CN-370000-CN090-TA1CO1.pdf

PDF 172 KB Posted

Attached to
Master Agreement FL|CN090|5a57f8b353c3b954336d2b6c01517571
Contract number
CN090
Issued by
Florida

About this file

This document is a Deductive Change Order for a Task Assignment related to the Spanish Harbor Bridge Retrofit project, issued by the Department of Environmental Protection (FDEP). The key parties involved include The LPA Group, Inc. as the consultant, Michael Schwier as the contract person, and Michael Baker International as the engineering firm. The change order is associated with Contract No. CN090 and Project No. 67002, located at FKOHT/Spanish Harbor Bridge Retrofit.

The change order reduces the task assignment's value by $12,593.68, bringing the total task amount to $170,978.70. The project is complete, and the deductive change order is being implemented to zero out the costs of Task Assignment #1 (TA#1), which expired prior to project completion. The FDEP created a new task assignment (TA#2) to allow the consultant to continue work necessary to complete the project's permits. The consultant has been contacted and agrees with the deductive change order, which will facilitate closing out the project and returning the remaining encumbered funds to FDEP.

View the file

Other files

File Type Posted
CN-370000-CN090.pdf PDF
CN-370000-CN090-TA1.pdf PDF
CN-370000-CN090-T2.pdf PDF
CN-370000-CN090-TA3.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .