CN-370000-CN182-CO4.pdf

PDF 4 MB Posted

Attached to
Master Agreement FL|GC677|8cdb278b9b14af8299b99c870b5c82f0
Contract number
GC677
Issued by
Florida

About this file

This document is a Change Order for Contract CN182 between the Florida Department of Environmental Protection (FDEP) and SWC Construction Inc., specifically related to the Wiregrass Trail ADA Improvements project at Falling Waters State Park. The change order involves AMEC Environment & Infrastructure, Inc. as a consulting firm, and involves multiple parties from the Bureau of Design and Construction, including Project Manager C. Hewitt and other state officials.

The change order extends the project's final completion date by 30 additional days, moving the completion date from June 27, 2015 to September 4, 2015, due to issues in determining work that needed correction at the Falling Waters State Park Wiregrass Trail. A supplemental field inspection report identified four locations along the trail route requiring remediation to meet construction specifications, including adjustments to running slopes and cross slopes. The contract's original substantial completion date was December 3, 2014, with the present change order maintaining the original contract sum of $68,840.00 and the current contract sum of $89,194.00. The additional time is intended to allow the contractor to address specific trail construction specifications and slope requirements identified in the inspection report.

View the file

Other files

File Type Posted
CN-370000-CN182-CO3.pdf PDF
CN-370000-CN182.pdf PDF
CN-370000-GC677-T1.pdf PDF
CN-370000-GC677-T2.pdf PDF
CN-370000-GC677-T4 CO1.pdf PDF
CN-370000-GC677-CO001.pdf PDF
CN-370000-GC677-A1.pdf PDF
CN-370000-GC677-T3.pdf PDF
CN-370000-GC677-T4.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CN182 CO4

CN182 CO4 backup

File details come from the government source that posted it. Updated .