Change Order and Professional Services Proposal Summary
This is Change Order No. 01 to Contract DC813 issued by the Florida Department of Environmental Protection (FDEP), Bureau of Design and Construction for construction services at Grassy Key State Park. The contract is held by WilsonMiller/Chris E. Brockmeier, P.E., with vendor contact Chris E. Brockmeier. The change order was sent to the Federal Energy Regulatory Administration (FERC) on April 4, 2009, and signed by authorized representatives from FDEP and WilsonMiller on March 23, 2009 and March 20, 2009, respectively.
The change order authorizes additional work for the Grassy Key Development project, specifically for site work, utilities, and new housing, including additional surveying of wetland lines and flagged trees per FDOT right-of-way exclusion application requirements, and modular home FACE stamped plans for City submittal and ACAD conversion. The total fixed price cost change is $8,950.00, with a net change of $8,950.00, bringing the present contract sum from $61,925.00 to $70,875.00. The original task assignment amount was $61,925.00. Construction completion is set for 60 days after the project's completion date but shall not exceed the contract expiration. The encumbrance information indicates project code 67907 with a total authorized amount of $8,950.00.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .