad Agreement.
3. The items of work covered by this Change Order are referenced to an Master Agreement of record dated
2-22-1988 and no supplemental Agreement is required.
Master Type: Crossing Surface Signals Preliminary Engineering
B. 1. The Railroad Relocation Work is to conform to that shown by the railroad adjustment plans as:
a. ATTACHED
b. X INCLUDED IN THE HIGHWAY CONTRACT PLANS
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as:
a. NONREIMBURSABLE – Section .011(2)
b. X REIMBURSABLE – Section .011(2)
(1) X Force Account Method
(2) Lump Sum Method
(3) Third Party Contract Method
C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER
ITEM
NO.
ITEM UNIT UNIT
PRICE
WORK ELIMINATED (-)
QTY AMOUNT
ADDITIONAL WORK (+)
QTY AMOUNT
Additonal funds for 929,000.00 17,966.00 Rail Support
Sub-Totals ………………………………………………………………… $929,000.00 $17,966.00
Net Cost of Construction Changes, this order ………………………... $17,966.00 $17,966.00
Cost of Construction Changes, previously ordered ………………….. $929,000.00 $929,000.00
Net Total Cost of Construction Changes, to date…………………………………………….. $946,966.00
Contract Amount ………………………………………………………………………………… $0.00
Estimated Cost of Work Authorized, to date………………………………………………….. $946,966.00
Examined as to provisions and participating items of cost:
Recommended: Approved: Approved:
Date Date Date
Wendy Sands District Rail Administrator
Paul Simmons Modal Development Administrator
Division Administrator N/A
Federal Highway Administration
DocuSign Envelope ID: 2018DE7C-14D1-4F65-B27A-E7E3273ED377
08/30/2023 | 1:06 PM EDT 08/30/2023 | 1:12 PM EDT
725-090-04B
RAIL
OGC – 1/21
EXHIBIT A
The Company shall:
1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and
2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.
OGC – 1/21
EXHIBIT B
The Company shall:
1. adhere to all Buy America requirements (23 CFR 635.410) to ensure that all manufacturing processes of steel and iron occur in the United States; and
2. ensure that prefabricated items that contain steel must also comply with Buy America; and
3. provide Buy America certifications that include correct language, project information, and the material’s delivery date.
OGC – 1/21
EXHIBIT C
The Company understands:
1. that while FHWA1273 does not apply to force account work performed by rail companies, FHWA-assistance is subject to Title VI (42 U.S.C. § 2000d et seq); and
2. requires appropriate assurances by providing an executed Title VI / Nondiscrimination Assurance, including Appendices A and E.
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
ASF88
8/25/2023
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 8/25/2023
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55014010106
Expansion Option: A5
Object Code: 563000
Amount: $17,966.00
Financial Project: 43982615701
Work Activity (FCT): 127
CFDA:
Fiscal Year: 2024
Budget Entity: 55150200
Category/Category Year: 088716/24
Amendment ID: W007
Sequence: 00
User Assigned ID: CO#5
Enc Line (6s)/Status: 0007/04
Total Amount: $17,966.00
Contract: ASF88
Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)
Vendor Name: FLORIDA MIDLAND RAILROAD CO, LL
Vendor ID: F581758851001
Beginning Date of This Agreement: 11/13/2019
Ending Date of This Agreement: 11/13/2029
Contract Total/Budgetary Ceiling:
Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT
Description: 439826- Florida Midland, US 17, Polk County
Page1 of 1
To: Phillip.Chapman@dot.state.fl.us
| 439826-1 CO#5 |
| 2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as: |
| 439826-1 CO#5 8-30-23 |
| 439826-1 CO#5 |
| 2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as: |