This is a Task Assignment Change Order Form for Florida Department of Environmental Protection Contract No. GM119, dated January 30, 2013. The document represents Change Order Number 7 between the Florida Department of Environmental Protection and Atkins North America, Inc., with David Larsen serving as the contractor representative and James Wolfe as the DEP Contract Manager.
The change order extends the schedule by six months, modifying the task completion date from February 6, 2013 to August 6, 2013. The original task completion date was August 7, 2008. The task amount increases from $415,400.42 to $513,633.69, reflecting an increase in cost reimbursement from $366,558.24 to $476,311.13 and fixed fees from $28,842.18 to $37,322.56. Funding is allocated under Organization Code 37, with Project Number 67749 referenced in the Change in Funding Information section. The change order was approved by the Contract Manager on January 30, 2013, and by the Director Division of Recreation and Parks on February 4, 2013.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-GM119-A1.pdf | ||
| CN-370000-GM119-A2.pdf | ||
| CN-370000-GM119-A7.pdf | ||
| CN-370000-GM119-CO001.pdf | ||
| CN-370000-GM119-T1CO3.pdf | ||
| CN-370000-GM119-A5.pdf | ||
| CN-370000-GM119-T1CO8.pdf | ||
| CN-370000-GM119-TA1CO6.pdf | ||
| CN-370000-GM119-A3.pdf | ||
| CN-370000-GM119-A6.pdf | ||
| CN-370000-GM119-T1CO1.pdf | ||
| CN-370000-GM119-T1CO4.pdf | ||
| CN-370000-GM119-TA1CO5.pdf | ||
| CN-370000-GM119.pdf | ||
| CN-370000-GM119-A4.pdf | ||
| CN-370000-GM119-T1.pdf | ||
| CN-370000-GM119-T1CO2.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .