CHRISTIANSTED NATIONAL HISTORIC SITE

CHRISTIANSTED, ST. CROIX

Security System Modifications- Danish Customs House

STATEMENT OF WORK

NATIONAL PARK SERVICE

INTERIOR REGION 2

SOUTH ATLANTIC GULF

1 PROJECT INTRODUCTION

Project Title: Security System Improvements at Old Danish Customs House (Customs House)

1.1 Scope

In accordance with the terms and conditions of the Contract, the Contractor shall perform the work for the National Park Service (NPS) as described in this document.

Confidentiality: The information developed in this project is the property of the U.S. Government and shall be kept in strict confidence.

The work to be performed consists of furnishing all labor, materials, equipment, and supervision necessary to modify existing intrusion detection system in accordance with this document and attached project drawings.

1.2 Location

Danish Customs House Christiansted National Historic Site 2100 Church Street St. Croix, US Virgin Island 00820-4611

1.3 Background

The Christiansted National Historic Site (CHRI) commissioned a contract in 2014 for the installation of an integrated intrusion detection and fire detection and alert system at the historic Danish Customs House (H-6, CHRI-1.003, LCS#00190). The intrusion and fire detection systems were installed at the two-level structure, on both the lower Basement Floor and the upper First Floor. The system includes a hardwired fire detection and alarm system, and an integrated intrusion detection system. The intrusion detection system has a hardwired controller, wireless door/window sensors, and interior wireless motion sensors. The door/window sensors are installed at each exterior door and window to indicate the open or closed condition. Two hardwired keypads were installed, one at each main entrance of each floor, to activate and de-activate the system utilizing a preprogrammed employee pin number. The system is connected to an auto-dialer to provide remote notification of events and communications with an offsite monitoring service.

Since its installation, the intrusion detection system has presented multiple and on-going false alarm notifications. These notifications are attributed to the wireless door/window sensors. There is a total of thirty-six (36) of theses sensors installed on the two floors of the facility. These sensors are unreliable and require a significant level of monitoring and maintenance.

Other park facilities, which include the Danish West India Guinea Company Warehouse (DWI GCW) and the Scale House, were equipped with a fire and intrusion detection system which operates independent of the system at the Customs House. The system at these facilities were installed afterwards and configured for interoperability and consolidated control of user access between the facilities. However, the system at the Customs House is not currently integrated with this system.

1.4 Description of Work

This project seeks to enhance the reliability and connectivity of the existing Customs House fire detection and intrusion detection system. These objectives will be accomplished by addressing two overall tasks:

1. Modifying the existing sensors that are used to communicate to the intrusion detection system

2. Integrating the Customs House fire detection and intrusion detection system with the newer fire and intrusion detection system located at the DWI GCW. See project drawings in Attachment A: Old Danish Customs House System Site Plan.

The work to be performed under this project includes furnishing all labor, materials, equipment, and supervision necessary to accomplish the following tasks:

Modify existing Customs House intrusion detection system:

1. Remove and dispose of wireless door and window contact sensors at the upper and lower floors of the Customs House. This item includes removing magnetic contact sensors and fasteners from historic glazed windows of the Customs House facility.

This work requires the skilled and deliberate removal of small metal fasteners at each sensor. All efforts shall be made to mitigate damage to the windows and window frames. This work may require the use of hand tools. This item does not require painting or patching the small screw holes at the historic windows. (Remove Approximately 36 Sensors).

2. Install, connect, and integrate four new wired door magnetic contact sensors at four exterior doors of the Customs House. Doors include two doors at the lower Basement Level and two doors at the upper First Level. (Install 4 Hardwired Door Sensors).

3. Install, integrate two new wireless motion sensors at the lower Basement Level.

(Install 2 Motion Sensors).

4. Reprogram Customs House system controller to account for the removal and addition of system sensors.

Integrate fire and intrusion detection systems for Danish Customs House and DWI Guinea Company Warehouse:

5. Verify connectivity between Customs House system and DWI GCW system. This item may require the installation of new communications circuits to achieve connectivity. Optional bid items for the installation of fiber optic and/or ethernet cable in existing conduit have been added to the bid schedule to account for this possible work.

6. Integrate the Customs House fire and security system with the existing system located at the DWI GCW system. This item includes cable, connectors, fittings, conduit, bracing, programming, and reconfiguration required to establish interoperability, centralized control, and alarm response between the two systems. This item includes modifying the auto-dial response system to allow the Customs House system to contact the remote monitoring service that currently oversees the DWI GCW and Scale House systems. Work shall provide centralized management capabilities of user access accounts between the systems and may require reprogramming system keypads.

1.5 Schedule

The deliverables associated with this project shall be completed in accordance with the following schedule:

Services:

• Services shall not begin until the Contracting Officer has issued the Notice to

Proceed.

• Services shall be completed no later than 180 calendar days after award of the contract.

Deliverables:

• All notes, schematics, drawings, plans, system settings, and operational instructions related to the modification of the original systems completed no later than 60 calendar days after Substantial Completion.

1.6 Government Furnished Items

The NPS will provide access to planning documents, as-constructed drawings, technical manuals, and configuration settings associated with the existing fire and security systems. The Owner will provide access to the project site and system components. The Contractor shall furnish and store all other items necessary for this work.

2 CONSTRUCTION REQUIREMENTS

2.1 Site Conditions

All work performed shall comply with applicable laws, regulations, and NPS policies and guidelines, http://www.nps.gov/dscw/laws-policies.htm. All work shall be installed per the manufacturer’s recommendations.

The Contractor shall determine actual site conditions. Locations, materials, and sizes of utilities are approximate and are not meant to be a complete representation of all utilities present. The Contractor shall determine exact locations and details from the responsible utility authority.

http://www.nps.gov/dscw/laws-policies.htm

Historic Structures: Equipment under this project may be planned for installation at historic structures. Items may require special installation and/or removal considerations to mitigate impact to the historic fabric of the structures. These considerations may include; the use of custom fabricated mounting systems, reduced use of fasteners, special use of adhesives or other mounting solutions, and the special use of paints and coatings. The installation and configuration of cable, conduit, and mounting hardware may vary depending on equipment location. Work at the Custom House requires removing wireless contact sensors form the wooden frames of historic glazed windows. This work shall be skilled and deliberate and may require the use of hand tools to mitigate damage to the windows and wooden frames.

Figure 1: Christiansted NHS Site Map - Customs House and DWI Guinea Company Warehouse

2.2 Environmental and Sustainability Requirements

Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.

Cultural Resources: Work includes the removal of wireless contact sensors from windows at the Danish Custom’s House. The referenced windows are historic and require sensitive treatment. It is very important that the windows and pane glass are not broken or damaged. If archeological resources are damaged at the project site while the archeological monitor is present or absent, all work in the vicinity of the discovery must stop immediately, and the damage must be reported to the Contracting Officer. The Contractor will be held liable for damage that is intentional or that results from negligence.

2.3 Quality Control

The quality of all work shall be the responsibility of the Contractor. The Contractor shall inspect and test all work as needed to ensure the quality of materials, workmanship, construction, finish, and functional performance are in compliance with applicable specifications and drawings.

2.4 Working Hour Restrictions

All work shall be limited to the weekday hours of 7:30 am to 3:30 pm unless otherwise approved by the Contracting Officer. No work shall occur on National Park Service holidays or weekends without prior approval.

2.5 Temporary Controls

Housekeeping: Keep project neat, orderly, and in a safe condition at all times.

Weather Protection: When inclement weather is expected, provide temporary protection, for areas where roofing, siding, windows, doors or other enclosing elements have been removed or have not been installed. Inspect protective coverings frequently to ensure that they are functioning properly.

3 PROJECT CLOSE-OUT

3.1 Deliverables

Provide ONE set of Hard Copy project documents and ONE set of electronic project documents to the Project Manager. Project documents shall include; operation and maintenance data, manufacturer's standard literature, equipment data sheets, vendor- furnished as-built drawings;

custom written data not included in manufacturer’s standard literature; schedules, warranties, parts lists, test results, and settings related to the scope of this project.

Post a single page laminated instructional sheet at each at each of the two alarm keypads providing step-by-step instruction for arming and de-arming the alarm system.

3.2 System Demonstration and Training

As a minimum requirement, the contractor shall provide an on-site explanation of system components, component locations, and system operations. This explanation shall include a demonstration and training of system operations, alarm conditions, arming and de-arming of the system, and adding and removing staff from the system. The training shall include an instructional period and informational literature related to the operations and maintenance of the system. As a minimum the training period shall be no less than one (1) continuous hour in duration and is required to be scheduled a minimum of one-week in advance of planned training date/s. Notification of intended training shall be provided to the Contracting Officer and Project Manager. The Project Manager will coordinate a suitable training environment.

3.3 Substantial Completion and Final Inspection

When work is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The Contracting Officer will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the Contracting Officer will notify the CONTRACTOR in writing.

After completing work, the Contractor shall resubmit certification and request a new final inspection.

3.4 Acceptance of the Work

After all deficiencies have been corrected, the Contracting Officer will issue a Letter of Final Acceptance.

4 TECHNICAL REQUIREMENTS

4.1 Existing System Components

Details of existing Customs House system components and configurations are available in Attachment B: Danish Customs House Intrusion Detection System Components and Attachment C: Danish Customs House As-Constructed Drawings.

Danish Customs House (Customs House):

Existing Customs House System Controller- Honeywell 128BP

Existing Customs House Wireless Module

Existing Wireless Door and Window Contact Sensor-

Existing Wireless Motion Sensor

Existing Customs House Network Switching Equipment-

Danish West India Guinea Company Warehouse (DWI GCW):

Existing Honeywell Fire and Security Controllers-

Existing Honeywell Security Controller-

4.2 Technical Specifications

Network Standards

All work associated with the network communications systems shall be performed in accordance with Federal regulation and the NPS Structured Cable Plan Standard.

PRODUCTS:

NETWORK TRANSMISSION MEDIA

Network Fiber Optic Transmission Media

A. Fiber Optic Media, 50 micro meter, OM4 multiplex type.

B. Connection type compatible with prescribed network switch.

C. Media associated with network backbone communication requires 12 strand (6-pair) media. Media planned for terminal switches may be specified as 6 strand (3-pair) media. See attached project drawings for specific installation requirements.

D. Item includes, Rack Mount Fiber Enclosure, Conversion Modules, Patch Cables, and Installation of media and fusion of fiber strands.

E. See Attachment A: NPS Cabling Standards for specific product requirements, installation requirements, and labeling and testing fiber optic media.

Ethernet Cable

A. Camera Ethernet Cable shall be consistent for all cameras installed under this project.

The cable shall be Plenum rated and designed for outdoor application where wet or submerged conditions may exist.

Requirements:

1. Type: Cat 6 F/UTP Shielded Plenum Rated Indoor-Outdoor Ethernet Cable.

2. Conductors: 23 AWG 4 Pair Solid Bare Copper.

3. Termination: Cat 6 RJ45 connectors, 23 AWG solid conductors or larger.

4. Protection: Overall foil shielding with integral drain wire.

5. UL Verified Category 6. Supports bandwidth of up to 250 MHz.

6. UL Verified (B627696) for long-term water submersion.

7. UL Listed for use in plenum areas.

8. UV Resistant jacket.

9. No-Gel Construction

10. Rated to 100 watts of power transmission.

11. Made in USA.

12. Color: White.

13. Products:

14. Hitachi Drybit Category 6 FUTP Indoor-Outdoor Cable or Approved Equal.

1 PROJECT INTRODUCTION
1.1 Scope
1.2 Location
1.3 Background
1.4 Description of Work
Modify existing Customs House intrusion detection system:
Integrate fire and intrusion detection systems for Danish Customs House and DWI Guinea Company Warehouse:
1.5 Schedule
1.6 Government Furnished Items
2 CONSTRUCTION REQUIREMENTS
2.2 Environmental and Sustainability Requirements
2.3 Quality Control
2.4 Working Hour Restrictions
2.5 Temporary Controls
3 PROJECT CLOSE-OUT
3.2 System Demonstration and Training
3.3 Substantial Completion and Final Inspection
3.4 Acceptance of the Work
4 TECHNICAL REQUIREMENTS
4.2 Technical Specifications