This document is a Task Assignment Change Order from the Florida Department of Environmental Protection (FDEP) for Dodstone Architects, Inc., involving park improvements at Colt Creek State Park. The change order is associated with Contract No. CN669 and specifically addresses modifications to Task Assignment No. 1, focusing on design and permitting services for updating horse barn facilities according to NFPA guidelines.
The change order authorizes an additional $24,031.86 to the existing contract, bringing the total project cost from $975,890.18 to $999,922.04. The scope includes developing a comprehensive sprinkler system for the horse barn, involving multiple design phases from 60% to 100% construction documents, permitting services, bidding support, and construction administration. The work will be performed by Dodstone Architects and McGinniss & Fleming, with tasks including developing fire protection system drawings, updating cost estimates, responding to permit and bid questions, and reviewing shop drawings. The project's original end date remains unchanged at 04/26/2028, and the change order removes three interim site visits to maintain the overall project fee under $1 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN669.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN669 1 1 61442C
Park Improvements
Dodstone Architects, Inc.
Jodie Dodson, AIA (850) 656-7326 jdodson@dodstone.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Change order to provide additional design and permitting services to address updated NFPA guidelines for the construction of horse barns and removes subtasks 11i, 13e, & 14e from initial TA, per attached proposal dated July 23, 2024.
$ 9,073.00 $ 966,817.18 $ 975,890.18 $ 9,073.00 $ 966,817.18 $ 975,890.18
$ 0.00 $ 24,031.86 $ 24,031.86 $ 9,073.00 $ 990,849.04 $ 999,922.04
10/20/2023
04/26/2028
04/26/2028
04/26/2028
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.08.02 16:18:19 -04'00'
Terry McCullum, Jr. Terry McCullum Jr.
Digitally signed by Terry McCullum Jr.
Date: 2024.08.02 16:28:38 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.08.07 10:07:46 -04'00'
Jodie Dodson, AIA Joel L Dodson Digitally signed by Joel L Dodson Date: 2024.08.08 10:27:32 -04'00'
Mara Gambineri Mara Gambineri Digitally signed by Mara Gambineri Date: 2024.09.04 14:48:08 -04'00'
61442C 37503000273 080039/23 000286 U3200 134000 AD $ 24,031.86
$ 24,031.86
Colt Creek State Park
Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211
July 23,2024
Mr. Terry McCullum Design Project Manager Florida Department of Environmental Protection Bureau of Design & Construction 3900 Commonwealth Blvd. MS 520 Tallahassee, Florida 32399
Re: Colt Creek State Park Trail Improvements and Headquarters Development
CN669 – TA01
CO1 – Sprinkler System design for the Barn
Mr. McCullum
The following Change Order will cover the costs associated with providing a sprinkler system per NFPA 150 for the horse barn. This system is anticipated to include sprinklers and piping, fire water pump, fire water storage tank, fire alarm system, and a diesel generator for emergency power to the pump.
To keep the overall product fee under 1 million, we have also removed three site visits from the Construction Administration phase. Those include the following:
Subtask 11i Interim Site Visit 9 – Architectural deduct of $2,800.93 Subtask 13e Interim Site Visit 5 – Mech/Plumb deduct of $2,182.65 Subtask 14e Interim Site Visit 5 – Electrical deduct of $2,182.65
Our approach to the project would be as follows:
Subtask 4h – Construction Document Phase (60%) – Barn Sprinkler System Description: MFE will develop the fire protection system for the Horse Barn to the 60% Construction Document level. Dodstone will revise the horse plan as required to accommodate the additional equipment.
Deliverables:
• Inclusion of sprinkler system within drawing set, developed to a 60% CD level. pdf
• Updated Opinion of Probable Cost to include projected cost of barn sprinkler system, pdf
Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4h
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Dodstone Architects Principal $172.43 2 $344.86 Registered Architect $140.81 10 $1,408.10 Graduate Architect $90.48 15 $1,357.20
$3,110.16
McGinniss&Fleming Principal/PE $125.73 40 $5,029.20 Engineer II $90.35 40 $3,614.00 Engineer I $75.17 24 $1,804.08 Technician $47.70 4 $190.80
$10,638.08
Subtask 4h Construction Document Phase (60%)- Barn Sprinkler System$13,748.24
Construction Document Phase (60%)- Barn Sprinkler System
Subtask 4h Total:
$13,748.24
Subtask 5h – Construction Document Phase (90%) – Barn Sprinkler System Description: MFE will develop the fire protection system for the Horse Barn to the 90% Construction Document level.
Deliverables:
• Inclusion of sprinkler system within drawing set, developed to a 90% CD level. pdf
• Updated Opinion of Probable Cost to include projected cost of barn sprinkler system, pdf
Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 5h Total:
$11,564.13
Subtask 6c – Construction Documents Phase (100%) – Barn Sprinkler System Description: MFE will develop the fire protection system for the Horse Barn to a level sufficient for use in acquiring bids and a construction permit.
Deliverables:
• Inclusion of sprinkler system within 100% Construction Documents. pdf
• Updated Opinion of Probable Cost to include projected cost of barn sprinkler system, pdf
Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 5h
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Dodstone Architects Principal $172.43 1 $172.43 Registered Architect $140.81 10 $1,408.10 Graduate Architect $90.48 15 $1,357.20
$2,937.73
McGinniss&Fleming Principal/PE $125.73 24 $3,017.52 Engineer II $90.35 40 $3,614.00 Engineer I $75.17 24 $1,804.08 Technician $47.70 4 $190.80
$8,626.40
Subtask 5h Construction Document Phase (90%) - Barn Sprinkler System$11,564.13
Construction Document Phase (90%) - Barn Sprinkler System
Subtask 6c Total:
$2,522.07
Subtask 7l – Permitting Services related to Barn Sprinkler System Description: Dodstone & MFE will respond in writing to any permitting questions or comments related to the sprinkler system received from the permitting office. Any necessary revisions to the drawings or specifications in response to those questions will be provided.
Deliverable:
• Responses to permit comments, addenda clarification, or plan/specs update, pdf Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 7l Total:
$1,077.61
Subtask 8d – Bidding Services related to Barn Sprinkler System Description: Dodstone & MFE will respond in writing to any bid questions or comments received prior to the cut-off date established by BDC for questions relating to the sprinkler system. Any necessary revisions to the drawings or specifications in response to those questions will be provided.
Deliverable:
Subtask 6c
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Dodstone Architects Principal $172.43 0.5 $86.22 Registered Architect $140.81 1 $140.81 Graduate Architect $90.48 3 $271.44
$498.47
McGinniss&Fleming Principal/PE $125.73 6 $754.38 Engineer II $90.35 8 $722.80 Engineer I $75.17 6 $451.02 Technician $47.70 2 $95.40
$2,023.60
Subtask 6c Construction Document Phase (100%) -Barn Sprinkler System$2,522.07
Construction Document Phase (100%) -Barn Sprinkler System
Subtask 7l
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Dodstone Architects Principal $172.43 1 $172.43 Registered Architect $140.81 4 $563.24 Graduate Architect $90.48 1 $90.48
$826.15
McGinniss&Fleming Principal/PE $125.73 2 $251.46 $251.46
Subtask 7l Permitting Services related to Barn Sprinkler System $1,077.61
Permitting Services related to Barn Sprinkler System
• Responses to bidder’s questions, addenda clarification, or plan/specs update, pdf Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 8d Total:
$1,329.07
Subtask 10c: Construction Administration – Barn Sprinkler System Description: The design team shall review electronically submitted shop drawings and respond in writing to RFI’s related to the sprinkler system. Our understanding is that BDC will be self-performing the pay application reviews, therefore that service is excluded.
Deliverable:
• Responses to Contractor’s Requests for Information (RFI), Reviewed Contractor Shop Drawings, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 10c Total:
$956.97
Subtask 8d
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Dodstone Architects Principal $172.43 1 $172.43 Registered Architect $140.81 4 $563.24 Graduate Architect $90.48 1 $90.48
$826.15
McGinniss&Fleming Principal/PE $125.73 4 $502.92 $502.92
Subtask 8d Bidding Services related to Barn Sprinkler System $1,329.07
Bidding Services related to Barn Sprinkler System
Subtask 10c
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Dodstone Architects Principal $172.43 1 $172.43 Registered Architect $140.81 2 $281.62
$454.05
McGinniss&Fleming Principal/PE $125.73 4 $502.92 $502.92
Subtask 10c Construction Administration - Barn Sprinkler System $956.97
Construction Administration - Barn Sprinkler System
We agree to complete the work as outlined in the proposal for the following lump sum amounts:
Change Order Total: $24,031.86
Project Schedule Summary:
These services will be submitted along with the previously scheduled delivery dates.
Client’s Responsibilities The Client and/or User shall provide the following:
1. Full information about the objectives, schedule, constraints and existing conditions of the Project.
2. Establishment of a construction budget with reasonable contingencies that meets the Project
Requirements.
3. Prompt responses to questions issued by DG regarding information necessary to complete the work on schedule.
4. Access to the site as necessary to perform the work (to be coordinated in advance with Park Staff).
5. Provide any existing information available on file regarding the existing adjacent buildings, past upgrades and/or renovations, on site utility data etc.
6. Provide a copy of DEP’s latest CAD Guidelines/Standards.
7. Provide copies of any prior communication and coordination with the State’s Historic Preservation
Department regarding this project or this site, if any.
8. Notification of any deliverables deemed unsatisfactory by DEP must be transmitted in writing to DG within
20 consecutive days of receipt of that deliverable. After that time frame deliverables are assumed approved by DEP.
Summary Provider Base Service Additional
Service Subtotal Reimb. Total
DS $3,110.16 $13,748.24 $13,748.24
MFE $10,638.08
DS $2,937.73 $11,564.13 $11,564.13
MFE $8,626.40
DS $498.47 $2,522.07 $2,522.07
MFE $2,023.60
DS $826.15 $1,077.61 $1,077.61
MFE $251.46
DS $826.15 $1,329.07 $1,329.07
MFE $502.92
DS $454.05 $956.97 $956.97
MFE $502.92
DS -$2,800.93 -$2,800.93 ($2,800.93)
DS -$422.43 -$2,182.65 ($2,182.65)
MFE -$1,760.22
DS -$422.43 -$2,182.65 ($2,182.65)
MFE -$1,760.22
Design Phases 4h, 5h,6c $27,834.44 $0.00 $27,834.44 $0.00 $27,834.44 Bidding & Permitting 7l, 8d $2,406.68 $0.00 $2,406.68 $0.00 $2,406.68 CA 10c -$6,209.26 $0.00 -$6,209.26 $0.00 -$6,209.26
$24,031.86 $0.00 $24,031.86 $24,031.86
Subtask 4h
Subtask 5h
CHANGE ORDER 1
Construction Document Phase (60%)- Barn Sprinkler System Construction Document Phase (90%) - Barn Sprinkler System
Change Order 1 Total
Subtask 6c Construction Document Phase (100%) -Barn Sprinkler System
Subtask 7l Permitting Services related to Barn Sprinkler System
Subtask 8d Bidding Services related to Barn Sprinkler System
Subtask 10c Construction Administration - Barn Sprinkler System
Subtask 11i Interim Site Visit 9 - Architectural
Subtask 13e Interim Site Visit 5 - Mech/Plumb
Subtask 14e Interim Site Visit 5 - Electrical
Base Services Additional Services Subtotal Reimb. Total
$467,725.99 $499,091.19 $966,817.18 $9,073.00 $975,890.18 $24,031.86 $0.00 $24,031.86 $0.00 $24,031.86
$0.00 $0.00 $0.00 $0.00 $0.00 $491,757.85 $499,091.19 $990,849.04 $9,073.00 $999,922.04
PROJECT TOTAL
Original Contract (Phase 1) Change Order 1
Project Total
Summary
Miscellaneous Provisions
1. DG shall have no responsibility for the identification, discovery, presence, handling, removal or disposal of, or exposure of persons to, hazardous materials.
2. All deliverables are electronic unless specifically noted otherwise.
3. Procurement of a building permit is not included.
4. Any services provided beyond the scope of this project will be billed at the hourly rates agreed previously agreed upon.
5. LEED design and/or documentation is not included.
Limit of Liability
Pursuant to section 558.0035 Florida statutes, DodStone Group Architects, Inc. is the responsible party for the professional services it agrees to provide under this agreement. No individual professional employee, agent, director, officer or principal may be individually liable for negligence arising out of this contract.
Payment
Payment request for each Task will be made upon submission of each deliverable and approval of the deliverables by DEP.
Sincerely, Joel L. Dodson, AIA Principal Architect Dodstone Architects, Inc.
File details come from the government source that posted it. Updated .