This document is a Change Order for Contract CN182 between the Florida Department of Environmental Protection (FDEP), Bureau of Design and Construction, and SWC Construction Inc. for the Wiregrass Trail ADA Improvements project at Falling Waters State Park. The change order involves AMEC Environment & Infrastructure, Inc. as a consulting firm, and includes various governmental and project stakeholders such as C. Hewitt (Project Manager) and Mae Roth (Government Operations Consultant).

The change order extends the project's final completion date by 30 additional days to August 28, 2015, due to issues in determining work corrections needed at the Falling Waters State Park ADA Wiregrass Trail. A supplemental field inspection report identified four locations along the trail route requiring remediation to meet construction specifications, including adjustments to running slopes and cross slopes. The original contract sum was $68,840.00, and the change order does not modify the contract price. The project involves constructing an ADA-compliant trail with specific gradient and slope requirements, with remedial activities needed to bring certain trail sections into compliance with specified construction standards.

View the file

Other files

File Type Posted
CN-370000-CN182-CO1.pdf PDF
CN-370000-CN182-CO2.pdf PDF
CN-370000-CN182-CO3.pdf PDF
CN-370000-CN182.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CN182 CO4

CN182 CO4 backup

File details come from the government source that posted it. Updated .