This document is a Task Assignment Notification from the Florida Department of Environmental Protection (DEP) issued to Taylor Engineering, Inc. for the Cat Point Living Shoreline Project in Franklin County, Florida. The project is part of the Deepwater Horizon Natural Resources Damage Assessment (NRDA) Phase III Early Restoration Program, located in Apalachicola Bay near the Apalachicola National Estuarine Research Reserve (ANERR) Environmental Education and Training Center.

The task assignment involves preparing preliminary and final design plans, specifications, and cost estimates for constructing two segmented breakwater systems that will expand existing structures and create salt marsh habitat. The total fixed price for the project is $67,090.15, with services including initial site visits, pre-application meetings with regulatory agencies, boundary and topographic surveys, natural resource investigations, preliminary engineering design, tidal exchange analysis, and regulatory permitting. The project is scheduled to run from May 2, 2016 to May 1, 2018, with various tasks to be completed sequentially, including environmental assessments, design iterations, and permit applications for state and federal agencies.

View the file

Other files

File Type Posted
CN-370000-S0480-TA4.pdf PDF
CN-370000-S0480-T8.pdf PDF
CN-370000-S0480-TA3.pdf PDF
CN-370000-S0480-TA5.pdf PDF
CN-370000-S0480-A1.pdf PDF
CN-370000-S0480-TA1.pdf PDF
CN-370000-S0480-TA6.pdf PDF
CN-370000-S0480-A2.pdf PDF
CN-370000-S0480-CO1.pdf PDF
CN-370000-S0480-TA2.pdf PDF
CN-370000-S0480.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

CONSULTANT’S TASK ASSIGNMENT NOTIFICATION

Required Signatures: Adobe Signature

FDEP Contract No:

No:

Total:

Task Assignment Project No: Owner’s Name:

Project Location: Project:

Consultant’s Name:

Consultant’s Representative: Ph: Email:

FDEP Contract Manager: Ph: Email:

Task Description:

Project Manager Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement not to exceed:

Total Task Amount:

Signatures and Date:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date Encumbrance Information:

Project

Grant

Org Code Category & Year

Fund Module Object Code

EO Amount

OOO-010 (Effective 0 - -2015) Page 1 of 1

CN026 N2103 Franklin County, Florida

Apalachicola Bay, Franklin County, Florida Cat Point Living Shoreline Taylor Engineering, Inc.

Matthew Trammell, P.E. 850-460-7040 mtrammell@taylorengineering.com

Mae Roth 850-245-2781 mae.roth@dep.state.fl.us

The Consultant shall prepare preliminary and final design plans, specifications, and cost estimates illustrating all technical components and requirements for the construction of two (2) segmented breakwater systems that will expand existing structures and create salt marsh habit between the breakwater system and the shoreline.

Pearce Barrett, P.E.

May 2, 2016 May 1, 2018 $67,090.15 0.00

$67,090.15

Kimberly A. Walker Walker_KA Digitally signed by Walker_KA Date: 2016.04.28 09:24:37 -04'00' 04/28/2016

Pearce Barrett, P.E. Barrett_P Digitally signed by Barrett_P Date: 2016.05.16 15:18:37 -04'00'

5/16/2016

Mae Roth Mae Roth Digitally signed by Mae Roth Date: 2016.05.25 11:27:07 -04'00'

5/25/2016

Ken Craig, Vice President

Trina Vielhauer

N2103 NRD03 37220500000 083654 / 12 099005 NRDR 139900 FN $67,090.15

$67,090.15

DEP Agreement No. CN026, Task Assignment #1, Page 1 of 12

TASK ASSIGNMENT

CAT POINT LIVING SHORELINE

The Florida Department of Environmental Protection (“DEP”) has selected Taylor Engineering, Inc.

(“Consultant”) to provide professional services for the Deepwater Horizon Natural Resources Damage Assessment (“NRDA”) Phase III Early Restoration Project, Cat Point Living Shoreline (“Project”) located off the water ward end of Millender Street, Franklin County, Florida within Apalachicola Bay in an area commonly known as Cat Point. Specifically, the project area is centered offshore of the Apalachicola National Estuarine Research Reserve (“ANERR”) Environmental Education and Training Center. This Task Assignment (“Task Assignment”) is issued pursuant to DEP Bureau of Design and Construction (“BDC”) Contract No. CN026 (“Contract”).

Background

As part of the Deepwater Horizon NRDA Early Restoration Program, DEP selected the Consultant to provide professional services for the Project, which is located within Apalachicola Bay just offshore of Cat Point in the vicinity of the ANERR facility. The Project is to construct two (2) segmented breakwater systems that will expand existing structures near the ANERR facility and create salt marsh habit between the breakwater system and the shoreline. The area of the Project was impacted by the Deepwater Horizon oil spill and its related cleanup efforts. This Task Assignment describes the tasks to be completed by the Consultant, including surveying, design, permitting, and limited construction administration services to develop construction documents for the Project. Since the Project is a NRDA Phase III Early Restoration project, it has been previously assessed and determined to be in compliance with the requirements of the National Environmental Policy Act.

Reporting Requirements

The Consultant shall submit monthly progress reports which indicate the work performed during the reporting period, work scheduled for the next reporting period, problems encountered and resolutions of the problems, and any schedule updates. This monthly report shall be provided to the DEP Project Manager within five (5) business days of the close of each proceeding month at no additional cost to DEP.

Additional Services

The Consultant may be requested to provide other professional services related to the Project, as deemed necessary by DEP, based on the availability of funding. Based on DEP’s ability to negotiate a satisfactory price, DEP reserves the right to amend this Task Assignment to include additional services related to the Project’s planning and design, bidding assistance, and construction administration as may become necessary.

Project Construction Documents

The Consultant shall prepare preliminary and final design plans, specifications, and cost estimates illustrating all technical components and requirements for the construction of the Project. An original copy of all final design documents, drawings, and other articles to meet all requirements of DEP, including the DEP BDC’s Contract with the Consultant, this Task Assignment, and any subsequent amendments, DEP Agreement No. CN026, Task Assignment #1, Page 2 of 12 shall be provided to the DEP Project Manager upon completion of the work. These original articles shall contain all original signatures and professional seals as necessary. At a minimum, the Consultant shall provide three (3) complete sets of all documents and drawings and one (1) complete set of documents, drawings and other articles that are reproducible to the DEP Project Manager. Reproducible narrative documents and other articles shall be clear and legible, on eight-and-one-half by eleven-inch (8-1/2” x 11”) paper, and shall not be bound or stapled. Reproducible drawings shall be of a paper from which Xerox type copies can be made. The Project documents and drawings shall also be provided on CD-ROM for bidding purposes.

Project Description The Project consists as follows:

A northern breakwater segment extending approximately 670 feet (offshore of the undeveloped shoreline) between the Bayshore Trailer Park and the existing breakwater that partially fronts the DEP-owned property on Millender Street. A southern breakwater segment shall extend approximately 800 feet south from the southern end of the existing breakwater offshore of the ANERR facility and an approximate 170-foot central breakwater segment, offshore of Millender Street, between the two existing breakwater structures. A saltmarsh habitat shall be created, in the lee of the structures (i.e., the area of reduced wave energy). The proposed breakwater structures would be constructed with rip-rap and/or bagged oyster shell, and the structure crest elevation shall be between the Mean Low Water Line (MLWL) and the Mean High Water Line (MHWL) with a crest width of approximately five (5) feet.

Assumptions

The Consultant has made several assumptions in developing this scope of services and associated fees for the Project. The assumptions affect the proposed level of effort and associated costs. If any of the assumptions should prove incorrect, the Consultant will submit a proposal to modify its scope of services and fees accordingly.

Tasks and Deliverables

Task 1 – Initial Site Visit and Kick-Off Meeting

Description: The Consultant will perform background investigations, perform an initial site visit and conduct a Project kick-off meeting to be held in the ANERR facility located on 108 Island Drive, East Point, Florida. The Consultant, DEP Project Manager and select ANERR staff will participate in the site visit and will also be in attendance during the kick-off meeting. The purpose of the site visit and kick-off meeting is to assess the current conditions at the Project site; review the initial plan for development of the Project;

review the available budget for construction, proposed schedule, and refine the proposed design to reflect current site conditions and construction budget. If available, DEP will assemble and provide to the Consultant previously completed plans, bathymetric surveys, property ownership information, natural resource surveys, regulatory permits and any other information that may be available from the development of the existing living shoreline. This material will be used for the discussions at the scoping meeting. Once the permit pre-application meeting identified in Task 2 has been completed then the Project development and scope may be further refined.

DEP Agreement No. CN026, Task Assignment #1, Page 3 of 12

Sub-Task 1.1 Background Investigations and Initial Site Visit: The Consultant will perform desktop investigations and conduct an initial site visit to assess the background and existing site conditions of the Project site that may be crucial for preliminary structure design. The field review shall observe current environmental and physical conditions at the Project site, and to further ascertain opportunities and/or constraints that may influence design considerations. The site visit and observations will include a detailed review of the existing shoreline, vegetation communities, nearshore, and upland conditions. The team shall also observe the structural condition of existing structures (e.g., breakwaters, oyster-reefs, bulkheads, etc.) along adjacent properties and/or other physical features on the site, and note any specific items of concern for project constructability. Key project team members, including but not limited to the DEP Project Manager and ANERR staff will accompany the Consultant during the initial site visit. The Consultant will coordinate with the DEP Project Manager in scheduling the site visit.

The Consultant will also, in addition to the site visit, conduct desktop investigations of existing information pertinent to the Project area coastline. Such information may include historical and recent topographic and bathymetric surveys; aerial photography; navigation channel and right-of-way boundaries; historic wind records; storm related data (storm surge and wave records); offshore sediment data; and existing literature on coastal processes and environmental issues. Investigations of historical data and aerials may reveal areas of probable impact to submerged aquatic vegetation, historical shoreline positions, and areas of accelerated erosion.

Sub-Task 1.2 Kick-Off Meeting: The Consultant shall coordinate with the DEP Project Manager and schedule a kick-off meeting with key Project team members (DEP Project Manager and ANERR staff) following the site visit. The kick-off meeting will be held the day following the site visit. This meeting will review the findings from the initial site visit, the current conditions at the site, the available construction budget, conceptual design components (materials, design criteria, etc.), information provided by DEP (or ANERR), and previous regulatory consultations for the proposed improvements. The Consultant shall prepare an agenda for the meeting and distribute it to all invited attendees at least two (2) business days prior to the site visit for review and comment.

Deliverables Sub-Tasks 1.1 – 1.2: The Consultant shall provide to the DEP Project Manager an attendance log of those individuals that participated in the site visitation, copies of field notes, sketches and photographs taken during the site visit. The Consultant shall also provide to the DEP Project Manager a copy of the meeting agenda, attendance log and minutes from the kick-off meeting.

Performance Measures Sub-Tasks 1.1 – 1.2: The DEP Project Manager shall review the site visit notes, sketches and photographs to verify satisfactory completion of the services rendered. The DEP Project Manager shall also review the proposed agenda (prior to the meeting), attendance log, and kick-off meeting minutes to verify satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Schedule Sub-Tasks 1.1 – 1.2: The initial site visit and kick-off meeting shall occur within 30 days of final contract authorization and receipt of notice to proceed, unless scheduling conflicts with the DEP Project Manager or Project team members preclude meeting this schedule. Final deliverables will be provided to the DEP Project Manager within one (1) week following the kick-off meeting.

Fixed Price Cost Sub-Tasks 1.1 – 1.2: $8,082.52 (includes Labor $7,498.12 and Direct Expenses for Travel $584.40)

DEP Agreement No. CN026, Task Assignment #1, Page 4 of 12

Direct Expenses: Direct expenses subject to reimbursement shall not exceed $584.40. (Note:

Reimbursement of direct expenses shall be supported by copies of invoices or paid receipts. No mark-ups shall be allowed on direct expenses. Travel expenses and per diem must be documented by a State of Florida Travel Voucher and appropriate receipts. Reimbursement will be made in accordance with Section 112.061, F.S.)

Task 2 – Pre-Application Meeting w/ Regulatory Agencies

Description Task 2: The Consultant will coordinate with the DEP Project Manager and with applicable regulatory agencies (DEP and United States Army Corps of Engineers (USACOE)) and commenting agencies (e.g., National Marine Fisheries Service (NMFS) and United States Fish and Wildlife Services (USFWS)) to schedule a pre-application meeting. The Consultant will conduct the pre-application meeting and shall prepare an agenda and conceptual figures for discussion during this meeting. The Consultant will solicit feedback from the regulatory and commenting agencies to define the requirements of the permit application package. It is the intent of the meeting to have regulators clarify the requirements of potential topographic, bathymetric, and/or property boundary surveys (Task 3), natural resource/submerged aquatic vegetation (SAV) survey(s) (Task 4), hydrographic/tidal exchange analyses (Task 6), and any other specific surveys or analyses required for regulatory authorization. The Consultant will refine Tasks 3, 4, and 6 based upon the feedback received during the meeting and will only proceed with Tasks 3, 4, and 6 if required by regulatory agencies and specifically authorized by the DEP Project Manager to conduct these tasks. Presumably, the joint pre-application meeting will occur in Pensacola, Florida at DEP’s or USACOE’s district office(s).

Deliverables Task 2: The Consultant shall provide to the DEP Project Manager an attendance log, meeting agenda, and meeting minutes of the pre-application meeting.

Performance Measures Task 2: The DEP Project Manager shall review the attendance log, meeting agenda, and meeting minutes of the pre-application meeting to verify satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Schedule Task 2: The Consultant shall begin coordinating the pre-application meeting immediately following the site visit and kick-off meeting (Task 1). The pre-application meeting shall occur within 30 days of the Task 1 services, unless scheduling conflicts with the regulatory staff and/or project team preclude meeting this schedule. Final deliverables will be provided to the DEP Project Manager within one (1) week following the pre-application meeting.

Fixed Price Cost Task 2: $3,540.68 (includes Labor $3,479.08 and Direct Expenses for Travel $61.60) Direct Expenses: Direct expenses subject to reimbursement shall not exceed $61.60. (Note:

Reimbursement of direct expenses shall be supported by copies of invoices or paid receipts. No mark-ups shall be allowed on direct expenses. Travel expenses and per diem must be documented by a State

DEP Agreement No. CN026, Task Assignment #1, Page 5 of 12

Task 3 – Boundary, Topographic/Bathymetric Survey

Description Task 3: If required by the regulatory agencies and authorized by the DEP Project Manager, a boundary, topographic, and bathymetric survey of the State and ANERR property and the area immediately offshore will be performed by the Consultant’s survey sub-consultant. The Consultant’s survey sub-consultant shall perform a boundary and topographic survey to document the upland parcel boundaries, ownership, and nearshore topography (within 100 feet of the MHWL). The survey sub-consultant shall also perform a bathymetric survey of the proposed project areas in order to document the existing bathymetric conditions for regulatory permitting and engineering design. All surveys shall be prepared in State Plane Coordinates, with vertical datum referenced to NAVD 1988 in feet and horizontal datum to NAD, 1983 and in accordance with the “Minimum Technical Standards” set forth by the Florida Board of Professional Surveyors and Mappers in Title G1G17, Florida Administrative Code (FAC).

The boundary, topographic, and bathymetric survey shall include at a minimum the following:

Contours will be generated at one (1) foot intervals based on grade shots taken on a fifty (50) foot grid and including any grade breaks for approximately 100 feet landward and 200 feet seaward.

Locate all visible improvements within survey limits.

A minimum of two (2) benchmarks will be set and shown on the survey.

Locate and show those utilities that are visible and/or marked.

Locate and show the edge of roadway, edge of undergrowth, visible improvements and topography, property lines, easements, coastal construction control line (“CCCL”), or other legal encumbrances upon the various properties included within the limits of the survey shall be shown where known or if provided by DEP and/or ANERR.

Perform a MHWL survey according to DEP requirements.

Locate and show all trees with a diameter greater than twelve (12) inches within the proposed impact (i.e. areas of construction activity, material storage, stockpiling, transport) areas.

Locate and show natural resource areas (e.g. submerged aquatic vegetation (“SAV”), wetlands, wildlife habitat identified in Task 4.)

Identify and locate any navigation markers, pilings or other structures within the survey area.

Locate and show the CCCL running through the Project area.

Deliverables Task 3: If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant shall provide to the DEP Project Manager two (2) copies of the signed and sealed boundary, topographic, and bathymetric survey.

Performance Measures Task 3: The DEP Project Manager shall review the boundary, topographic, and bathymetric survey to verify that all required elements are included and to ensure satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Schedule Task 3: If required by the regulatory agencies and authorized by the DEP Project Manager, the survey field data collection shall be completed within six (6) weeks following the pre-application meeting (Task 2) with the regulatory agencies and the Natural Resource Investigations (Task 4) assuming suitable weather conditions. Final deliverables shall be provided to the DEP Project Manager within 30 days of completing all field data collection.

DEP Agreement No. CN026, Task Assignment #1, Page 6 of 12

Fixed Price Cost Task 3: $12,279.71 (includes Labor $529.71, Survey $9,652.50, and Direct Expenses for Travel $2,097.50) Direct Expenses: Direct expenses subject to reimbursement shall not exceed $2,097.50. (Note:

Reimbursement of direct expenses shall be supported by copies of invoices or paid receipts. No mark-ups shall be allowed on direct expenses. Travel expenses and per diem must be documented by a State

Task 4 – Natural Resource Investigations

Description: If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant will perform natural resource investigations to complete the preliminary design documents and environmental permitting phases of the project as follows:

Sub-Task 4.1 Natural Resource Investigations Survey (NRS): If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant shall perform a NRS to characterize and map existing vegetation communities and habitat conditions along and immediately adjacent to the Project area shoreline. The habitat characterization work will be limited to the shoreline and immediately adjacent areas that may be impacted during construction of the Project.

Sub-Task 4.2 Submerged Aquatic Vegetation Survey (SAV): If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant will perform a SAV survey in accordance with DEP requirements to characterize and map SAV and other submerged resources (e.g., oysters) within the Project area. The Consultant will use the results of the SAV survey to develop a preliminary breakwater design that avoids impacts to SAV or other submerged resources.

The SAV survey area shall be of the nearshore area extending from the MHWL to approximately 100 feet seaward of the existing shoreline (or until the landward edge of vegetation) along the 0.3-miles of shoreline where structures are proposed. This proposed SAV survey area will extend approximately 50 feet beyond the boundaries of the proposed shoreline stabilization activities (in both the alongshore and offshore directions), based on the proposed structure locations described in the project Fish and Wildlife Service ESA consultation report. The SAV survey area may encompass additional distance from the shoreline should structures be placed further seaward at the northern end of the project area to connect with the existing shoreline and structures within this area. Since construction is proposed to be from land-based equipment, surveys of additional offshore areas for barge/equipment corridors will not be proposed.

The SAV survey will employ qualitative and quantitative methods accepted by the state and federal regulatory and resource agencies. No additional environmental data collection or analyses other than those stated herein shall be provided. Should additional environmental data collection or analyses be required from the reviewing agencies (e.g., water or sediment quality investigations), it will be addressed as an additional service to this Task Assignment.

Deliverables Sub-Tasks 4.1 – 4.2: If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant shall provide to the DEP Project Manager a NRS report, which will incorporate

DEP Agreement No. CN026, Task Assignment #1, Page 7 of 12 the SAV survey, to document the survey findings and verify that all required elements are included and to ensure satisfactory completion of the services rendered. The report will include photographs and graphics as necessary to describe existing natural resource habitat conditions within the proposed project area as described above. The NRS report will aid in the development of the preliminary design (Task 5) and provide required data for future regulatory permitting (Task 7).

Performance Measures Sub-Tasks 4.1 – 4.2: The DEP Project Manager shall review the NRS report, which will incorporate the SAV report, to verify that all required elements are included and to ensure satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Schedule Sub-Tasks 4.1 – 4.2: If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant shall perform the NRS (4.1) and SAV (4.2) within four (4) weeks, pending weather, following the pre-application meeting (Task 2). The Consultant will notify DEP Project Manager of any reasonable delays and when actual date of mobilization to the site occurs. The actual date of the NRS will depend on guidance from regulatory staff and weather conditions. SAV surveys are typically required to occur between June and September. NRS report(s) shall be submitted to DEP Project Manager for review within three (3) weeks following the field surveys.

Fixed Price Cost Sub-Tasks 4.1 – 4.2: $13,328.88 (includes Labor $12,078.88 and Direct Expenses for Travel $1,250.00) Direct Expenses: Direct expenses subject to reimbursement shall not exceed $1,250.00. (Note:

Reimbursement of direct expenses shall be supported by copies of invoices or paid receipts. No mark-ups shall be allowed on direct expenses. Travel expenses and per diem must be documented by a State

Task 5 – Preliminary Engineering Design

Description: The Consultant will prepare a preliminary segmented breakwater design for Project permitting. Major components of the preliminary engineering design shall include analysis of coastal conditions and definition of design parameters, structural design of the breakwater components, and the plan-view layout of the breakwater(s). During the kick-off meeting (Task 1) and prior to the preliminary design, the Consultant will seek direction from DEP and ANERR staff regarding the Project design criteria.

Sub-Task 5.1 Coastal Conditions Analysis: The Consultant will conduct a coastal conditions analysis to define key design parameters such as wave characteristics and storm surge elevations at the Project site utilizing background data collected in Task 1, as well as existing site-specific information such as tidal datums, historic storm surge elevations and wind records, critical fetch lengths, and existing bathymetric data. Utilizing historic wind records and Apalachicola Bay bathymetry, we will perform empirical wave modeling to determine probable wave characteristics (e.g., wave heights and periods) during varying-level storm events. These data collection efforts and analyses provide the information necessary to perform preliminary engineering design of the shoreline stabilization structures (e.g., crest height, slopes, DEP Agreement No. CN026, Task Assignment #1, Page 8 of 12 orientation, etc.) and allow ANERR staff to accurately assess the risks associated with varying design conditions and alternatives.

Sub-Task 5.2 Preliminary Engineering Design: Based upon the results of the coastal conditions analysis, the Consultant will perform preliminary engineering design analyses for the proposed segmented breakwaters. The FWS ESA consultation documents state that the proposed breakwater structures should be emergent (crest elevation between the MLWL and the MHWL), with approximate dimensions as follows: crest width of 5 feet, length of 70 feet, gap length up to 25 feet, and distance to shoreline 30 feet.

The consultation result documents the northern segmented breakwater shall be constructed of rock or rip-rap and have a total length of approximately 690 feet and the southern structure shall be constructed of bagged oyster shell with a total length of approximately 750 feet. During the preliminary design, the Consultant will adhere to the general constraints of the design provided in the consultation results;

however, the optimal design may require alteration of the previously proposed design. The Consultant will aim to minimize the structure footprint and the total volume of rock required, therefore, decreasing construction costs and maximizing the total length of protected shoreline. The analysis will focus on readily available materials (e.g., limestone rock rip-rap, bagged oyster shell, and/or recycled concrete) as opposed to larger granite armor stones to further reduce the potential construction costs.

The Consultant will perform an iterative coastal engineering analysis to assess variable structural cross-sections and plan-view layouts against a range of probable design conditions. The structural analysis will provide the general structure details (crest width, footprint, structure slope, and rock size) for these varying conditions. The layout of the structures in plan-view will provide details such as distance from the shoreline, crest length, and gap length between structures. The plan-view design, based on general empirical guidance and wave transmission through and over the segmented breakwater system, will be critical for the success of the salt marsh in lee of the structures.

Sub-Task 5.3 Opinion of Probable Construction Costs (OPCC): The Consultant will prepare an OPCC for the preliminary design(s). The OPCC will comprise a list of major items with associated quantities and unit costs. The Consultant will apply internal and external data to develop a cost opinion for each major Project element. This OPCC will provide the DEP Project Manager and ANERR staff with an initial budget estimate, which will be used to determine the amount of work that can be completed utilizing the funds available for the Project.

Deliverables Sub-Tasks 5.1 – 5.3: Once the preliminary engineering design has been completed, the Consultant will coordinate with the DEP Project Manager and schedule a meeting with the DEP Project Manager and ANERR staff to review the preliminary design(s) and receive comment. The Consultant will make one revision to the preliminary design to incorporate those comments received from the DEP Project Manager and ANERR staff, where feasible, and further develop the preferred concept. The Consultant will prepare a revised preliminary design based upon the comments received during the review and submit to the DEP Project Manager. This revised version of the preliminary design will serve as the basis for Project permitting

Performance Measures Sub-Tasks 5.1 – 5.3: The DEP Project Manager shall review the final preliminary design and OPCC to verify that all required elements are included and to ensure satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

DEP Agreement No. CN026, Task Assignment #1, Page 9 of 12

Schedule Sub-Tasks 5.1 – 5.3: The Consultant shall commence Task 5 services upon completion of Tasks 1 - 4. The Consultant shall prepare the recommended preliminary design within eight (8) weeks of commencement of Task 5, and the final preliminary design within two (2) weeks of conducting the review meeting with the DEP Project Manager and ANERR staff.

Fixed Price Cost Sub-Tasks 5.1 – 5.3: $14,537.98

Task 6 – Tidal Exchange Analysis

Description Task 6: If required by the regulatory agencies and authorized by the DEP Project Manager following the completion of Task 2, the Consultant shall perform a hydrographic assessment to demonstrate that the proposed structure(s) do not adversely affect tidal exchange within the project area.

Given the relatively shallow water, close proximity of the structures to the shoreline, and the restorative nature of the Project, the Consultant will prepare a simplified tidal exchange analysis to satisfy the regulatory agency’s tidal exchange/hydrodynamic requirements. The tidal exchange/hydrodynamic study will include running an empirical tidal exchange analysis of the proposed structure(s) to determine the tidal exchange within the lee of the structures for mean tide conditions. The Consultant will also review the hydrodynamic or similar tidal assessment(s) employed for the existing breakwater structures and utilize this information for further Project support. The Consultant makes no assurances the Project as proposed will meet regulatory requirements. Should the proposed structures not meet the state agency flushing requirements, the Consultant will advise the DEP Project Manager and ANERR staff on possible remedies. Should subsequent flushing analyses be required to address other designs then an amendment to this Task Assignment may be necessary.

Deliverables Task 6: If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant shall provide to the DEP Project Manager a report summarizing the methods and results of the tidal exchange analysis. The deliverable will include all necessary detail typically required for regulatory permitting. The Consultant does not guarantee regulatory agency staff will deem the study complete. Should additional work be required, the Consultant will submit a proposal to modify the scope of services and fees accordingly.

Performance Measures Task 6: The DEP Project Manager shall review the summary report to verify that all required elements are included and to ensure satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Schedule Task 6: If required by the regulatory agencies and authorized by the DEP Project Manager, the Consultant shall commence Task 6 services upon completion of Task 5. The Consultant shall submit the analysis and summary report within four (4) weeks of commencement of Task 6.

Fixed Price Cost Task 6: $4,578.32

DEP Agreement No. CN026, Task Assignment #1, Page 10 of 12

Task 7 – Regulatory Permitting

Description: The Consultant shall prepare complete permit applications for all state and federal permits required to construct the Project and submit to the appropriate regulatory agencies (e.g. DEP, USACOE or the Northwest Florida Water Management District (NWFWMD)). The work under this task shall include

1) the development of permit drawings in the format required by the regulatory agencies for review and

2) completion of the required forms accompanied with sufficient narrative to support the application.

Any fees associated with the applications will be the responsibility of the DEP.

Sub-Task 7.1 Permit Drawings: Once the preliminary designs (Task 5) have been developed and approved by the DEP Project Manager, the Consultant will prepare permit drawings depicting:

Existing conditions, including property boundaries, existing bathymetry and topography, MHWL, structures, and natural resources (identified during previous investigations);

Preliminary structural design sections and details for the offshore breakwaters/oyster habitat;

Shoreline restoration layouts including preliminary design sections and planting/stabilization details; and Proposed environmental protection measures (turbidity curtains, erosion control measures, etc.).

The Consultant will complete the preliminary permit drawings and provide them to the DEP Project Manager and ANERR staff for review and comment. The preliminary permit drawing submittal will provide two sets of eight-and-one-half by eleven-inch (8-1/2” x 11”) paper plots and corresponding digital format drawing files in PDF format. The Consultant will incorporate the comments from the DEP Project Manager and ANERR staff on the preliminary drawings and make any necessary changes to produce final permit drawings.

Sub-Task 7.2 Regulatory Permit Applications: The Project will require an Environmental Resources Permit (“ERP”) issued by DEP or NWFWMD and a U.S. Department of the Army Dredge and Fill Permit from the USACOE. Since DEP and ANERR are the upland property owners, the DEP Project Manager will provide direction to the Consultant as to whether the NWFWMD or DEP will lead the state permitting effort. The Consultant will then develop a joint ERP application that includes the information necessary for state and federal agencies to perform their technical review and public processes. The application, in addition to the permit drawings, will also include narratives describing the project design, purpose and need; project best management practices (BMPs); avoidance and minimization measures; natural resource analyses; tidal flushing analyses (if required); and construction methodology and schedule. The application will include as attachments, the findings from previous tasks such as the natural resource survey report and tidal exchange analysis.

The Consultant will provide copies of the completed application(s) to both the DEP Project Manager and ANERR staff for review and approval prior to submitting to the lead state and federal regulatory agencies.

It will be the responsibility of the lead agencies to distribute the application packages to all other appropriate commenting agencies (e.g. USFWS, National Oceanic and Atmospheric Administration (NOAA), Florida Fish and Wildlife Conservation Commission (FWC)).

Deliverables Sub-Tasks 7.1 – 7.2: The Consultant shall provide to the DEP Project Manager the permit application package (including the joint ERP application, permit drawings, and supporting documents as described in sub-tasks 7.1 and 7.2). The deliverable will include all necessary detail typically required or

DEP Agreement No. CN026, Task Assignment #1, Page 11 of 12 set forth from pre-application meeting(s) with the regulatory agencies and described in this Task Assignment for regulatory permitting. Should additional work outside of the professional services described in this Task Assignment be required by the regulatory agencies, the Consultant will submit a proposal for consideration by the DEP Project Manager to modify this Task Assignment (the scope of services, schedule and fees) accordingly.

Performance Measures Sub-Tasks 7.1 – 7.2: The DEP Project Manager shall review the permit application package to verify that all required elements are included and to ensure satisfactory completion of the services rendered. The DEP Project Manager shall notify the Consultant of any deficiencies in the deliverable(s) and shall give the Consultant reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Schedule Sub-Tasks 7.1 – 7.2: The Consultant shall commence Task 7 services upon completion and receipt of approval by the DEP Project Manager of Task 5. The Consultant shall submit to the DEP Project Managers the permit application package (including all supporting information) within eight (8) weeks of receipt of approval of Task 5. Consultant shall incorporate any comments from DEP Project Manager and shall submit the revised permit application package to the regulatory agencies within two (2) weeks of receipt of comments from the DEP Project Manager.

Fixed Price Cost Sub-Tasks 7.1 – 7.2: $10,742.06

TOTAL FIXED PRICE COST TASKS 1.0 – 7.2: $67,090.15

Excluded Items

The following tasks are excluded from this Task Assignment unless later included through issuance of an amendment to this Task Assignment:

A guarantee that the environmental regulatory agencies will approve permits for the Project;

Upland site layout and design;

Dredging design or permitting;

Geotechnical investigations, including but not limited to, general surface conditions, soil bearing capacity, and potential settlement estimates;

Numerical wave transformation, hydrographic, or sediment transport/morphologic modeling to assess hydrodynamic flushing, wave/structure interactions, long-shore and cross-shore sediment transport, or the potential impacts to adjacent shorelines or property;

Mitigation design, permitting or property;

Regulatory fees associated with the permits or permit application reviews;

Submerged land lease surveying or recording;

Construction permits and fees of any kind from the local municipality or county;

Development of multiple conceptual shoreline stabilization alternatives beyond those described above;

DEP Agreement No. CN026, Task Assignment #1, Page 12 of 12

Additional natural resource or existing condition assessments that the DEP may require beyond those included within this Task Assignment (e.g., water quality or sediment quality assessments, etc.);

RAI support outside of Consultants responsibilities described in this Task Assignment;

Negotiations with State and/or Federal Agencies in regards to preparing requests for waiver of permit conditions considered unreasonable, inappropriate or irrelevant;

Value Engineering or cost comparison for multiple project alternatives;

Endangered or protected species monitoring (e.g., shorebirds, turtles, and/or sturgeon);

Turbidity or other environmental monitoring; and Post-construction monitoring including but not limited to topographic/bathymetric surveys, natural resource surveys [e.g. seagrasses], and/or sand sampling/analyses that may be required by regulatory authorizations.

Services Provided by DEP

The following tasks will be the responsibility of the DEP Project Manager:

a. Coordination with ANERR staff; and

b. Serve as liaison for any questions presented by stakeholders and press.

Note: As used in tasks, “Consultant” includes work performed by the Consultant and their sub-consultants.

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK