CN-370000-GC773-A17.pdf

PDF 112 KB Posted

Attached to
Master Agreement FL|GC773|a31730f9f29dcfc2beb16824d7667935
Contract number
GC773
Issued by
Florida

About this file

This is Amendment No. 17 to Agency Term Contract No. GC773 between the Florida Department of Environmental Protection (the contracting state agency) and APTIM Environmental & Infrastructure, LLC (the contractor). The amendment extends the existing contract, which was originally effective February 19, 2014, for an additional term beginning February 15, 2025, and ending June 30, 2025.

The contract covers petroleum contamination site response action services. Under this amendment, the contractor shall continue to perform its duties during the extension period pursuant to the same terms and conditions established in the original contract. No changes to pricing, service scope, or other contractual provisions are specified in this amendment; all existing terms and conditions remain in effect unless specifically modified by this amendment, in which case the amendment provisions control.

View the file

Other files

File Type Posted
CN-370000-GC773-A15E1.pdf PDF
CN-370000-GC773-A18.pdf PDF
CN-370000-GC773-A5.pdf PDF
CN-370000-GC773-CMC4.pdf PDF
CN-370000-GC773-A1.pdf PDF
CN-370000-GC773-A10.pdf PDF
CN-370000-GC773-A12.pdf PDF
CN-370000-GC773-A6.pdf PDF
CN-370000-GC773-AR1.pdf PDF
CN-370000-GC773.pdf PDF
CN-370000-GC773-A11.pdf PDF
CN-370000-GC773-A16E2.pdf PDF
CN-370000-GC773-A3.pdf PDF
CN-370000-GC773-A4.pdf PDF
CN-370000-GC773-A7.pdf PDF
CN-370000-GC773-A8.pdf PDF
CN-370000-GC773-CMC2.pdf PDF
CN-370000-GC773-CMC3.pdf PDF
CN-370000-GC773-A13.pdf PDF
CN-370000-GC773-A14.pdf PDF
CN-370000-GC773-A9.pdf PDF
CN-370000-GC773-CMC.pdf PDF
CN-370000-GC773-CMC5.pdf PDF
PC-370000-GC773.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PETROLEUM RESTORATION PROGRAM

AGENCY TERM CONTRACT NO. GC773

AMENDMENT NO. 17

This Amendment to Contract No. GC773, as previously amended (Contract) is made by and between the Department of Environmental Protection (Department), an agency of the State of Florida, and APTIM ENVIRONMENTAL & INFRASTRUCTURE, LLC (Contractor), on the date last signed below.

WHEREAS, the Department entered into the Contract with the Contractor for February 19, 2014; and

WHEREAS, the parties wish to amend the Contract as set forth herein.

NOW, THEREFORE, the parties agree as follows:

1. The Contract is extended pursuant to section 287.057(13), F.S., to begin February 15, 2025, and remain in effect until June 30, 2025. The Department and the Contractor shall continue to perform their respective duties during this extension period pursuant to the same terms and conditions provided in the Contract.

2. All other terms and conditions of the Contract remain in effect. If and to the extent that any inconsistency may appear between the Contract and this Amendment, the provisions of this Amendment shall control.

The parties agree to the terms and conditions of this Amendment and have duly authorized their respective representatives to sign it on the dates indicated below.

APTIM ENVIRONMENTAL &

INFRASTRUCTURE, LLC

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

By: __________________________________

By: __________________________________

Title: ________________________________ Secretary or Designee for the Florida Department of Environmental Protection

Date: ________________________________ Date: ________________________________

Vice President

01/28/25 (see signature block)

Jason Andreotta Digitally signed by Jason Andreotta Date: 2025.02.03 16:13:34 -05'00'

File details come from the government source that posted it. Updated .