CN-550000-ASF88-W0060000.pdf
PDF 225 KB Posted
- Contract number
- ASF88
- Issued by
- Florida
About this file
This document is a Railroad Change Order No. 02 issued by the Florida Department of Transportation (FDOT) for the Florida Midland Railroad, Inc., pertaining to a project on SR 555 at Spirit Lake Road in Polk County. The change order involves additional funds for railroad crossing work and is referenced to a Master Agreement dated 2-19-1988, with exhibits that outline requirements for E-Verify, Buy America provisions, and Title VI nondiscrimination assurances.
The change order authorizes additional funding of $250,000 for flagging, signals, and other necessary railroad work at two specific railroad crossings (crossing #623052N and #623053V) located at Spirit Lake Road and US 17 in Bartow, Polk County. The work is reimbursable under Administrative Rule Chapter 14-57, and a detailed quotation from Florida Midland Railroad breaks down the costs, including signal materials, field materials, labor, equipment, and railroad oversight, totaling $110,629.00. The contract is part of a broader agreement running from 11/13/2019 to 11/13/2029, with the funds approved on 5/8/2023 for the current fiscal year.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-ASF88-W0010000.pdf | ||
| CN-550000-ASF88-W0040000.pdf | ||
| CN-550000-ASF88-W0050000.pdf | ||
| CN-550000-ASF88-W0020000.pdf | ||
| CN-550000-ASF88.pdf | ||
| CN-550000-ASF88-W0030000.pdf | ||
| CN-550000-C9X41-00110000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
RAILROAD CHANGE ORDER NO. 02
725-090-04B
RAIL
OGC – 1/21
Financial Project Number Road Name or Number County Name Parcel & R/W
Number
FAP
Number
43982615701 SR 555 at Spirit Lake Road Polk 1(16030-6106) N/A
A. 1. The Florida Midland Railroad, Inc. Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:
Additional Funds for Flagging and Signals for R/R crossing #623052N, RRMP #AW 846.78 and Crossing #623053V, RRMP # AW846.80 at Spirit Lake Road and US 17, Bartow, Polk County, Florida.
Includes any other Railroad work deemed necessary for the project.
2. Exhibit A, Exhibit B, and Exhibit C are attached to the Railroad Change Order and made part of the Original
Railroad Agreement.
3. The items of work covered by this Change Order are referenced to an Master Agreement of record dated
2-19-1988 and no supplemental Agreement is required.
Master Type: Crossing Surface Signals Preliminary Engineering
B. 1. The Railroad Relocation Work is to conform to that shown by the railroad adjustment plans as:
a. ATTACHED
b. X INCLUDED IN THE HIGHWAY CONTRACT PLANS
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as:
a. NONREIMBURSABLE – Section .011(2)
b. X REIMBURSABLE – Section .011(2)
(1) Force Account Method
(2) Lump Sum Method
(3) Third Party Contract Method
C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER
ITEM
NO.
ITEM UNIT UNIT
PRICE
WORK ELIMINATED (-)
QTY AMOUNT
ADDITIONAL WORK (+)
QTY AMOUNT
PE, Flagging, Materials 469,000.00 250,000.00 Equipment
Sub-Totals ………………………………………………………………… $469,000.00 $250,000.00
Net Cost of Construction Changes, this order ………………………... $250,000.00 $250,000.00
Cost of Construction Changes, previously ordered ………………….. $469,000.00 $469,000.00
Net Total Cost of Construction Changes, to date…………………………………………….. $719,000.00
Contract Amount ………………………………………………………………………………… $0.00
Estimated Cost of Work Authorized, to date………………………………………………….. $719,000.00
Examined as to provisions and participating items of cost:
Recommended: Approved: Approved:
Date Date Date
Wendy Sands District Rail Adminsitrator
Paul Simmons Modal Development Administrator
Division Administrator N/A
Federal Highway Administration
DocuSign Envelope ID: 081236E3-E6D4-4553-8362-B88FA26E8395
05/15/2023 | 3:13 PM EDT 05/15/2023 | 4:07 PM EDT
725-090-04B
RAIL
OGC – 1/21
EXHIBIT A
The Company shall:
1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and
2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.
OGC – 1/21
EXHIBIT B
The Company shall:
1. adhere to all Buy America requirements (23 CFR 635.410) to ensure that all manufacturing processes of steel and iron occur in the United States; and
2. ensure that prefabricated items that contain steel must also comply with Buy America; and
3. provide Buy America certifications that include correct language, project information, and the material’s delivery date.
OGC – 1/21
EXHIBIT C
The Company understands:
1. that while FHWA1273 does not apply to force account work performed by rail companies, FHWA-assistance is subject to Title VI (42 U.S.C. § 2000d et seq); and
2. requires appropriate assurances by providing an executed Title VI / Nondiscrimination Assurance, including Appendices A and E.
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
ASF88
5/8/2023
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 5/8/2023
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55014010106
Expansion Option: A5
Object Code: 563000
Amount: $250,000.00
Financial Project: 43982615701
Work Activity (FCT): 127
CFDA:
Fiscal Year: 2023
Budget Entity: 55150200
Category/Category Year: 088716/23
Amendment ID: W006
Sequence: 00
User Assigned ID: CO#5
Enc Line (6s)/Status: 0006/04
Total Amount: $250,000.00
Contract: ASF88
Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)
Vendor Name: FLORIDA MIDLAND RAILROAD CO, LL
Vendor ID: F581758851001
Beginning Date of This Agreement: 11/13/2019
Ending Date of This Agreement: 11/13/2029
Contract Total/Budgetary Ceiling:
Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT
Description: 439826- Florida Midland, US 17, Polk County
Page1 of 1
To: Phillip.Chapman@dot.state.fl.us
FLORIDA CENTRAL RAILROAD CO LLC
FLORIDA MIDLAND RAILROAD CO LLC
FLORIDA NORTHERN RAILROAD LLC
3001 W Orange Ave Apopka Fl 32703 · PO Box 967 Plymouth Fl 32768 · 407-880-8500
FDOT District 1 Rail Administration April 19, 2023 Kyle Green/Phil Chapman
RE: US 17 Signal Placement 439826-1
Gentleman, Florida Midland Railroad is pleased to submit the following quotation to install new median gates and equipment at US 17 in Bartow Fl. DOT #623563V MP AW 846.8.
SIGNAL MATERIAL= $ 38,661.00
FIELD MATERIAL= $ 16,380.00 Foundations supplied by FMR
CONTROL MATERIAL= $ 2,800.00
SHIPPING = $ 5,785.00
LABOR= $ 15,876.00
EQUIPMENT= $ 3,877.00
PLANS & IN SERVICE TEST = $ 4,000.00
BORE= $ 11,000.00
MOBILIZATION= $ 2,250.00
RAILROAD OVERSIGHT= $ 10,000.00
$110,629.00
Railroad’s contractor will install median gates in their final location on account of ongoing road construction. Signal House and interface cable supplied by Florida Midland Railroad. No charges to FDOT relating to recent vehicular accident damaging equipment are included.
Best Regards, Manager of RE/Contracts
| 439826-1 CO#5 5-10-23 |
| 2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as: |
| 439826-1 CO#5 5-10-23 |
| 439826-1 CO#5 5-10-23 |
| 2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as: |
| _KNAKNPP-ASF88-W006-DIST-01-20230508-035232-KNAKNPP@dot.state.fl.us-Phillip-Chapman |
| FMR Quote US 17 Signal Placement |
File details come from the government source that posted it. Updated .