CN-370000-GC733-A12.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|GC733|d2129b28e3c784981e89c569e2e631f1
Contract number
GC733
Issued by
Florida

About this file

This is Amendment No. 12 to Agency Term Contract No. GC733, a rate increase amendment executed between the Florida Department of Environmental Protection (DEP) and Andreyev Engineering, Inc. The original contract was executed on February 27, 2014, to provide petroleum contamination site response action services in the Central Region of Florida. The amendment was signed on May 8, 2024, by Jeffery E. Eller, Vice President of Andreyev Engineering, Inc., and Jessica Kramer, Deputy Secretary of the Florida Department of Environmental Protection.

The amendment updates the rate schedule (Attachment D, Version 3.4) for services rendered under the contract, effective for new work assignments offered on or after the Rate Change Date of June 10, 2024. The rate increases apply only to new work assignments; all pre-rate change work assignments continue under the previous rates. The requested rate increases do not exceed the 5% maximum authorized under contract provision 11.B.ii, with most increases ranging from approximately 3.74% to 5.00%. The rate schedule encompasses over 400 pay items covering a comprehensive range of petroleum site remediation services, including mobilization, drilling and boring operations, soil and water sampling and analysis, well installation and abandonment, excavation and remediation, treatment systems, engineering oversight, and various professional services. The Agreed New Rates represent the maximum rates authorized for payment under the contract.

View the file

Other files

File Type Posted
CN-370000-GC733-A6.pdf PDF
CN-370000-GC733-AR1.pdf.crdownload CRDOWNLOAD file
CN-370000-GC733-A11E1.pdf PDF
CN-370000-GC733-A14.pdf PDF
CN-370000-GC733-A3.pdf PDF
CN-370000-GC733-A4.pdf PDF
CN-370000-GC733-A8.pdf PDF
CN-370000-GC733-AR1.pdf PDF
CN-370000-GC733-CMC1.pdf PDF
CN-370000-GC733-A7.pdf PDF
CN-370000-GC733-A9.pdf PDF
CN-370000-GC733-CMC.pdf PDF
CN-370000-GC733.pdf PDF
CN-370000-GC832-CMC3.pdf PDF
CN-370000-GC733-A10.pdf PDF
CN-370000-GC733-A13E2.pdf PDF
CN-370000-GC733-A15.pdf PDF
CN-370000-GC733-A2.pdf PDF
CN-370000-GC733-A5.pdf PDF
CN-370000-GC733-CCO1.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.

2.

3.

NOW THEREFORE, the parties agree as follows:

WHEREAS, the rate changes authorized will be applicable only for new work assignments offered

WHEREAS, the Department and Contractor wish to establish a date certain for the rate changes

WHEREAS, the Contractor has requested that rate increases be made to Attachment D (V3.3) entitled "Rate Schedule" in accordance with provision 11.B of the Contract; and, WHEREAS, the Contractor has submitted the detailed justification required under provision 11.B.ii to support the increase(s) requested; and, WHEREAS, the Department has reviewed this justification and agrees with the requested increase(s); and, WHEREAS, the requested increase percentage does not exceed the maximum of 5% allowed in provision 11.B.ii; and, The Agency Term Contract No. GC733 (hereinafter "Contract") between the FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION (hereinafter "Department") and ANDREYEV ENGINEERING, INC. (hereinafter "Contractor") executed on February 27, 2014, to provide petroleum contamination site response action services in the Central Region, is hereby amended.

PETROLEUM RESTORATION PROGRAM

AGENCY TERM CONTRACT NO. GC733

RATE INCREASE

AMENDMENT NO. 12

Amendment No. 12 DEP Agency Term Contract No. GC733

This amendment only changes the rates as specified on Table 1, and does not add, delete or otherwise modify any of the line items contained in the Contract.

All pre-Rate Change Date work assignments and previously offered work assignments will continue effective for New Work assignments unless and until further modified by a subsequent amendment to the Contract.

Amendment No. 12 DEP Agency Term Contract No. GC733

4.

5.

6.

Attachment D, Rate Schedule (V3.4) is hereby added to the Contract and attached hereto and made a part hereof. For all work assignments offered on or after the Rate Change Date established in this Amendment, Attachment D, Rate Schedule (V3.4) shall apply.

Data Processing Information. Prior to the Rate Change Date, the Department shall provide Contractor a copy of the tabulated rate changes herein and showing the effective Rate Change Date, within five (5) business days from the data entry date.

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK

All other terms and conditions of the Contract remain in effect. If and to the extent that any inconsistency may appear between the Contract and this Amendment, the provisions of this Amendment shall control.

Pre-existing Rate

Agreed New Rate(1)

540.00$ $567.00 378.00$ $396.90

297.00$ $311.85

400.00$ $420.00 396.90$ $416.50

378.00$ $396.90

680.40$ $714.40

356.40$ $374.20

535.68$ $562.40

654.48$ $687.20

832.68$ $874.30

215.00$ $225.75 324.00$ $340.20

713.88$ $749.50

1,416.96$ $1,487.80

832.68$ $874.30

1,368.36$ $1,436.00

675.00$ $708.50

775.00$ $813.75

590.00$ $619.50

775.00$ $813.75

Est % Rate

Change(2)

+5.00% +5.00%

+5.00%

+5.00% +4.94%

+5.00%

+5.00%

+4.99%

+4.99%

+5.00%

+5.00%

+5.00% +5.00%

+4.99%

+5.00%

2-1.

2-2.

2-4.

3-1.

3-2.

3-3.

3-4.

3-15.

3-16.

Description

3-12.

Table 1. Listed Schedule of Pay Items with Rate Changes

Drill Rig and Support Vehicles Mobilization (hollow way

DPT Rig and Support Vehicles Mobilization - > 100 miles each way miles each way

Work Trailer - > 100 miles each way

Heavy Duty/Stakebed Truck (3/4 ton +) - > 100 miles each way each way

Mobilization, Light Duty Vehicle (car or 1/2 ton truck) - > 100 miles each way

Mobilization, Light Duty Vehicle (car or 1/2 ton

Contractor Oversight for Non-Price Schedule Activities

Excavator Mobilization - > 100 miles each way

Drill Rig and Support Vehicles Mobilization (hollow stem auger, mud rotary or sonic) - > 100 miles each way

File Review Site Health & Safety Plan Notice of Discovery of Contamination Package (Initial or TPOC) Off-Site Property Access Agreement

Receptor Survey and Exposure Pathway Identification (excludes report)

Site Reconnaissance/Field Measurement Visit

Loader/Backhoe Mobilization - > 100 miles each way

Pay Item No.

1-1.

1-2.

1-3.

1-5.

3-5.

3-6.

3-7.a.

3-8.a.

3-9.a.

3-10.a.

3-11.

+5.00%

+4.94%

+4.96%

+5.00%

+5.00%

+5.00%

509.76$ $535.20

653.40$ $686.00

500.00$ $525.00

630.00$ $661.50

29.70$ $31.10

33.26$ $34.90

33.60$ $35.20

150.00$ $157.50

142.56$ $149.60

3,213.00$ $3,373.00

1,732.50$ $1,819.00

17.82$ $18.70

21.38$ $22.40

26.19$ $27.40

23.76$ $24.90

29.70$ $31.10

35.64$ $37.40

26.08$ $27.30

31.75$ $33.30

39.69$ $41.60

28.25$ $29.60

+4.94%

+4.68%

+4.88%

+4.81%

3-17.

3-18.

3-19.

3-20.

5-9.

5-10.

5-11.

Sonic Core Sampling - 5 or 10 foot (during boring) feet total depth depth

DPT Membrane Interface Probe (MIP) Equipped with PID and ECD (add-on cost to DPT base rate)

Direct Push Technology (DPT) Rig and Equipment

HSA or MR Boring, > 10 to 14 inch diameter, > 100 foot total depth

HSA or MR Boring, > 10 to 14 inch diameter, 50 to 100 foot total depth

HSA or MR Boring, > 10 to 14 inch diameter, < 50 foot total depth

HSA or MR Boring, > 6 to 10 inch diameter, > 100 foot total depth

HSA or MR Boring, > 6 to 10 inch diameter, 50 to 100 foot total depth

HSA or MR Boring, > 6 to 10 inch diameter, < 50 foot total depth total depth

100 feet feet

Drum Compactor mobilization - > 100 miles each way

Mini Excavator/Loader (BobcatTM) Mobilization - > 100 miles each way

Mini Excavator/Loader (BobcatTM

100 miles each way

5-1.a.1.

5-1.a.2.

5-1.a.3.

5-1.b.

5-2.

5-3.a.

5-5.a.

5-6.

5-7.

5-12.

5-13.

5-14.

5-15.

5-8.

+4.99%

+4.99%

+5.00%

+5.00%

+4.71%

+4.93%

+4.76%

+5.00%

+4.94%

+4.98%

+4.99%

+4.94%

+4.77%

+4.62%

+4.80%

+4.71%

+4.78%

33.90$ $35.50

39.50$ $41.40

33.90$ $35.50

39.50$ $41.40

45.30$ $47.50

45.30$ $47.50

51.00$ $53.50

62.00$ $65.10

21.38$ $22.40 28.51$ $29.90

130.68$ $137.00

32.07$ $33.60

136.08$ $142.80

33.26$ $34.90 29.70$ $31.10 31.70$ $33.20 41.75$ $43.80 47.25$ $49.60

4.00$ $4.20

6.00$ $6.30

7.00$ $7.30

8.00$ $8.40

400.00$ $420.00 400.00$ $420.00 600.00$ $630.00 175.00$ $183.70

325.00$ $341.00

6-5.

Removal and Reinstallation of 8-inch Manhole and Well Pad (well pad/manhole has been damaged or destroyed)

6-6.

6-7.

6-8.

Well Redevelopment Installation of Well Vault - 4 x 4 x 2 foot Installation of Well Vault - 2 x 2 x 2 foot

6-9.a.

6-9.b.

6-9.c.

6-9.d.

6-10.

6-11.

6-12.

6-13.

6-14.

Surface Casing - 8 inch diameter Surface Casing - 6 inch diameter

Sonic Boring, > 6 to 10 inch diameter, > 100 foot total depth

Sonic Boring, > 6 to 10 inch diameter, 50 to 100 foot total depth

Sonic Boring, > 6 to 10 inch diameter, < 50 foot total depth depth depth

Well Installation - 1 inch diameter

Sonic Boring, > 10 to 14 inch diameter, > 100 foot total depth

Sonic Boring, > 10 to 14 inch diameter, 50 to 100 foot total depth

Sonic Boring, > 10 to 14 inch diameter, < 50 foot total depth

Well Installation - 2 inch diameter (vertical)

Above Grade Well Completion

Additional Well Screen > 20 feet - 6 inch diameter

Additional Well Screen > 20 feet - 4 inch diameter

Additional Well Screen > 20 feet - 2 inch diameter

Additional Well Screen > 20 feet - 1 inch diameter

Surface Casing - 12 inch diameter Surface Casing - 10 inch diameter

Well Installation - 6 inch diameter

Well Installation - 4 inch diameter (horizontal, by trenching, not directional drilling)

Well Installation - 4 inch diameter (vertical)

Well Installation - 2 inch diameter (horizontal, by trenching, not directional drilling)

6-3.a.

6-3.b.

6-4.

6-2.b.

5-17.

5-18.

5-19.

5-20.

5-21.

5-22.

5-23.

6-1.

6-2.a.

5-16.

+4.94%

+4.93% +4.71% +4.73% +4.91% +4.97%

+5.00%

+5.00%

+4.29%

+5.00%

+5.00% +5.00% +5.00% +4.97%

+4.72%

+4.81%

+4.72%

+4.81%

+4.86%

+4.86%

+4.90%

+5.00%

+4.77% +4.88%

+4.84%

+4.77%

+4.92%

275.00$ $288.00

14.25$ $14.90

16.63$ $17.40

18.14$ $19.00

18.14$ $19.00 282.96$ $297.00 453.60$ $476.00 141.48$ $148.00

219.24$ $230.00

95.00$ $99.70 95.00$ $99.70 95.00$ $99.70 28.51$ $29.90

23.76$ $24.90

56.70$ $59.50

89.20$ $93.60

20.00$ $21.00

490.32$ $514.80

53.56$ $56.20

65.44$ $68.70

89.20$ $93.60

83.26$ $87.42

8-14.

9-1.

9-2.

9-3.

9-4.

9-5.

8-3.

8-4.

8-5.

8-7.

8-9.

8-10.

8-11.

Removal and Reinstallation of 12-inch Manhole and Well Pad (well pad/manhole has been damaged or destroyed)

Free Product Sample Collection Other Water Sampling Domestic Water Well Sampling foot depth

Removal of Well Pad and Manhole Removal of Well Vault - 4 x 4 x 2 foot Removal of Well Vault - 2 x 2 x 2 foot

7-2.

7-3.

7-4.

7-5.

7-1.

6-15.

7-6.

7-7.

8-1.

Grout and Abandon Well, > 6 inch diameter

Grout and Abandon Well, > 4 to 6 inch diameter

Grout and Abandon Well, > 2 to 4 inch diameter

Grout and Abandon Well, 1 to 2 inch diameter

Electronic Data Deliverables (EDD)

Vapor/Ambient Air Sample Collection - SUMMATM Canister (or equivalent)

Vapor/Ambient Air Sample Collection - Passive

Dosimeter, Sorbent Tube, TedlarTM Bag (or Equivalent)

Water Level or Free Product Gauging

Soil, Volatile Organic Halocarbons (EPA 8021 or

EPA 8260)

Soil, BTEX + MTBE (EPA 8021 or EPA 8260)

Soil, Used Oil/Unknown Product Group-Table D of Ch. 62-780, F.A.C., except for non-Priority Pollutant Organics (multiple methods)

Encore (25 gram) for SPLP Soil Sample Collection:

[Per Encore]. The cost will include the 25 gram Encore samples submitted to the laboratory for SPLP testing and the 25 gram Encore samples collected in the field but not submitted to the laboratory for testing (discarded).

Soil, Polycyclic Aromatic Hydrocarbons (EPA 8270 or EPA 8310)

Soil, BTEX + MTBE + VOHs (EPA 8021 or EPA 8260)

+4.73%

+4.56%

+4.63%

+4.74%

+5.00%

+4.99%

+4.93%

+4.98%

+4.93%

+5.00%

+4.74% +4.96% +4.94% +4.61%

+4.91%

+4.95% +4.95% +4.95% +4.88%

+4.80%

+4.94%

+4.93%

85.00$ $89.25

282.00$ $296.10

77.32$ $81.10

250.02$ $262.50

71.38$ $74.90

89.20$ $93.60

11.88$ $12.45 11.88$ $12.45 11.88$ $12.45 11.88$ $12.45

53.56$ $56.20

53.56$ $56.20

53.56$ $56.20

30.00$ $31.50

10.00$ $10.50

320.00$ $336.00

60.00$ $63.00

230.00$ $241.50

303.48$ $318.60

+5.00%

+5.00%

+5.00%

+5.00%

+5.00%

+4.98%

+4.80% +4.80% +4.80% +4.80%

+4.93%

+4.93%

+4.93%

9-6.

9-16.

9-17.

9-18.

9-19.

9-15.

9-7.

9-8.

9-8.a.

9-9.

9-10.

9-11.

9-12.

9-13.

9-14.

Soil, TRPH Fractionation (MADEP-EPH/VPH Method or TPHCWG Direct Method)

Soil, Total Recoverable Petroleum Hydrocarbons (FL-

PRO)

Soil, Priority Pollutant Extractable Organics-Base Neutral and Acid Extractables (EPA 8270 list [e.g., EPA 8081/8082 + EPA 8270])

Soil, Priority Pollutant Volatile Organics (EPA 8260)

Soil, Moisture Content (ASTM D2216-10)

Soil, Dry Bulk Density (ASTM D1556-07, ASTM D2167-08, ASTM D2922-01, -04, -04e, -96e1 or

ASTM D2937-10)

Soil, Organic Carbon, Total (EPA 9060 or Walkey- Black)

Soil, Synthetic Precipitation Leaching Procedure- Extraction Only (EPA1312)

Soil, Toxicity Characteristic Leaching Procedure- Extraction Only (EPA 1311)

Water, Gasoline/Kerosene Analytical Group-Table C of Ch. 62-780, F.A.C. (multiple methods)

Soil, C10-C40 Alkane Fingerprint, N-Alkanes and Isoalkanes (ASTM D3328 GC/MS)

Soil, 5 Fuel Oxygenates, MTBE, DIPE, TAME, ETBE and TBA (EPA 8260Mod, High Resolution

GC/MS)

Soil, GC/MS Full Scan, Alkanes, Isoalkanes, Cycloalkanes, Aromatics, Bicyclane, Sterane, and Terpane Biomarkers (ASTM D5739 High Resolution

GC/MS)

Soil, Lead (EPA 6010 or EPA 6020) Soil, Chromium (EPA 6010 or EPA 6020) Soil, Cadmium (EPA 6010 or EPA 6020) Soil, Arsenic (EPA 6010 or EPA 6020)

Soil, 8 RCRA Metals (EPA 6010 or EPA 6020 [Arsenic, Barium, Cadmium, Chromium, Lead, Selenium, Silver] and EPA 6020 or EPA 7471 [Mercury])

Soil, PCBs [or Aroclors] (EPA 8082)

9-24.

9-25.

9-21.

9-23.

+5.00%

+5.00%

+4.89%

+4.99%

+4.93%

+4.93%

476.28$ $500.00

51.03$ $53.50

65.44$ $68.70

89.20$ $93.60

83.16$ $87.30

41.58$ $43.60

65.44$ $68.70

85.00$ $89.20

85.00$ $89.20

282.00$ $296.00

282.00$ $296.00

77.32$ $81.10

71.28$ $74.80

11.88$ $12.45

11.88$ $12.45

11.88$ $12.45

11.88$ $12.45

+4.98%

+4.84%

+4.98%

+4.93%

+4.98%

+4.86%

+4.98%

Water, Priority Pollutant Volatile Organics [for NPDES purposes only] (EPA 624)

Water, EDB [1,2-dibromoethane or ethylene dibromide] (EPA 8260 SIM)

Water, EDB [1,2-dibromoethane or ethylene dibromide] (EPA 504.1 or EPA 8011)

Water, Polycyclic Aromatic Hydrocarbons, including 1-methylnaphthalene + 2-methylnaphthalene (EPA 610 [HPLC], EPA 625, EPA 8270 or EPA 8310)

Water, BTEX + MTBE + VOHs (EPA 601/602, EPA 624, EPA 6021 or EPA 8260)

Water, Volatile Organic Halocarbons, except EDB (EPA 8021 or EPA 8260)

Water, BTEX + MTBE (EPA 602, EPA 624, EPA 8021 or EPA 8260)

Water, PCBs [or Aroclors] (EPA 608 or EPA 8082)

Water, Total Recoverable Petroleum Hydrocarbons

(FL-PRO)

Water, Priority Pollutant Extractable Organics-Base Neutral and Acid Extractables (EPA 8270 list [e.g., EPA 8081/8082 + EPA 8270 or EPA 608 + EPA 8270)

Water, Priority Pollutant Extractable Organics-Base Neutral and Acid Extractables [for NPDES purposes only] (EPA 625 list [e.g., EPA 608 + EPA 625])

Water, Priority Pollutant Volatile Organics (EPA 8260)

Water, Used Oil/Unknown Product Group-Table D of Ch. 62-780, F.A.C., except for non-Priority Pollutant Organics (multiple methods)

Water, Cadmium, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)

Water, Arsenic, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)

Water, Lead, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)

Water, Chromium, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)

9-32.

9-26.

9-27.

9-28.

9-29.

9-30.

9-31.

9-31.a.

9-41.

9-39.

9-40.

9-33.

9-34.

9-35.

9-36.

9-37.

9-38.

+4.96%

+4.96%

+4.89%

+4.94%

+4.80%

+4.80%

+4.80%

+4.80%

+4.94%

+4.94%

23.76$ $24.90

22.68$ $23.80

11.88$ $12.45

11.88$ $12.45

23.76$ $24.90

11.88$ $12.45

11.88$ $12.45

11.88$ $12.45

11.88$ $12.45

14.25$ $14.90

15.44$ $16.20

13.50$ $14.10

13.50$ $14.10

13.50$ $14.10

13.50$ $14.10

13.50$ $14.10

20.40$ $21.40

15.75$ $16.50 9-57.

9-49.

9-50.

9-51.

9-52.

9-53.

9-54.

9-55.

9-56.

Water, Potassium, Total (EPA 200.7, EPA 6010 or

EPA 6020)

Water, Orthophosphate [as P] (EPA 300.0, EPA

300.1, EPA 365.1, EPA 365.3, EPA 9056, SM 4500-

PE or SM 4500-PF)

Water, Organic Carbon, Total (SM 5310 B, SM 5310 C or EPA 9060)

Water, Nitrite [as N] (EPA 300.0, EPA 300.1, SM 4500-NO2 B or SM 4500-NO3 F)

Water, Nitrate-Nitrite [as N] (EPA 300.0, EPA 353.2, SM 4500-NO3 E or SM 4500-NO3 F)

Water, Nitrate [as N] (EPA 300.0 or EPA 353.2)

Water, Hardness, Total [as CaCO3] (SM 2340 B or

SM 2340 C)

Water, Chloride (EPA 300.0, EPA 9056, EPA 9251, EPA 9053, SM 4500CI B, SM 4500CI C or SM

4500CI E)

Water, Ammonia [as N] (EPA 350.1, SM 4500-NH3 C, SM 4500-NH3 D, SM 4500-NH3 G or SM 4500-

NH3 H)

Water, Alkalinity [as CaCO3] (EPA 310.2 or SM 2320 B)

Water, Sodium, Total (EPA 200.7, EPA 6010 or EPA 6020)

Water, Manganese, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)

Water, Magnesium, Total (EPA 200.7, EPA 6010 or

EPA 6020)

Water, Dissolved Iron (includes filter appropriate to sample method - EPA 200.7, 200.9, 6010B, or 7380)

Water, Iron, Total (EPA 200.7, EPA 6010 or EPA 6020)

Water, Calcium, Total (EPA 200.7, EPA 6010 or

EPA 6020)

Water, Mercury, Total (EPA 245.1, EPA 6020 or

EPA 7470)

Water, Dissolved Lead (includes filter appropriate to sample method - EPA 200.7, 200.9, 6010B, or 7380)

9-48.

9-41.a.

9-42.

9-43.

9-44.

9-44.a.

9-45.

9-46.

9-47.

+4.80%

+4.94%

+4.80%

+4.80%

+4.80%

+4.80%

+4.80%

+4.80%

+4.80%

+4.56%

+4.92%

+4.44%

+4.44%

+4.44%

+4.44%

+4.44%

+4.90%

+4.76%

13.50$ $14.10

13.50$ $14.10

12.60$ $13.21

45.00$ $47.20

1,069.20$ $1,122.00

1,124.28$ $1,180.00

367.50$ $385.00

63.00$ $66.00

241.50$ $253.00

63.00$ $66.00

47.25$ $49.60

71.28$ $74.80

101.19$ $106.00

177.66$ $186.00

266.76$ $279.00

308.88$ $324.00

9-66.

9-58.

9-59.

9-60.

9-61.

9-62.

9-63.

9-64.

9-67.

9-78.

9-79.

9-80.

9-68.

9-69.

9-70.

9-71.

Water, Residue-nonfilterable [Total Suspended Solids] (SM 2540 D)

Water, Residue-filterable [Total Dissolved Solids]

(SM 2540 C)

Air, Polycyclic Aromatic Hydrocarbons (EPA Method

TO-13)

Air, Volatile Organic Aromatics (EPA Method TO- 15)

Air, Volatile Organic Compounds (EPA Method TO- 17)

Water, Sulfate (ASTM D516-02, ASTM D516-90, EPA 300.0, EPA 300.1, EPA 375.2, EPA 9038, EPA

9056 or SM 4500-SO4 C)

Air, Total Petroleum Hydrocarbons (EPA Method 18 or TO-3)

Water, Methane (EPA SOP RSK-175)

Water, EDC [1,2-dichloroethane] (EPA Method 8021 or 8260)

Water, BTEX/MTBE + Naphthalene (EPA 8260)

Water, C10-C40 Alkane Fingerprint, N-Alkanes and Isoalkanes (ASTM D3328 GC/MS)

Water, 5 Fuel Oxygenates, MTBE, DIPE, TAME, ETBE and TBA (EPA 8260Mod, High Resolution

GC/MS)

Water, GC/MS Full Scan, Alkanes, Isoalkanes, Cycloalkanes, Aromatics, Bicyclane, Sterane, and Terpane Biomarkers (ASTM D5739 High Resolution

GC/MS)

Water, Acute Bioassay-96 Hour, Estuarine + Marine, Vertebrate/Invertebrate [Vertebrate: Menidia beryllina, Meridia menidia or Menida peninsulae/Invertebrate: Mysidopsis bahia] (EPA 2006.0/2007.0)

Water, Acute Bioassay-96 Hour, Freshwater, Vertebrate/Invertebrate [Vertebrate: Pimephales promelas or Cyprinella leedsi/Invertebrate:

Ceriodaphnia dubia] (EPA 2000.0/2002.0)

Water, Heterotrophic Plate Count (SM 9215 B)

+4.76%

+4.97%

+4.94%

+4.75%

+4.69%

+4.59%

+4.90%

+4.44%

+4.44%

+4.84%

+4.89%

+4.94%

+4.96%

+4.76%

+4.76%

+4.76%

0.50$ $0.50

1.00$ $1.00

31.75$ $33.30

3.40$ $3.57

5.67$ $5.95

11.34$ $11.90

40.00$ $42.00

5.00$ $5.25

5.00$ $5.25

10.00$ $10.50

47.52$ $49.80

+5.00%

+4.80%

+0.00%

+0.00%

+4.88%

+5.00%

+4.94%

+4.94%

+5.00%

+5.00%

+5.00%10-2.c.

10-2.d.

10-7.

10-2.a.

9-76.

9-77.

10-1.a.

10-1.b.

10-1.c.

10-1.d.

10-2.b.

Additional Laboratory % Surcharge authorized in the ATC contract for 1 Day Turnaround. The quoted price should be a total of all standard costs for analysis receiving 1 Day Turnaround in each Task. Enter this price in the Quant. column for the associated task.

The rate is the % surcharge authorized in the ATC contract (% surcharge is calculated using the item price, where: $1.00 = 100%, $0.75 = 75%, ect.). This will be payable per sample per % surcharge utilizing the dollars as the number of units.

Additional Laboratory % Surcharge authorized in the ATC contract for 3 Day Turnaround. The quoted price should be a total of all standard costs for analysis receiving 3 Day Turnaround in each Task. Enter this price in the Quant. column for the associated task.

The rate is the % surcharge authorized in the ATC contract (% surcharge is calculated using the item price, where: $1.00 = 100%, $0.75 = 75%, ect.). This will be payable per sample per % surcharge utilizing the dollars as the number of units.

Excavation cubic yards

Sheet Piling Rental for > 20 feet deep Excavation

Sheet Piling Rental for > 20 feet deep Excavation

Sheet Piling Rental for > 20 feet deep Excavation

Sheet Piling Installation for > 20 feet deep Excavation

113.40$ $119.00

107.67$ $113.00

152.28$ $159.00

214.92$ $225.00

142.56$ $149.00

197.64$ $207.00

113.40$ $119.00

41.36$ $43.40

45.36$ $47.60

22.68$ $23.80

19.22$ $20.10

68.04$ $71.40 56.70$ $59.50

198.18$ $208.00

7,705.80$ $8,091.00

368.28$ $386.00

10,773.00$ $11,311.00

282.96$ $297.00

5,500.00$ $5,750.00

7,300.00$ $7,650.00

9,000.00$ $9,450.00

13,000.00$ $13,600.00

2.94$ $3.05

+4.94%

+4.95%

+4.41%

+4.69%

+4.52%

+4.74%

+4.94%

+4.93%

+4.94%

+4.94%

+4.58%

+4.94%

10-9.

10-10.

#57 Stone Pea Gravel

Clean Overburden Used As Backfill, Compaction and Testing > 300 cubic yards

Clean Overburden Used As Backfill, Compaction and

Clean Backfill Material, Compaction and Testing (includes transport) > 300 cubic yards

Clean Backfill Material, Compaction and Testing Flowable Fill Concrete and Installation

Dewatering System, up to 12 well points (includes installation)

Additional Dewatering System Well Points (2) (includes installation)

Dewatering System, up to 12 well points (includes installation)

Additional Dewatering System Well Points (2) (includes installation)

LDA Excavation and Loading With Driven Casing > 300 cubic yards

LDA Excavation and Loading With Surface Casing > 300 cubic yards

LDA Excavation and Loading With Driven Casing < 300 cubic yards

300 cubic yards

LDA Excavation and Loading Without Casing > 300 cubic yards cubic yards

Remove and Dispose Petroleum Storage Tank - > 1,000 to 5,000 gal. capacity

1,000 gal. capacity

Additional Dewatering System Well Points (2) (includes installation)

Additional Removal/Loading Cost for Concrete - > 4 inch thickness

Remove and Dispose Petroleum Storage Tank - > 10,000 gal. capacity

Remove and Dispose Petroleum Storage Tank - > 5,000 to 10,000 gal. capacity

10-11.a.

10-19.

10-20.

10-21.

10-22.

10-23.

10-17.

10-11.b.

10-12.a.

10-12.b.

10-13.

10-14.

10-15.

10-15.a.

10-15.b.

10-16.

11-3.

11-4.

12-2.

11-1.

11-2.

+4.96%

+5.00%

+4.81%

+4.99%

+4.96%

+4.55%

+4.94%

+4.79%

+5.00%

+4.62%

+3.74%

56.70$ $59.50

43.20$ $45.30 39.63$ $41.60

224.64$ $235.00

24.84$ $26.00

41.58$ $43.60

32.07$ $33.60

32.07$ $33.60

34.45$ $36.00

33.26$ $34.90

226.15$ $237.00

1.26$ $1.32

199.80$ $209.00

1.20$ $1.26

1,076.76$ $1,130.00

169.56$ $178.00

7.34$ $7.70

2.09$ $2.19

7.30$ $7.66

1.97$ $2.06 1.12$ $1.17 1.41$ $1.41 0.45$ $0.45

3,780.00$ $3,960.00

1,350.00$ $1,410.00

12-3.

12-4.

12-5.

12-6.

12-7.

In-Situ Injection Into Existing Well/Treatment Point

Direct Push Boring with In-Situ Injection Grass - Seed and Mulch Grass - Sod Crushed Lime Rock Cover - 2 inch thickness

Disposal of Petroleum Impacted Soil at a Landfill

Transport Petroleum Impacted Soil (bulk) > 100 miles

Asphalt Paving - 2 inch thickness (includes sub-base)

Additional Rental of 20 Cubic Yard Roll-Off Container

Delivery, Pick Up and Rental of 20 Cubic Yard Roll- Off Container

Transport and Disposal of Petroleum Product (bulk)

Transport and Disposal of Petroleum Product (includes drum)

Transport and Disposal of Petroleum Contact Water (bulk)

Transport and Disposal of Petroleum Contact Water (includes drum)

Disposal of Petroleum Impacted Soil at a Thermal Treatment Facility (bulk) > 450 tons

Disposal of Petroleum Impacted Soil at a Thermal

Disposal of Petroleum Impacted Soil at a Landfill (bulk) > 450 tons

Transport and Disposal of Petroleum Impacted Soil (includes drum)

Transport and Disposal of Mixed Debris Transport and Disposal of Clean Concrete

Loading, Transport and Disposal/Recycle Clean Overburden

Concrete Paving - additional 1 inch thickness

Concrete Paving - 4 inch thickness (includes sub-base)

Asphalt Paving - additional 1 inch thickness

14-1.a.

12-17.

12-18.

13-1.

13-2.

13-3.

13-4.

13-5.

13-6.

13-7.

12-8.

12-9.

12-10.

12-11.

12-12.

12-13.

12-14.

12-15.

12-16.

14-2.a.

+4.94%

+4.86% +4.97%

+4.61%

+4.67%

+4.86%

+4.77%

+4.77%

+4.50%

+4.93%

+4.80%

+4.76%

+4.60%

+5.00%

+4.94%

+4.98%

+4.90%

+4.78%

+4.93%

+4.57% +4.46% +0.00% +0.00% +4.76%

+4.44%

3,500.00$ $3,500.00

6,000.00$ $6,000.00

101.19$ $106.00

113.07$ $118.00 125.02$ $131.00

11.90$ $12.40

4,166.64$ $4,360.00

4,450.00$ $4,672.00

270.00$ $283.00

2,490.00$ $2,614.00

270.00$ $283.00

2,976.48$ $3,125.00 283.50$ $297.50

4,750.00$ $4,987.00

270.00$ $283.50

3,214.08$ $3,374.00

282.96$ $297.00

4,800.00$ $5,040.00 270.00$ $283.00

4,300.00$ $4,515.00

860.00$ $903.00

3,700.00$ $3,885.00

+4.99%

+4.81%

+4.98%

+4.81%

+4.99% +4.94%

+4.99%

+5.00%

+4.98%

+4.96%

+5.00% +4.81%

+5.00%

+5.00%

+4.36% +4.78%

+4.20%

+4.64%

16-5.

16-17.

16-6.

16-7.

16-8.

16-9.

16-10.

16-11.

16-12.

16-13.

16-14.

14-4.

14-5.

15-1.a.

15-1.b.

15-1.c.

16-1.

16-2.

16-3.

16-4.

Multi-Phase Pilot Test - Additional Time

Vapor Extraction/Aquifer Pumping Test - Additional Time

Vapor Extraction/Aquifer Pumping Test - 8 hours

Vapor Extraction Pilot Test - Additional Time Vapor Extraction Pilot Test - 8 hours

Air Sparging or Biosparging Pilot Test - Additional Time

Air Sparging or Biosparging Pilot Test - 8 hours

Groundwater Recovery System Pilot Test - Additional Time

Groundwater Recovery System Pilot Test - 8 hours

Trenching and Installation of 21 - 30 Lines Trenching and Installation of 11 - 20 Lines

System Installation/Integration/Startup - 1 Technology Component - 1-10 Additional Recovery/Treatment Points greater Than 30 (This item is used in conjunction with 15.4.c when needed)

Installation of Plumbing (and Electrical) Lines Above Ground: Per Linear Foot of Piping. Electrical lines are not counted in determination of costs.

Trenching and Installation of 1-10 Plumbing (and Electrical) Lines in Trench

Groundwater Injection System (not by direct push)

Groundwater Injection System (not by direct push)

Multi-Phase Pilot Test - 8 hours

Air Sparging/Vapor Extraction Pilot Test - Additional Time

Air Sparging/Vapor Extraction Pilot Test - 8 hours

Groundwater Treatment System Package - Medium

Air Sparging/Multiphase Extraction Pilot Test - Additional Time

Air Sparging/Multiphase Extraction Pilot Test - 8 hours

15-2.a.

15-4.d.

+0.00%

+0.00%

+4.75%

9,600.00$ $10,080.00

7,000.00$ $7,350.00 3,855.60$ $4,048.00 3,300.00$ $3,465.00 8,300.00$ $8,715.00 6,000.00$ $6,300.00

13,000.00$ $13,650.00 3,780.00$ $3,969.00 2,630.88$ $2,762.00 3,079.08$ $3,233.00 3,628.80$ $3,810.00 4,146.12$ $4,353.00

500.04$ $525.00

396.36$ $416.00

317.52$ $333.00

1,076.76$ $1,130.00

793.80$ $833.00

6,430.00$ $6,751.00

4,100.00$ $4,300.00

9,900.00$ $10,350.00

6,300.00$ $6,600.00

14,000.00$ $14,700.00

8,900.00$ $9,300.00

3,512.16$ $3,687.00

2,381.40$ $2,500.00

3,810.24$ $4,000.00

2,619.00$ $2,740.00

16-24.

16-25.

18-3.

18-4.

18-5.

18-6.

18-7.

18-8.

18-9.

18-10.

18-2.

16-26.

16-27.

17-1.

17-2.

17-3.

17-4.

17-5.

18-1.

18-11.

18-12.

18-13.

18-14.

16-18.

16-20.

16-21.

16-23.

Medium Holding Tank - 2,000 to 6,000 gal. capacity -

Supplemental System O&M Package - Add Thermox or Catox Treatment

Groundwater Treatment System - Stand Alone Large - Long Term > 6 mos.

Groundwater Treatment System - Stand Alone Large -

Groundwater Treatment System - Stand Alone Medium - Long Term > 6 mos.

Groundwater Treatment System - Stand Alone

Groundwater Treatment System - Stand Alone Small - Long Term > 6 mos.

Groundwater Treatment System - Stand Alone Small -

Large Holding Tank > 6,000 to 10,000 gal. capacity - Long Term > 6 mos.

Large Holding Tank > 6,000 to 10,000 gal. capacity -

Medium Holding Tank - 2,000 to 6,000 gal. capacity - Long Term > 6 mos.

System O&M Package - Extra Large System O&M Package - Large System O&M Package - Medium System O&M Package - Small SVE System Package - Medium AS/MPE System Package - Medium AS/MPE System Package - Medium MPE System Package - Medium MPE System Package - Medium AS/SVE System Package - Medium Air Sparge System Package - Medium

Groundwater Treatment System Package - Medium

Air Sparge System - Small - Long Term > 6 mos.

Air Sparge System - Medium - Long Term > 6 mos.

+5.00%

+5.00%

+4.99% +5.00% +5.00% +5.00% +5.00% +5.00% +4.98% +5.00% +4.99% +4.99%

+4.99%

+4.96%

+4.88%

+4.94%

+4.94%

+4.99%

+4.88%

+4.55%

+4.76%

+5.00%

+4.49%

+4.98%

+4.98%

+4.98%

+4.62%

5,500.00$ $5,775.00

3,500.00$ $3,675.00

4,642.92$ $4,850.00

5,000.40$ $5,250.00

6,368.76$ $6,680.00

4,350.00$ $4,550.00 2,950.00$ $3,090.00

6,000.00$ $6,300.00

4,100.00$ $4,300.00 7,500.00$ $7,850.00 5,300.00$ $5,550.00

4,100.00$ $4,300.00

3,850.00$ $4,040.00

7,300.00$ $7,665.00

3,900.00$ $4,090.00

5,500.00$ $5,750.00

6,800.00$ $7,100.00

666.36$ $699.00

737.64$ $774.00

1,142.64$ $1,199.00

453.60$ $476.00

680.40$ $714.00

4,166.64$ $4,370.00

4,642.92$ $4,875.00

+4.99%

18-22.

18-20.

18-15.

18-16.

18-18.

Thermox/Catox Off Gas Treatment - Add On - Small -

Carbon Off Gas Treatment - Add On - Large - Long Term > 6 mos.

Carbon Off Gas Treatment - Add On - Medium - Long Term > 6 mos.

Groundwater Treatment - Add On - Large - Long Term > 6 mos.

Groundwater Treatment - Add On - Medium - Long Term > 6 mos.

Groundwater Treatment - Add On - Small - Long Term > 6 mos.

Groundwater Treatment - Add On - Large - Short

Groundwater Treatment - Add On - Medium - Short

Groundwater Treatment - Add On - Small - Short MPE System - Large - Long Term > 6 mos.

MPE System - Medium - Long Term > 6 mos.

MPE System - Small - Long Term > 6 mos.

AS/SVE System - Large - Long Term > 6 mos.

AS/SVE System - Medium - Long Term > 6 mos.

AS/SVE System - Small - Long Term > 6 mos.

Air Sparge System - Large - Long Term > 6 mos.

Carbon Off Gas Treatment - Add On - Large - Short

Carbon Off Gas Treatment - Add On - Medium -

Carbon Off Gas Treatment - Add On - Small - Short

Thermox/Catox Off Gas Treatment - Add On -

18-29.

18-30.

18-31.

18-32.

18-33.

18-34.

18-35.

18-36.

18-37.

18-23.

18-24.

18-25.

18-26.

18-27.

18-28.

18-39.

18-40.

18-41.

18-42.

+4.89%

+4.60% +4.75%

+5.00%

+4.88% +4.67% +4.72%

+4.88%

+4.94%

+5.00%

+4.87%

+4.55%

+4.41%

+5.00%

+5.00%

+4.46%

+4.90%

+4.93%

+4.93%

+4.94%

+4.94%

+4.88%

6,191.64$ $6,500.00

3,571.56$ $3,750.00

4,344.84$ $4,560.00

6,429.24$ $6,750.00

4,500.00$ $4,725.00

4,100.00$ $4,300.00

5,000.00$ $5,250.00

5,500.00$ $5,775.00

7,000.00$ $7,350.00

6,510.00$ $6,800.00

6,900.00$ $7,240.00

5,700.00$ $5,980.00

7,400.00$ $7,770.00

7,000.00$ $7,350.00

9,000.00$ $9,400.00

8,700.00$ $9,100.00

2,023.92$ $2,125.00 832.68$ $874.00 595.08$ $624.00

1,134.00$ $1,190.00 1,247.40$ $1,309.00

653.40$ $686.00

1,547.64$ $1,625.00

832.68$ $874.00 1,487.16$ $1,561.00

+5.00%

+4.44%

19-8.

19-9.

19-10.

18-43.

18-44.

18-45.

18-46.

18-57.

18-58.

19-1.

19-3.

19-4.

19-5.

19-6.

19-7.

18-56.

18-47.

18.48.

18-49.

18-50.

18-51.

18-52.

18-53.

18-54.

18-55.

Pilot Test Report Pilot Test Plan

Natural Attenuation or Post RA Monitoring Report, Annual

Natural Attenuation or Post RA Monitoring Report, Quarterly or Non-Annual

Level 2 Natural Attenuation Monitoring Plan Receptor and Exposure Pathway Report

Soil Vapor Extraction (SVE) System - Large - Short

Soil Vapor Extraction (SVE) System - Medium - Long Term > 6 Months

Supplemental Site Assessment Report General Site Assessment Report Soil Source Removal Report

Air Sparge/Multiphase Extraction (AS/MPE) System - Large - Long Term > 6 Months

Air Sparge/Multiphase Extraction (AS/MPE) System -

Air Sparge/Multiphase Extraction (AS/MPE) System - Medium - Long Term > 6 Months

Air Sparge/Multiphase Extraction (AS/MPE) System -

Air Sparge/Multiphase Extraction (AS/MPE) System - Small - Long Term > 6 Months

Air Sparge/Multiphase Extraction (AS/MPE) System -

Soil Vapor Extraction (SVE) System - Large - Long Term > 6 Months

Soil Vapor Extraction (SVE) System - Medium -

Soil Vapor Extraction (SVE) System - Small - Long Term > 6 Months

Soil Vapor Extraction (SVE) System - Small - Short

Thermox/Catox Off Gas Treatment - Add On - Large - Long Term > 6 mos.

Thermox/Catox Off Gas Treatment - Add On - Medium - Long Term > 6 mos.

Thermox/Catox Off Gas Treatment - Add On - Small - Long Term > 6 mos.

Thermox/Catox Off Gas Treatment - Add On - Large -

+4.60%

+4.99% +4.96% +4.86% +4.94% +4.94%

+4.99%

+5.00%

+4.96% +4.97%

+4.98%

+5.00%

+4.95%

+4.99%

+5.00%

+4.88%

+5.00%

+5.00%

+5.00%

+4.45%

+4.93%

+4.91%

14,742.00$ $15,470.00 18,711.00$ $19,640.00

1,643.76$ $1,725.00

3,175.20$ $3,333.00

5,670.00$ $5,950.50

9,752.40$ $10,200.00

3,969.00$ $4,160.00

773.28$ $811.00

3,095.28$ $3,250.00 356.40$ $374.00

1,963.44$ $2,061.00

3,690.36$ $3,874.00 1,308.96$ $1,374.00

653.40$ $686.00 567.00$ $595.00 297.00$ $311.00 773.28$ $811.00 169.56$ $178.00 124.20$ $130.00 113.40$ $119.00 107.73$ $113.00 107.73$ $113.00

96.39$ $101.00 85.05$ $89.00 68.04$ $71.00 73.71$ $77.00 62.37$ $65.00 50.76$ $53.00

169.56$ $178.00 152.28$ $159.00

152.28$ $159.00

152.28$ $159.00

680.40$ $710.00

+4.94%

+4.97%

+4.98% +4.97% +4.99% +4.94% +4.71% +4.88% +4.98% +4.67% +4.94% +4.89% +4.89% +4.78% +4.64% +4.35% +4.46%

19-20.

19-21.

19-22.

19-23.

19-24.

19-25.

20-9.

20-10.

20-11.

21-1.

19-17.

19-11.

19-12.

19-13.

19-14.

19-15.

19-16.

20-8.

19-26.

19-27.

20-1.

20-2.

20-3.

20-4.

20-5.

20-6.

20-7.

19-18.

19-19. Remedial Action Startup Report

As-Built Drawings (P.E. Sealed red lined modifications)

Professional Geologist (Key) Professional Engineer (Key) Laborers and Security Guards Administrative Draftsperson Field Technician (Key)

Construction Drawings and Specs Report

P.E. Project Oversight for Remediation Technology Pilot Testing

P.G. Field Oversight of Well Installation (Use hourly rate on site specific basis)

P.G. Field Oversight of Drilling and Boring and Soil- Boring Logging (Use hourly rate on site specific basis)

Level 1 Remedial Action Plan

Level 4 Limited Scope Remedial Action Plan or RAP Modification Plan

Level 3 Limited Scope Remedial Action Plan or RAP Modification Plan

Level 2 Limited Scope Remedial Action Plan or RAP Modification Plan

Level 1 Limited Scope Remedial Action Plan or RAP Modification Plan

Level 2 Remedial Action Plan

Assistant Scientist/Technical Specialist Scientist/Technical Specialist (Key) Hydrogeologist/Modeler (Key) Geologist/Geoscientist (Key) Engineer (Key) Project Manager (Key) Program Manager (Key) Interim Assessment Report Well Abandonment/Site Restoration Report Free Product Recovery Report Remedial Action Interim Report Remedial Action General Report Operation & Maintenance Annual Report

Operation & Maintenance Report, Quarterly or Non- Annual

Letter/NPDES Report

21-2.

21-3.

21-4.

21-5.

+4.94%

+4.97%

+4.95%

+4.59%

+4.81%

+4.88%

+5.00%

+4.22% +4.41% +4.98% +4.41%

+4.41%

+4.41%

+4.35%

+4.96%

680.40$ $710.00

1,020.60$ $1,071.00

1,360.80$ $1,428.00

1,701.00$ $1,786.00

1,190.16$ $1,240.00

340.20$ $357.00

509.76$ $535.00

396.36$ $416.00

680.40$ $714.00

396.36$ $416.00

396.36$ $416.00

+4.95%

P.G. Review and Certification of Sufficiency of Engineering Controls Limited to Permanent, Impermeable Surface or Top Two Feet of Clean Fill with Monitoring and Maintenance Recommendations Required for a Conditional NFA

P.E. Review and Certification of Sufficiency of Engineering Controls (other than permanent, impermeable surface or top two feet of clean fill), with Monitoring and Maintenance Recommendations Required for a Conditional NFA

P.E. Project Oversight for Remediation System Operation and Maintenance

P.E. Project Oversight for Short Term or Episodic Remediation System Operation - Weekly Basis

P.E. Project Oversight for Remediation System Integration and Startup - Extra Large System

P.E. Project Oversight for Remediation System Integration and Startup - Large System

P.E. Project Oversight for Remediation System Integration and Startup - Medium System

P.E. Project Oversight for Remediation System Integration and Startup - Small System

P.G. or P.E. Review, Evaluation and Certification of a Soil Source Removal Report That Includes a Recommendation for NFA

P.G. Review, Evaluation and Certification of Plans and Project Oversight for Installation of Engineering Controls Limited to Permanent, Impermeable Surface or Top Two Feet of Clean Fill Required for a Conditional NFA

P.E. Design and Certification of Plans and Project Oversight of Installation for Engineering Controls (other than permanent, impermeable surface or top two feet of clean fill) required for a conditional NFA

21-11.

21-12.

21-13.

21-6.a.

21-6.b.

21-6.c.

21-6.d.

21-7.b.

21-8.

21-9.

21-10.

+4.96%

+4.96%

+4.35%

+4.94%

+4.94%

+5.00%

+4.19%

+4.96%

+4.94%

396.36$ $416.00

396.36$ $416.00

396.36$ $416.00

396.36$ $416.00

396.36$ $416.00

396.36$ $416.00

509.76$ $535.00

509.76$ $535.00

680.40$ $714.00

680.40$ $714.00

680.40$ $714.00

849.96$ $892.00

680.40$ $714.00

623.16$ $654.00

453.60$ $476.00

+4.96%

+4.96%

+4.96%

+4.96%

+4.96%

+4.96%

+4.95%

+4.95%

+4.94%

+4.94%

+4.94%

+4.95%

21-32.

21-35.

21-36.

P.E. Review, Evaluation, and Certification of Annual PARM Report

P.E. Review, Evaluation, and Certification of Construction Drawings

P.E. Review, Evaluation and Certification of a Level 1 Remedial Action Plan

P.E. Review, Evaluation and Certification of a Pilot Test Report

P.G or P.E. Review, Evaluation and Certification of an Annual Natural Attenuation Monitoring Report

Notes:

P.E. Review, Evaluation and Certification of an Annual Operation and Maintenance Report

P.E. Review, Evaluation and Certification of a Non- Annual Natural Attenuation or Post RA Monitoring Report That Includes a Recommendation for NFA or a Recommendation to Modify the Approved Monitoring Plan

P.E. Review, Evaluation and Certification of a Level 2 Natural Attenuation Monitoring Plan

P.G. or P.E. Review, Evaluation and Certification of a Receptor and Exposure Pathway Report

P.G. or Qualified P.E. Review, Evaluation and Certification of a Supplemental Site Assessment Report

P.G. or Qualified P.E. Review, Evaluation and Certification of a General Site Assessment Report

P.E. Review, Evaluation and Certification of a Level 4 Limited Scope Remedial Action Plan or RAP Modification Plan

P.E. Review, Evaluation and Certification of a Level 3 Limited Scope Remedial Action Plan or RAP Modification Plan

P.E. Review, Evaluation and Certification of a Level 2 Limited Scope Remedial Action Plan or RAP Modification Plan

P.E. Review, Evaluation and Certification of a Level 2 Remedial Action Plan

21-15.

21-16.

21-17.

21-18.

21-19.

21-20.

21-22.

21-23.

21-24.

21-26.

21-27.

21-28.

+4.94%

+4.95%

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK

(1) The Agreed New Rate(s) shall be effective on and after the Rate Change Date as indicated for table labeled Department Data Processing Information below.

(2) The column indicating estimated Percentage Rate Change is for informational purposes only and shall not supersede the actual Agreed New Rate. The Agreed New Rate is the maximum rate authorized for payment.

File details come from the government source that posted it. Updated .