CN-370000-CN187-A1.pdf
PDF 2 MB Posted
- Contract number
- CN187
- Issued by
- Florida
About this file
This document is a Guaranteed Maximum Price (GMP) Proposal from Ajax Building Corporation to the Florida Department of Environmental Protection (DEP) for the St. Andrews State Park Dune Crossovers Reinforcement of Vertical Supports project. The proposal is dated January 20, 2015, and involves Ajax Building Corporation as the contractor working directly with the Florida Department of Environmental Protection's Bureau of Design and Construction.
The project scope involves reinforcing 77 vertical support posts on three elevated dune crossover sections (named 'Dunes', 'Surfers', and 'Divers') at St. Andrews State Park. The work includes installing new .60 ACQ treated 4"x6" Southern Pine timber posts, 6' in length, adjacent to existing vertical supports and attaching them with 5 stainless steel bolts. The Base Bid GMP Proposal totals $55,336, with a construction duration of eleven (11) weeks from Notice to Proceed to Substantial Completion. The contract includes provisions for performance and payment bonds, insurance requirements, and E-Verify employment eligibility verification. The substantial completion date is set for April 29, 2015, with final completion on May 06, 2015.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-PL318-TA2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GMP PROPOSAL
State of Florida Department of Environmental Protection
St. Andrews State Park Dune Cross Over Repairs
Ajax Project No. 201446 January 20, 2015
Submitted by:
1080 Commerce Boulevard Midway, Florida 32343 | 850.224.9571 Phone | 850.224.2496 Fax
CG C042112
AJAX PROJECT NO. 201414
ST. ANDREWS STATE PARK DUNE CROSSOVERS
REINFORCEMENT OF VERTICAL SUPPORTS
GMP PROPOSAL January 20, 2015
TABLE OF CONTENTS
I. Executive Summary
II. List of Documents
III. Description of Work
A. Clarifications, Qualifications and Assumptions B. Allowance Schedule
IV. GMP Cost Summary
A. GMP Estimate Narrative B. GMP Estimate – Base Bid GMP (CM Summary Report)
V. Site Utilization Plan
A. Site Utilization Plan Narrative B. Site Utilization Plan
VI. Project Schedule
A. Project Schedule Narrative B. Project Schedule
EXECUTIVE SUMMARY
Ajax Building Corporation is pleased to present this Guaranteed Maximum Price (GMP) Proposal for the St. Andrews State Park Dune Crossover Improvements Project for consideration by Florida Department of Environmental Protection Bureau of Design and Construction. This GMP Proposal will provide an estimate, schedule and other project information to be utilized by the project team as the project moves forward. This GMP Proposal, upon acceptance by Florida Department of Environmental Protection Bureau of Design and Construction, is intended to serve as the basis for an Amendment to the CM Contract, adding the construction phase activities to the current contract.
Project Description
The project consists of the installation of reinforcing piles and the attachment of these new piles to the existing vertical support posts for select elevated areas on the existing dune crossovers known as ‘Dunes’, ‘Surfers’, and ‘Divers’ (total of approximately 77 locations).
Guaranteed Maximum Price (GMP)
Ajax Building Corporation is confident that the GMP Proposal included herein is representative of the proposed scope of work depicted in the GMP Documents. The work included in the GMP Proposal is based upon the List of Documents included in Section II of this proposal as amended by 1) the Clarifications, Qualifications, and Assumptions, and 2) the Allowance Schedule, all contained in Section III of this proposal.
The Base Bid GMP Proposal for the St. Andrews State Park Dune Crossover Improvements Project totals $55,336.
The Base Bid GMP Proposal includes the site-work and construction for the structural improvements described above.
LIST OF DOCUMENTS
The work included in this GMP Proposal is based upon the List of Documents immediately following this narrative subject to amendments by 1) the Clarifications, Qualifications, and Assumptions, and 2) the Allowance Schedule, all contained in Section III of this proposal.
The List of Documents include the following:
▪ Contract Drawings
▪ Project Specifications
▪ Revised documents Issued by the Architect / Engineer
▪ Other Documents (As Listed)
▪ Bid Packages and Bid Package Addenda
1/6/2015
LAGOON PIER
Drawing No. & Title Date
S-1 PILE LAYOUT PLAN 12/17/14
S-2 WALKWAY - SECTION 12/17/14
S-3 WALKWAY - ELEVATION 17-Dec
S-4 WALKWAY - PLAN 12/17/14
S-5 EAST/ WEST HANDRAIL 12/17/14
S-6 MAIN DECK - SECTION 12/17/14
S-7 MAIN DECK - ELEVATION 12/17/14
S-8 MAIN DECK - PLAN 12/17/14
S-9 NORTH/ SOUTH HANDRAIL 12/17/14
S-10 SITE PLAN 12/17/14
S-11 SHEET PILE 12/17/14
S-12 CONCRETE CAP DETAIL 12/17/14
S-18a HEADWALL/ BERM DETAILS 01/06/15 Report of Existing Timber Pile Condition Assessment - NOVA 11/04/14
10/31/14
DUNE CROSSOVERS
Drawing No. & Title Date
S-13 DUNE WALKOVER PILE SPLICE DETAILS 11/20/14
S-13 DUNE WALKOVER SITE PLAN 01/06/15
S-14 DUNE WALKOVER #1 01/06/15
S-15 DUNE WALKOVER #2 01/06/15
S-16 DUNE WALKOVER #3 01/06/15
S-17 DUNE WALKOVER PILE SPLICE DETAILS 01/06/15
Report of Existing Conditions Dune Crossover Boardwalks - JGP 02/28/14
LAGOON HEADWALL
Drawing No. & Title Date
S-14 HEADWALL/ BERM DETAILS 11/26/14
S-18b HEADWALL/ BERM DETAILS 01/06/15
ATTACHMENT E
FLDEP ST. ANDREWS STATE PARK MARINE PROJECTS
DOCUMENT LIST
Report of Subsurface Exploration and Geotechnical Engineering Evaluation - NOVA
FL Department of Environmental Protection
Ajax Project #201434
St. Andrews State Park
Marine Projects
January 08, 2015
Allan Rectangle
Allan Rectangle
ADDENDA ISSUED BY THE ARCHITECT/ENGINEER
Addenda # Description # Pages Date Revised
1 ADDENDUM #1 7 01/06/2015
(END OF ADDENDA)
AJAX PROJECT NO. 201434
ST. ANDREWS STATE PARK LAGOON PIER RENOVATION/ REPLACEMENT
PRE-BID REQUESTS FOR INFORMATION (PRE-BID RFI’s)
PB RFI No. Description Issued Resp Revised
(END OF PRE-BID RFI’S)
BID PACKAGES AND BID PACKAGE ADDENDA
BP No. Description Date
BP 31.1 Site Work (Addendum 1 dated 12/30/15, Addendum 2 dated 1/8/15 12/22/15
(END OF BID PACKAGES AND BID PACKAGE ADDENDA)
END OF DOCUMENT LIST
CLARIFICATIONS, QUALIFICATIONS AND ASSUMPTIONS
St. Andrews State Park Reinforcement of Vertical Supports
For Elevated Sections of Dune Crossovers GMP Proposal
This GMP Proposal has been prepared based on the 100% Construction Documents by Anderson Engineers, PA., dated Jan. 06, 2014, and the following Clarifications, Qualifications and Assumptions.
It is understood that various allowances are included in this GMP Proposal as indicated throughout the estimate.
The sizes, quantities and descriptions indicated within the GMP Proposal, are considered to be part of these clarifications, qualifications and assumptions.
These qualifications, clarifications and assumptions are intended to supplement the GMP Proposal and are an attempt to inform the Owner of the Construction Manager’s interpretation of the scope items which are included or excluded, and which may not be clearly shown or defined by specification, plan, elevation, detail, section, schedule, or schematic.
Scope of the GMP Proposal
The scope of this GMP Proposal consists of the following:
▫ The Construction Manager’s general conditions and general requirements covering the construction duration and associated closeout.
▫ The construction duration is Eleven (11) weeks from NTP to Substantial Completion ▫ 100% Construction Document – Includes the following scope of work:
Base Bid
Reinforcing of 77 vertical support posts on 3 of the elevated sections of the existing dune crossovers located at the jetty recreation area, designated as ‘Dunes’, ‘Surfers’, and ‘Divers’ dune crossovers.
This work includes the placement of a new .60 ACQ treated 4”x6” Southern Pine timber post, 6’ in length adjacent to the existing vertical supports at 77 individual locations, and attaching the new post to the existing post with 5 stainless steel bolts.
Quantities indicated on the 100% Construction Documents were utilized in developing this estimate.
Division 01 – General Requirements
Clarifications, qualifications and assumptions related to Division 01:
▫ The Estimate includes the Construction Manager’s full general conditions and general requirements. – see estimate breakdown.
▫ Performance and Payment Bonds are included in the estimate.
▫ General Liability Insurance is included in the estimate.
▫ Costs for procuring Builder’s Risk Insurance are included in the estimate.
The standard deductible for this policy is $5,000.
The windstorm and flood deductibles for this policy are $25,000.
Should a Builder’s Risk claim occur, any deductibles or uncovered costs will be treated as a change in scope to be funded via a change order to the Construction Manager’s Contract.
▫ The Builder’s Risk and General Liability Policies do not cover existing construction or existing building components, therefore the Owner shall list Ajax Building Corporation as an additional insured on their Property Damage Policy or provide for a waiver of subrogation in Ajax Building Corporation’s favor.
▫ A Construction Manager’s Contingency is included in the estimate. This contingency is to be utilized solely by Ajax Building Corporation in executing the work described in this proposal.
▫ Architectural and/or Engineering Fees are included in the estimate.
▫ The Construction Manager’s Construction Phase Fee’s are included.
▫ The Construction Manager’s Pre-Construction Services Fees are not included.
Division 05 – Metals
Clarifications, qualifications and assumptions related to Division 05:
▫ Hardware & Fasteners We include all hardware and fasteners as 316 grade stainless steel
Division 06 – Wood and Plastics
Clarifications, qualifications and assumptions related to Division 06:
▫ Lumber and Rough Carpentry This proposal includes all pilings.
4”x6” ACQ treated Southern Pine timber pilings Report of Existing Conditions prepared by JGP, dated 2/28/14 indicates numerous deficiencies with regard to the existing dune crossovers, and includes recommendations in addition to the work that is being performed and incorporated in this proposal. This proposal does not include any other work than that specifically note on the 100% drawings provided by Anderson Engineer, PA and described herein.
This proposal does not include any work associated with existing hardware, fasteners, connections or structure (handrails, stairs, joists, beams, cross-bracing, etc.), modification, removal, repair or replacement of existing vertical support posts except what is indicated in the drawings and as noted in these Qualifications.
During site visits, it was noted that the south end of the ‘Dunes’ crossover has been constructed over another timber boardwalk that has since been covered with beach sand.
Invasive testing was not performed or provided in these locations.
This proposal assumes no variances in installation of piles in this location.
All (77) locations where new vertical piles are noted to be placed are assumed to be typical with no obstructions.
Division 32 – Exterior Improvements
Clarifications, qualifications and assumptions related to Division 32:
Water for jetting piles will be metered and sourced from the closest fresh water fire hydrant (city water supply).
This proposal assumes access (on the sand dunes) will be provided adjacent to and along the full length of each of the affected dune crossovers, limited to 4’ on each side of the crossover boardwalks as a work area.
Vehicles and equipment will not be permitted on the dunes during the completion of this work.
END OF CLARIFICATIONS, QUALIFICATIONS AND ASSUMPTIONS TO THE ESTIMATE REPORT
ALLOWANCE SCHEDULE
The following allowances are included in the GMP Proposal where a clear scope has not been defined by the GMP Documents or where the items require further research. These allowances are for the cost of work only and do not include costs for insurance, bonds, contingency, fee, etc.
It is understood that the Construction Manager’s Contract will require adjustments by change order (either additive or deductive) for reconciling the difference between each of the below listed allowances and the actual costs and/or savings realized for each allowance.
Description Allowance Amount
Building Permits $1,000.00
END OF ALLOWANCE SCHEDULE
ESTIMATE NARRATIVE
Ajax Building Corporation is confident that the GMP Proposal included herein is representative of the proposed scope of work depicted in the GMP Documents. The work included in the GMP Proposal is based upon the List of Documents included in Section II of this proposal as amended by 1) the Clarifications, Qualifications, and Assumptions, and 2) the Allowance Schedule, all contained in Section III of this proposal.
The Base Bid GMP Proposal for the St. Andrews State Park Dune Crossover Improvements Project totals $55,336.
The Base Bid GMP Proposal includes the site-work and construction for the structural improvements to the existing dune crossovers known as ‘Dunes’, ‘Surfers’, and ‘Divers’ (total of approximately 76 locations). This work consists of the installation of reinforcing piles and the attachment of these new piles to the existing vertical support posts for select elevated areas of the crossovers.
GMP Estimate:
BASE BID GMP
Estimate Breakdown:
Construction Phase Fee $ 15,130.00
OH&P $ 5,900.00
Design Fee (Construction administration and inspection)
Sr. Engineer - 8 hours @ $150 = $1200 $ 1,200.00
Technician - 6 hours @ 90 = $540 $ 540.00
BP 31.1 Subcontractor $ 21,890.00
Reimbursable General Conditions $ 7,726.00
Contingency $ 2,950.00
$ 55,336.00
DEP - St. Andrews State Park
DUNE CROSSOVERS VERT. SUPPORT REINFORCEMENT
FEE PROPOSAL SUMMARY
1/20/2015
Budget 59,000.00$
Fee Proposal Pre-Construction Phase Fee $1,690 2.86% Pre-Construction Phase Fee (Engineering) $3,620 6.14% Construction Phase Fee $15,130 25.64% Construction Phase Fee (Engineering) $1,740 2.95% Overhead & Profit For Construction Phase $5,900 10.00%
$28,080 38.51%
Page 1 of 1 AJAX BUILDING CORPORATION
58%
CONTRACT HOURS/ HOURLY LABOR
JOB PERSONNEL ARTICLE WEEKS WEEK RATE SUBTOTAL BURDEN
Operations Manager 8.2(1)a 0.0 2.0 65.0 $0.00 $0.00 Full Time Project Manager 8.2(1)a 0.0 5.0 50.0 $0.00 $0.00 Full Time Superintendent (prior to store compl8.2(1)a 0.0 0.0 52.0 $0.00 $0.00 General Superintendent 8.2(1)a 0.0 1.0 65.0 $0.00 $0.00 Home Office Secretary 8.2(1)a 0.0 11.4 17.0 $0.00 $0.00 Safety Director 8.2(1)a 0.0 2.0 40.0 $0.00 $0.00
SUBTOTAL: $0.00 $0.00
ESTIMATING SERVICES
Estimator 8.2(1)a 0.0 1.0 40.0 $0.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL JOB PERSONNEL: $0.00
TRAVEL, PER DIEM, RELOCATION MONTHLY
MONTHS COST TOTAL
Per Diem 9.2(16) 0.0 541.75$ $0.00
NIGHTS COST/NIGHT TOTAL
Hotel Expenses 9.2(16) 0.0 79.50$ $0.00 MILES COST/MILE Wks TOTAL
Travel Expenses 9.2(16) 300.0 0.45$ 4 $506.00 Operations Manager Vehicle Allowance 8.2(1)a 0.0 MO 160.00$ $0.00 Project Manager Vehicle Allowance 8.2(1)a 0.0 MO 216.67$ $0.00 MEP Coordinator Vehicle Allowance 8.2(1)a 0.0 MO 35.00$ $0.00 Director of Field Ops. Vehicle Allowance 8.2(1)a 0.0 MO 200.00$ $0.00
TOTAL MISC. GENERAL REQ.: $506.00
PROJECT COORDINATION UNIT
UNITS COST TOTAL
Bid Advertisements 9.2(13) 0.0 963.00$ $0.00 Bid Packages 9.2(13) 0.0 80.25$ $0.00 Project Manuals 8.2(1)f 0.0 150.00$ $0.00 Purchase Drawings/Reproductions 9.2(17) 1.0 200.00$ $200.00 Operation/Maintenance Training 9.2(13) 0.0 500.00$ $0.00 Construction Schedule 8.2(1)f 0.0 75.00$ $0.00
TOTAL FIELD OFFICES: $200.00
REGULATORY REQUIREMENTS UNIT
UNITS COST
Building Permits(not incl. Fire Marshall) 9.2(13) 0.0 1,000.00$ $0.00 Environmental Permits 9.2(13) 0.0 1.00$ $0.00 Water System Service Charges 9.2(13) 0.0 1.00$ $0.00 Water System Tap Fee 9.2(13) 0.0 1.00$ $0.00 Sewer System Service Charges 9.2(13) 0.0 1.00$ $0.00 Sewer System Tap Fee 9.2(13) 0.0 1.00$ $0.00 Transportation Impact Fees 9.2(13) 0.0 1.00$ $0.00 Impact Connection Fees 9.2(13) 0.0 1.00$ $0.00
AJAX BUILDING CORPORATION
Reimburseable General Conditions
DEP - St. Andrews State Park (Dune Crossovers)
Meter/Tap Fees 9.2(13) 0.0 1.00$ $0.00
TOTAL REG. REQUIREMENTS: $0.00
PROJECT CLEANING 58%
UNIT LABOR
UNITS COST BURDEN
Final Job Cleanup 9.2(10) 0.0 0.19$ $0.00 Rubbish Removal 9.2(10) 3.0 107.00$ $321.00 Dump Charges 9.2(10) 3.0 267.50$ $802.50 Construction Cleanup 9.2(10) 20.0 10.00$ $200.00 $116.00
SUBTOTAL: $1,323.50
LABOR BURDEN: $116.00
TOTAL PROJECT CLEANUP: $1,439.50
58%
HOURS/ HOURLY LABOR
SURVEYS & FIELD ENGINEERING WEEKS WEEK RATE BURDEN
Layout Labor 9.2(13) 0.0 1.00$ $12.50 $0.00 $0.00
COST/WEEK
Layout Supplies 9.2(13) 0.0 -$ $267.00 $0.00 Video Survey - Initial 9.2(13) 0.0 -$ $1,500.00 $0.00 As Built 9.2(22) 0.0 -$ $1,500.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL SURVEYS & FIELD ENG'RG: $0.00
PROJECT SAFETY UNIT
UNITS COST SUBTOTAL
First Aid Supplies 9.2(13) 1.0 100.00$ $100.00 Safety Supplies 9.2(13) 3.0 20.00$ $60.00 Temporary Fire Protection 9.2(20) 0.0 66.05$ $0.00 Water, Ice, & Cups 9.2(20) 3.0 20.00$ $60.00
TOTAL PROJECT SAFETY: $220.00
FIELD OFFICES MONTHLY
MONTHS COST SUBTOTAL
Postage 9.2(9) 0.0 160.50$ $0.00 Office Supplies 8.2(1)(g) 0.0 35.00$ $0.00 Office Supply Set Up 8.2(1)(g) 0.0 75.00$ $0.00 Data Processing 8.2(1)(c) 0.0 50.00$ $0.00 Jobsite Equipment 9.2(20) 0.0 1,000.00$ $0.00 Office Trailer 9.2(20) 0.0 722.25$ $0.00 Office Trailer Set-up 9.2(20) 0.0 4,009.00$ $0.00 Office Trailer Removal 9.2(20) 0.0 2,475.00$ $0.00 Superintendent Pick-up 8.2(1)(e) 0.0 600.00$ $0.00 Fuel for Superintendent Pick-up 8.2(1)(e) 0.0 250.00$ $0.00 Jobsite Runner 9.2(9) 0.0 75.00$ $0.00
TOTAL FIELD OFFICES: $0.00
PROJECT COMMUNICATIONS MONTHLY
MONTHS COST SUBTOTAL
Jobsite Cellular Phones 9.2(9) 0.0 347.75$ $0.00 Jobsite Radios (See Above) 9.2(9) 0.0 -$ $0.00 Project Telephones 9.2(9) 0.0 508.25$ $0.00 Telephone Connection Fees 9.2(9) 0.0 561.75$ $0.00 Project Camera 9.2(9) 0.0 75.00$ $0.00 Aerial Photos 9.2(9) 0.0 125.00$ $0.00
Progress Photos 9.2(9) 0.0 37.45$ $0.00
TOTAL PROJECT COMMUNICATIONS: $0.00
PROJECT UTILITIES MONTHLY
MONTHS COST SUBTOTAL
Chemical Toilet 9.2(20) 3.0 125.00$ $375.00 Temporary Electric 9.2(20) 0.0 321.00$ $0.00 Temporary Electric Connection 9.2(20) 0.0 500.00$ $0.00 Temporary Water 9.2(20) 0.0 1,000.00$ $0.00 Temporary Water Connection 9.2(20) 1.0 300.00$ $300.00 Temporary Heat 9.2(20) 0.0 160.50$ $0.00 Early Cut-on Permanent HVAC 9.2(20) 0.0 0.21$ $0.00
TOTAL PROJECT UTILITIES: $675.00
QUALITY CONTROL
SUBTOTAL
Lab Testing Allowance 9.2(13) 0.0 2,500.00$ $0.00
TOTAL QUALITY CONTROL: $0.00
CONSTRUCTION TOOLS & EQUIPMENT 58%
UNIT LABOR
UNITS COST SUBTOTAL BURDEN
Small Tools & Equipment 9.2(4) 3.0 100.00$ $300.00 Fork Lift - 2.5 Ton, 4 WD 9.2(5) 0.0 2,050.00$ $0.00 Fork Lift - Fuel, Oil, & Lube 9.2(5) 0.0 160.50$ $0.00 Fork Lift Operator 9.2(5) 0.0 480.00$ $0.00 $0.00
SUBTOTAL: $300.00
LABOR BURDEN: $0.00
TOTAL CONST'N TOOLS & EQUIP: $300.00
TEMPORARY FENCES & ENCLOSURES 58%
UNIT LABOR
UNITS COST SUBTOTAL BURDEN
Temporary Job Fence 9.2(18) 100.0 4.50$ $450.00 Temporary Dry-in of Building 9.2(20) 0.0 267.50$ $0.00 Temporary Dry-in of Building (Labor) 9.2(20) 0.0 375.00$ $0.00 $0.00 Environmental Controls 9.2(20) 1.0 2,500.00$ $2,500.00
SUBTOTAL: $2,950.00
LABOR BURDEN: $0.00
TOTAL TEMP. FENCES & ENCL.: $2,950.00
PROJECT SIGNS 58%
UNIT LABOR
UNITS COST SUBTOTAL BURDEN
Project Sign 9.2(13) 0.0 750.00$ $0.00 Project Sign (Labor) 9.2(13) 0.0 12.00$ $0.00 $0.00 Jobsite Signage 9.2(13) 0.0 481.50$ $0.00 Jobsite Signage (Labor) 9.2(13) 0.0 12.00$ $0.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL PROJECT SIGNS: $0.00
WARRANTY EXPENSE MONTHLY
SUM COST SUBTOTAL
Warranty Expense 9.2(8) 1 LS 23.60$ $23.60 Insurance 9.2(8) 1 LS 625.10$ $625.10 Bonds 9.2(8) 1 LS 786.91$ $786.91
TOTAL WARRANTY EXPENSE: $1,435.61
TOTAL MANAGEMENT FEE: $7,726
1/20/2015
Page 1 of 3 AJAX BUILDING CORPORATION
58%
CONTRACT HOURS/ HOURLY LABOR
JOB PERSONNEL ARTICLE WEEKS WEEK RATE SUBTOTAL BURDEN
Operations Manager 8.2(1)a 11 2.0 $65.00 $1,430.00 $829.40 Full Time Project Manager 8.2(1)a 11 5.0 $50.00 $2,750.00 $1,595.00 Full Time Superintendent (prior to store compl8.2(1)a 9 0.0 $52.00 $0.00 $0.00 Full Time Superintendent (after store compl.) 8.2(1)a 2 13.0 $52.00 $1,352.00 $784.16 General Superintendent 8.2(1)a 11 1.0 $65.00 $715.00 $414.70 Home Office Secretary 8.2(1)a 11 11.4 $17.00 $2,127.87 $1,234.17 Safety Director 8.2(1)a 11 2.0 $40.00 $880.00 $510.40
SUBTOTAL: $9,254.87 $5,367.83
ESTIMATING SERVICES
Estimator 8.2(1)a 6 1.0 $40.00 $240.00 $117.60
SUBTOTAL: $9,494.87
LABOR BURDEN: $5,485.43
TOTAL JOB PERSONNEL: $14,980.30
TRAVEL, PER DIEM, RELOCATION MONTHLY
MONTHS COST TOTAL
Per Diem 9.2(16) 0 $541.75 $0.00
NIGHTS COST/NIGHT TOTAL
Hotel Expenses 9.2(16) 0 $79.50 $0.00 MILES COST/MILE Wks TOTAL
Travel Expenses 9.2(16) 0 $0.45 4 $0.00 Operations Manager Vehicle Allowance 8.2(1)a 0 MO $160.00 $0.00 Project Manager Vehicle Allowance 8.2(1)a 0 MO $216.67 $0.00 MEP Coordinator Vehicle Allowance 8.2(1)a 0 MO $35.00 $0.00 Director of Field Ops. Vehicle Allowance 8.2(1)a 0 MO $200.00 $0.00
TOTAL MISC. GENERAL REQ.: $0.00
PROJECT COORDINATION UNIT
UNITS COST TOTAL
Bid Advertisements 9.2(13) 0 LS $963.00 $0.00 Bid Packages 9.2(13) 0 EA $80.25 $0.00 Project Manuals 8.2(1)f 0 EA $150.00 $0.00 Purchase Drawings/Reproductions 9.2(17) 0 LS $200.00 $0.00 Operation/Maintenance Training 9.2(13) 0 AL $500.00 $0.00 Construction Schedule 8.2(1)f 0 MO $75.00 $0.00
TOTAL FIELD OFFICES: $0.00
REGULATORY REQUIREMENTS UNIT
UNITS COST TOTAL
Building Permits(not incl. Fire Marshall) 9.2(13) 0 AL $1,000.00 $0.00 Environmental Permits 9.2(13) 0 NIC $1.00 $0.00 Water System Service Charges 9.2(13) 0 NIC $1.00 $0.00 Water System Tap Fee 9.2(13) 0 NIC $1.00 $0.00 Sewer System Service Charges 9.2(13) 0 NIC $1.00 $0.00 Sewer System Tap Fee 9.2(13) 0 NIC $1.00 $0.00 Transportation Impact Fees 9.2(13) 0 NIC $1.00 $0.00 Impact Connection Fees 9.2(13) 0 NIC $1.00 $0.00 Meter/Tap Fees 9.2(13) 0 NIC $1.00 $0.00
TOTAL REG. REQUIREMENTS: $0.00
AJAX BUILDING CORPORATION
CONSTRUCTION MANAGEMENT FEE
DEP - St. Andrews State Park (Dune Crossovers)
Page 2 of 3 AJAX BUILDING CORPORATION
AJAX BUILDING CORPORATION
CONSTRUCTION MANAGEMENT FEE
DEP - St. Andrews State Park (Dune Crossovers)
PROJECT CLEANING 58%
UNIT LABOR
UNITS COST SUBTOTAL BURDEN
Final Job Cleanup 9.2(10) 0 SF $0.19 $0.00 Rubbish Removal 9.2(10) 0 MO $107.00 $0.00 Dump Charges 9.2(10) 0 EA $267.50 $0.00 Construction Cleanup 9.2(10) 0 MH $10.00 $0.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL PROJECT CLEANUP: $0.00
58%
HOURS/ HOURLY LABOR
SURVEYS & FIELD ENGINEERING WEEKS WEEK RATE SUBTOTAL BURDEN
Layout Labor 9.2(13) 0 1.00 $12.50 $0.00 $0.00
COST/WEEK
Layout Supplies 9.2(13) 0 $267.00 $0.00 Video Survey - Initial 9.2(13) 0 LS $1,500.00 $0.00 As Built 9.2(22) 0 LS $1,500.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL SURVEYS & FIELD ENG'RG: $0.00
PROJECT SAFETY UNIT
UNITS COST SUBTOTAL
First Aid Supplies 9.2(13) 0 LS $100.00 $0.00 Safety Supplies 9.2(13) 0 MO $20.00 $0.00 Temporary Fire Protection 9.2(20) 0 MO $66.05 $0.00 Water, Ice, & Cups 9.2(20) 0 MO $20.00 $0.00
TOTAL PROJECT SAFETY: $0.00
FIELD OFFICES MONTHLY
MONTHS COST TOTAL
Postage 9.2(9) 0 $160.50 $0.00 Office Supplies 8.2(1)(g) 0 $35.00 $0.00 Office Supply Set Up 8.2(1)(g) 0 LS $75.00 $0.00 Data Processing 8.2(1)(c) 3 MO $50.00 $150.00 Jobsite Equipment 9.2(20) 0 $1,000.00 $0.00 Office Trailer 9.2(20) 0 $722.25 $0.00 Office Trailer Set-up 9.2(20) 0 EA $4,009.00 $0.00 Office Trailer Removal 9.2(20) 0 EA $2,475.00 $0.00 Superintendent Pick-up 8.2(1)(e) 0 MO $600.00 $0.00 Fuel for Superintendent Pick-up 8.2(1)(e) 0 MO $250.00 $0.00 Jobsite Runner 9.2(9) 0 MO $75.00 $0.00
TOTAL FIELD OFFICES: $150.00
PROJECT COMMUNICATIONS MONTHLY
MONTHS COST TOTAL
Jobsite Cellular Phones 9.2(9) 0 $347.75 $0.00 Jobsite Radios (See Above) 9.2(9) 0 $0.00 $0.00 Project Telephones 9.2(9) 0 $508.25 $0.00 Telephone Connection Fees 9.2(9) 0 LS $561.75 $0.00 Project Camera 9.2(9) 0 $75.00 $0.00 Aerial Photos 9.2(9) 0 $125.00 $0.00 Progress Photos 9.2(9) 0 $37.45 $0.00
TOTAL PROJECT COMMUNICATIONS: $0.00
Page 3 of 3 AJAX BUILDING CORPORATION
AJAX BUILDING CORPORATION
CONSTRUCTION MANAGEMENT FEE
DEP - St. Andrews State Park (Dune Crossovers)
PROJECT UTILITIES MONTHLY
MONTHS COST TOTAL
Chemical Toilet 9.2(20) 0 $125.00 $0.00 Temporary Electric 9.2(20) 0 $321.00 $0.00 Temporary Electric Connection 9.2(20) 0 LS $500.00 $0.00 Temporary Water 9.2(20) 0 $1,000.00 $0.00 Temporary Water Connection 9.2(20) 0 LS $300.00 $0.00 Temporary Heat 9.2(20) 0 $160.50 $0.00 Early Cut-on Permanent HVAC 9.2(20) 0 SF $0.21 $0.00
TOTAL PROJECT UTILITIES: $0.00
QUALITY CONTROL UNIT
UNITS COST TOTAL
Lab Testing Allowance 9.2(13) 0 LS $2,500.00 $0.00
TOTAL QUALITY CONTROL: $0.00
CONSTRUCTION TOOLS & EQUIPMENT 58%
UNIT LABOR
UNITS COST TOTAL BURDEN
Small Tools & Equipment 9.2(4) 0 MO $100.00 $0.00 Fork Lift - 2.5 Ton, 4 WD 9.2(5) 0 MO $2,050.00 $0.00 Fork Lift - Fuel, Oil, & Lube 9.2(5) 0 MO $160.50 $0.00 Fork Lift Operator 9.2(5) 0 WK $480.00 $0.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL CONST'N TOOLS & EQUIP: $0.00
TEMPORARY FENCES & ENCLOSURES 58%
UNIT LABOR
UNITS COST TOTAL BURDEN
Temporary Job Fence 9.2(18) 0 LF $4.50 $0.00 Temporary Dry-in of Building 9.2(20) 0 LS $267.50 $0.00 Temporary Dry-in of Building (Labor) 9.2(20) 0 WK $375.00 $0.00 $0.00 Environmental Controls 9.2(20) 0 LS $2,500.00 $0.00
SUBTOTAL: $0.00
LABOR BURDEN: $0.00
TOTAL TEMP. FENCES & ENCL.: $0.00
PROJECT SIGNS 58%
UNIT LABOR
UNITS COST TOTAL BURDEN
Project Sign 9.2(13) 0 EA $750.00 $0.00 Project Sign (Labor) 9.2(13) 0 HR $12.00 $0.00 $0.00 Jobsite Signage 9.2(13) 0 LS $481.50 $0.00 Jobsite Signage (Labor) 9.2(13) 0 HR $12.00 $0.00 $0.00
SUBTOTAL: $0.00 $0.00
LABOR BURDEN: $0.00
TOTAL PROJECT SIGNS: $0.00
WARRANTY EXPENSE LUMP MONTHLY
SUM COST TOTAL
Warranty Expense 9.2(8) 0 LS $23.60 $0.00 $0.00 Insurance 9.2(8) 0 LS $625.10 $0.00 $0.00 Bonds 9.2(8) 0 LS $786.91 $0.00 $0.00
TOTAL WARRANTY EXPENSE: $0.00
$0.00 $0.00
TOTAL MANAGEMENT FEE: $15,130
SITE UTILIZATION AND PHASING NARRATIVE
Refer to the attached Site Utilization and Phasing Plan as prepared by Ajax Building Corporation and included in Section V-B of this proposal for the illustration of the below listed items.
SITE UTILIZATION PLAN NARRATIVE
A detailed Site Utilization and Phasing Plan has been prepared by Ajax Building Corporation and is attached for the illustration of the below listed items.
Public Access
Public access will be blocked at the entry point of each of the affected Dune Crossovers.
The work at all three of the Dune Crossovers will be performed simultaneously.
All parties involved (Park staff, Owner, Subcontractors) will be notified prior to the commencement of work.
Site Security
All materials, tools and equipment will either be removed from the site or locked in storage containers if left on-site.
Work areas will remain blocked to public access when workers are not present.
Debris Removal
Roll-off containers will be supplied and maintained by Ajax Building Corporation for removing construction debris from the project site.
All roll-off container pulls will be scheduled by Ajax Building Corporation’s Project Superintendent.
Unless otherwise dictated by the progress/requirements of the project, Ajax Building Corporation will endeavor to perform all roll-off container pulls during business hours.
Tree Protection / Erosion Control / Barricades
Erosion Control: All silt fencing, hay bales and other erosion control measures required by the Contract
Documents will be installed prior to the commencement of site work.
Vehicle and Equipment Paths
All Subcontractors have been notified that vehicles and equipment will not be permitted on the dunes, although personnel will need to access areas below and adjacent to the dune crossovers. It is expected that there will be minimal impact to the dunes mostly due to limited foot traffic required for installation of piles/ posts.
On-Site Material Storage
Storage Containers: Various materials, equipment and fabricated items will be stored in Connex-type trailers, tractor trailers and storage boxes within the fenced area of the project site. All storage containers will be locked during non-work hours.
Open Material Storage: Various materials, equipment and fabricated items that do not lend themselves to be stored in containers will be stored and/or staged on the project site. Such items will be stored on dunnage and protected from the elements as necessary to ensure that that quality and condition of the items is not jeopardized.
Temporary Facilities
Temporary Power:
o Temporary electrical service for tolls and equipment (if needed) will be sourced from gas powered porable generators..
Temporary Water:
o Temporary water service for the jobsite will be obtained from the closest source (fresh water hydrant) at no cost to Ajax Building Corporation or its Subcontractors.
Temporary Sanitary Sewer:
o In such cases where portable toilet facilities (port-o-lets) are required, those facilities will be serviced two (2) times per week or as otherwise necessary when they are in use.
Construction Traffic, Parking and Deliveries
Construction Employees and Personnel: Construction employees and personnel will utilize the jetty parking area.
Parking for Construction workers will remain as far west as possible. Any overflow of Construction personnel parking will be coordinated with the park and DEP.
Construction Deliveries: General construction related deliveries will utilize the jobsite Entrance gate for access to the project site.
Maintenance of Site
Ajax Building Corporation will maintain all erosion control measures, construction storage areas, and construction parking areas to ensure safety and an acceptable appearance. It is assumed that the Owner will continue to maintain all other areas outside the construction site or not occupied by Ajax Building Corporation.
The site will be monitored for trash, debris, and general housekeeping. Cleanup and housekeeping will be performed on a regular basis as necessary to ensure safety and an acceptable appearance.
Emergency Contact Information
Emergency Contacts: The following is a list of emergency contact numbers for Ajax personnel assigned to the project.
Contact Person Job Title Contact Number Allan Wooden Operations Manager Mobile # 850-251-3534 James Penrod Project Manager Office/ Mobile # 850-590-0871 Reggie Kemp Project Superintendent Mobile # 850-408-1471
SITE UTILIZATION AND PHASING PLAN
JPenrod Polygonal Line
JPenrod Polygon
JPenrod Polygonal Line
JPenrod Polygonal Line
JPenrod Text Box
* Deisgnated work areas (4' on either side of affected boardwalks)
* Public access blocked
JPenrod Line
JPenrod Line
JPenrod Line
JPenrod Text Box Proposed Dumpster location
JPenrod Line
SCHEDULE NARRATIVE
Refer to the attached Master Project Schedule dated Jan. 13, 2015 as prepared by Ajax Building Corporation and included in Section VI-B of this proposal for the illustration of the below listed items.
The project schedule included within this proposal is based on the information represented in the GMP Documents.
The project schedule reflects an overall duration of six (6) weeks for the construction phase of the project.
The following contractual dates are incorporated into the CM Contract via this GMP Proposal.
▪ Substantial Completion April 29, 2015
▪ Final Completion May 06, 2015
The following additional Milestone Dates are anticipated within the project schedule in order to achieve the contractual dates listed above.
▪ Mobilization / Start of Construction Feb. 19, 2015
▪ Owner Occupancy May 06, 2015
In order for construction activities to commence on Feb. 19, 2015 as scheduled, the following contractual activities will need to be completed as indicated.
▪ GMP Negotiations Complete Feb. 02, 2015
▪ Notice to Proceed Issued Feb. 17, 2015
▪ CM Contract Amendment Executed Feb. 18, 2015
Should any of the above listed dates not be met and therefore delay the commencement and/or progress of construction, the contractual substantial and final completion dates noted above will require extension on a day for day basis. Additionally, a revision to the General Conditions costs may also need to be revised if the final completion dates are affected enough to extend past the final completion date of the Pier Store project (currently April 7, 2015).
Ajax Building Corporation will continue to work closely with the Project Team throughout the Preconstruction and Construction Phases of the project to ensure that all critical dates are maintained.
PROJECT SCHEDULE
Act ID Description Early
Start Early
Finish Orig Dur 01
DEC
JAN
FEB
MAR
APR
MAY
JUN
JUL
26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 2
PREBID
1000.010 ACTIVATION LAGOON PIER 08/21/14 A 0
1000.020 ACTIVATION LAGOON HEADWALL 12/01/14 A 0
1000.030 ACTIVATION DUNE CROSSOVERS 12/01/14 A 0
1001.100 PRE-BID MEETING - ALL 12/30/14 * 0
BID
1010.000 Bid Period - ALL 12/30/14 01/13/15 10
1031.110 PRE-AWARD MTG PIER 01/14/15 01/14/15 1
2031.110 PRE-AWARD MTG HDWL 01/14/15 01/14/15 1
3031.110 PRE-AWARD MTG DUNEX 01/14/15 01/14/15 1
1500.000 PREPARE GMP PROPOSAL - ALL 01/15/15 01/19/15 3
1510.000 Final GMP Approval - ALL 01/20/15 02/02/15 10
1600.000 Notice to Proceed from DEP 02/17/15 02/17/15 1
1031.120 ISSUE CONTRACT PIER 02/18/15 02/18/15 1
2031.120 ISSUE CONTRACT HDWL 02/18/15 02/18/15 1
3031.120 ISSUE CONTRACT DUNEX 02/18/15 02/18/15 1
PREP
2005.130 PREP SUBM HDWL HAND RAILS 02/03/15 02/09/15 5
1003.130 PREP SUBM PIER CONCR. MIX 02/19/15 02/23/15 3
1031.130 PREP SUBM PILING LOGS 02/19/15 02/25/15 5
1032.130 PREP SUBM PIER LUMBER 02/19/15 02/25/15 5
1033.130 PREP SUBM PIER HRDWR-FSTNRS 02/19/15 02/25/15 5
1034.130 PREP SUBM PIER QUALS/CERTS 02/19/15 02/25/15 5
2003.130 PREP SUBM HDWL CONCR. MIX 02/19/15 02/23/15 3
3032.130 PREP SUBM DUNEX LUMBER 02/19/15 02/19/15 1
3033.130 PREP SUBM DUNEX HRDWR-FSTNRS 02/19/15 02/19/15 1
AJXRVW
2005.131 AJAX RVW SUBM HDWL HAND RAILS 02/10/15 02/16/15 5
3032.131 AJAX RVW SUBM DUNEX LUMBER 02/20/15 02/20/15 1
3033.131 AJAX RVW SUBM DUNEX 02/20/15 02/20/15 1
1003.131 AJAX RVW SUBM PIER CONCR. MIX 02/24/15 03/02/15 5
2003.131 AJAX RVW SUBM HDWL CONCR. MIX 02/24/15 02/24/15 1
1031.131 AJAX RVW SUBM PILING LOGS 02/26/15 02/26/15 1
1032.131 AJAX RVW SUBM PIER LUMBER 02/26/15 03/04/15 5
1033.131 AJAX RVW SUBM PIER HRDWR-FSTNRS 02/26/15 03/04/15 5
1034.131 AJAX RVW SUBM PIER QUALS/CERTS 02/26/15 03/04/15 5
ARCHRVW
2005.132 A/E RVW SUBM HDWL HAND RAILS 02/17/15 02/19/15 3
3032.132 A/E RVW SUBM DUNEX LUMBER 02/23/15 02/25/15 3
3033.132 A/E RVW SUBM DUNEX HRDWR-FSTNRS 02/23/15 02/27/15 5
ACTIVATION LAGOON HEADWALL
ACTIVATION DUNE CROSSOVERS
PRE-BID MEETING - ALL
Bid Period - ALL
PRE-AWARD MTG PIER
PRE-AWARD MTG HDWL
PRE-AWARD MTG DUNEX
PREPARE GMP PROPOSAL - ALL
Final GMP Approval - ALL
Notice to Proceed from DEP
ISSUE CONTRACT PIER
ISSUE CONTRACT HDWL
ISSUE CONTRACT DUNEX
PREP SUBM HDWL HAND RAILS
PREP SUBM PIER CONCR. MIX
PREP SUBM PILING LOGS
PREP SUBM PIER LUMBER
PREP SUBM PIER HRDWR-FSTNRS
PREP SUBM PIER QUALS/CERTS
PREP SUBM HDWL CONCR. MIX
PREP SUBM DUNEX LUMBER
PREP SUBM DUNEX HRDWR-FSTNRS
AJAX RVW SUBM HDWL HAND RAILS
AJAX RVW SUBM DUNEX LUMBER
AJAX RVW SUBM DUNEX HRDWR-FSTNRS
AJAX RVW SUBM PIER CONCR. MIX
AJAX RVW SUBM HDWL CONCR. MIX
AJAX RVW SUBM PILING LOGS
AJAX RVW SUBM PIER LUMBER
AJAX RVW SUBM PIER HRDWR-FSTNRS
AJAX RVW SUBM PIER QUALS/CERTS
A/E RVW SUBM HDWL HAND RAILS
A/E RVW SUBM DUNEX LUMBER
A/E RVW SUBM DUNEX HRDWR-FSTNRS
Start date 08/21/14 Finish date 06/01/15 Data date 12/15/14 Run date 01/19/15 Page number 1A
© Primavera Systems, Inc.
AJAX BUILDING CORPORATION
ST. ANDREWS STATE PARK LAGOON PIER
Start Early
Finish Orig Dur 01
DEC
JAN
FEB
MAR
APR
MAY
JUN
JUL
26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 2
2003.132 A/E RVW SUBM HDWL CONCR. MIX 02/25/15 03/03/15 5
1031.132 A/E RVW SUBM PILING LOGS 02/27/15 03/05/15 5
1003.132 A/E RVW SUBM PIER CONCR. MIX 03/03/15 03/09/15 5
1032.132 A/E RVW SUBM PIER LUMBER 03/05/15 03/11/15 5
1033.132 A/E RVW SUBM PIER HRDWR-FSTNRS 03/05/15 03/11/15 5
1034.132 A/E RVW SUBM PIER QUALS/CERTS 03/05/15 03/11/15 5
DELIV
2005.133 FAB/DELIV HDWL HAND RAILS 02/20/15 03/19/15 20
3032.133 FAB/DELIV DUNEX LUMBER 02/26/15 03/02/15 3
3033.133 FAB/DELIV DUNEX HRDWR-FSTNRS 03/02/15 03/04/15 3
1031.133 FAB/DELIV PILING LOGS 03/06/15 03/16/15 7
1032.133 FAB/DELIV PIER LUMBER 03/12/15 03/18/15 5
1033.133 FAB/DELIV PIER HRDWR-FSTNRS 03/12/15 03/18/15 5
LAGOON PIER
1.100 Mobilize 02/19/15 0
1.110 Demo/ dismantle exstg pier 02/26/15 03/11/15 10
1.120 Remove damaged pilings 03/12/15 03/16/15 3
1.130 Install new pilings 03/17/15 03/19/15 3
1.140 cut piling tops 03/20/15 03/26/15 5
1.150 Install Piling caps 03/27/15 04/02/15 5
1.160 Install substructure 03/31/15 04/09/15 8
1.170 Install decking 04/06/15 04/21/15 12
1.180 Install sheet piles 04/09/15 04/15/15 5
1.190 demo xstg sidewalks 04/16/15 04/29/15 10
1.210 backfill at sheet piles 04/30/15 05/01/15 2
1.200 install helical anchors 05/04/15 05/07/15 4
1.220 Form/ pour new sheet pile caps 05/08/15 05/14/15 5
1.230 Form/ pour new sidewalk 05/15/15 05/21/15 5
1.900 SUBST COMPL LAGOON PIER 05/21/15 0
1.240 Punch list corrections 05/22/15 05/28/15 5
1.800 Demobilize 05/29/15 06/01/15 2
LAGOON HEADWALL
2.100 Mobilize 02/19/15 0
2.110 Demo existing sidewalks 02/19/15 02/25/15 5
2.130 Grade berm area 02/19/15 02/24/15 4
2.150 Fill at berm 02/25/15 02/27/15 3
2.120 Excavate at headwall 02/26/15 03/02/15 3
2.160 Seed berm & disturbed areas 03/02/15 03/03/15 2
2.140 Fill under sidewalks 03/03/15 03/05/15 3
2.170 Install new concrete 03/06/15 03/12/15 5
2.180 Install handrails 03/24/15 03/25/15 2
A/E RVW SUBM HDWL CONCR. MIX
A/E RVW SUBM PILING LOGS
A/E RVW SUBM PIER CONCR. MIX
A/E RVW SUBM PIER LUMBER
A/E RVW SUBM PIER HRDWR-FSTNRS
A/E RVW SUBM PIER QUALS/CERTS
FAB/DELIV HDWL HAND RAILS
FAB/DELIV DUNEX LUMBER
FAB/DELIV DUNEX HRDWR-FSTNRS
FAB/DELIV PILING LOGS
FAB/DELIV PIER LUMBER
FAB/DELIV PIER HRDWR-FSTNRS
Mobilize Demo/ dismantle exstg pier
Remove damaged pilings Install new pilings cut piling tops Install Piling caps
Install substructure Install decking
Install sheet piles demo xstg sidewalks backfill at sheet piles install helical anchors Form/ pour new sheet pile caps
Form/ pour new sidewalk
SUBST COMPL LAGOON PIER
Punch list corrections Demobilize
Mobilize Demo existing sidewalks Grade berm area
Fill at berm Excavate at headwall Seed berm & disturbed areas Fill under sidewalks
Install new concrete Install handrails
Start date 08/21/14 Finish date 06/01/15 Data date 12/15/14 Run date 01/19/15 Page number 2A
© Primavera Systems, Inc.
Start Early
Finish Orig Dur 01
DEC
JAN
FEB
MAR
APR
MAY
JUN
JUL
26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 2
2.900 SUBST COMPL HEADWALL 03/25/15 0
2.190 Punch list corrections 03/26/15 04/01/15 5
2.800 Demobilize 04/02/15 04/03/15 2
DUNE CROSSOVERS
3.100 Mobilize 02/19/15 0
3.110 Surfer's Crossover (10) 03/05/15 03/11/15 5
3.115 Clean area/ relocate eqpt 03/12/15 03/13/15 2
3.120 Dunes Crossover (30) 03/16/15 03/31/15 12
3.125 Clean area/ relocate eqpt 04/01/15 04/02/15 2
3.130 Divers Crossover (30) 04/03/15 04/20/15 12
3.132 Punch list corrections 04/21/15 04/27/15 5
3.135 Clean area/ demobilize 04/28/15 04/29/15 2
3.900 SUBST COMPL CROSSOVERS 04/29/15 0
3.140 Punch list/ Corrections 04/30/15 05/06/15 5
CLOSEOUT
4.910 12/15/14 12/15/14 1
4.900 FINAL COMPLETION 06/01/15 0
SUBST COMPL HEADWALL
Punch list corrections Demobilize
Mobilize
Surfer's Crossover (10) Clean area/ relocate eqpt
Dunes Crossover (30) Clean area/ relocate eqpt
Divers Crossover (30) Punch list corrections Clean area/ demobilize
SUBST COMPL CROSSOVERS
Punch list/ Corrections
FINAL COMPLETION
Start date 08/21/14 Finish date 06/01/15 Data date 12/15/14 Run date 01/19/15 Page number 3A
© Primavera Systems, Inc.
| CN187 A01 CRF |
| CN187 A01 signed |
| CN187 A01 backup |
| Copy of Cover.pdf |
| Front Cover |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| dUNEx GMP FINAL 01 20 2015 |
| 15.01.16 Fees and GCs SASP Dune Xover(9).pdf |
| CONSTRUCTION (9) |
| 15.01.16 Fees and GCs SASP Dune Xover (8).pdf |
| CONSTRUCTION (8) |
dUNEx GMP FINAL 01 20 2015.pdf