This is a Task Assignment Change Order Form (Change Order No. 3) issued by the Florida Department of Environmental Protection dated April 30, 2018. The form documents a modification to Task Assignment GC909-1 between the Florida Department of Environmental Protection and Monroe County, with Robert Eadie serving as the contractor representative and Roger Ruiz as the DEP Contract Manager.
The change order reduces funding for Variable Inspections by $5,000.00, decreasing the task amount from $75,288.78 to $70,288.78. The completion date remains unchanged at June 30, 2018. Funding is allocated from Organizational Code 37450104000 (E.O. JD, Object Code 132500, Budget Entity 37450300, Special Category 100029) for fiscal year 2018. The change order was approved by Jennifer Vickers (Budget Representative) and Tim J. Bahr (Contractual Authority) on May 10, 2018, and copies were distributed to the Procurement Section (MS93) and Bureau of Finance & Accounting (MS78).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-GC909-A2.pdf | ||
| CN-370000-GC909-T2.pdf | ||
| CN-370000-GC909-T2CO2.pdf | ||
| CN-370000-GC909-T2CO1.pdf | ||
| CN-370000-GC909-T2CO5.pdf | ||
| CN-370000-GC909.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-GC909-T1CO1.pdf | ||
| CN-370000-GC909-T2CO3.pdf | ||
| CN-370000-GC909-T2CO4.pdf | ||
| CN-370000-GC909-ARC1.pdf | ||
| CN-370000-GC909-T1.pdf | ||
| CN-370000-GC909-T1CO2.pdf | ||
| CN-370000-GC909-T3.pdf | ||
| CN-370000-GC909-T3CO1.pdf | ||
| CN-370000-GC909-T4.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OOO-012 (Effective 09-14-2015) Page 1 of 2
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
Required Signatures: Adobe Signature
Task Assignment Number: __________________ Date: _______________ Change Order No.______________
Contractor Name: _________________________________________________________________
Contractor Representative: __________________________________________________________
DEP Contract Manager:
Description of Change (Use additional sheets if necessary):
Change in Task Amount
Item Cost Reimbursement Fee Schedule Total Original Task Amount:
Task amount prior to this change order:
Net increase/decrease in task amount:
Task amount with all change orders:
Change in Task Time
Original task completion date:
Completion date prior to this change:
Net increase/decrease in task period:
Completion date with all change orders:
GC909-1 04/30/2018 3
Monroe County
Robert Eadie
Roger Ruiz
Reduction on funding for Variable Inspections.
A net decrease of $5,000.00.
74,543.92 74,543.92
75,288.78 75,288.78
(5,000.00) (5,000.00)
70,288.78 70,288.78
06/30/18 06/30/18 (5,000.00) 06/30/18
OOO-012 (Effective 09-14-2015) Page 2 of 2
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
Change in Funding Information
Org. Code E.O. Object Code Budget Entity
Special Category
Grant # Year Amount
CONTRACTOR FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
Contract Manager Date Contract Manager Date
APPROVED:
Budget Representative Date
Contractual Authority Date cc: Procurement Section (MS93) Bureau of Finance & Accounting (MS78) - 2 copies
37450104000 JD 132500 37450300 100029 2018 $ 70,288.78
Robert B. Eadie Digitally signed by Robert B. Eadie Date: 2018.05.10 09:14:15 -04'00' Roger Ruiz Digitally signed by Roger Ruiz
Date: 2018.05.10 09:21:00 -04'00'
Jennifer Vickers Digitally signed by Jennifer Vickers Date: 2018.05.10 11:55:16 -04'00'
Tim J. Bahr Digitally signed by Tim J. Bahr Date: 2018.05.10 12:57:48 -04'00'
File details come from the government source that posted it. Updated .