Calculation of Self Performance Work.pdf
PDF 120 KB Posted
- Solicitation number
- 36C24922B0024
About this file
This document provides guidance for calculating the percentage of self-performed work on a federal contract for replacing flooring and abatement at a Veterans Affairs facility in Nashville, Tennessee. The solicitation requires offerors for general construction work under NAICS code 236220 to self-perform at least 15% of the total contract costs incurred for personnel, or 25% for specialty trades with NAICS codes beginning with 237 or 238. Offerors must submit a breakdown of personnel and material/equipment costs by specification division, with a subtotal calculated before adding overhead, profit, fees, and bond costs. They must also clearly identify the personnel costs for work they will self-perform versus work performed by eligible small business subcontractors. The suggested format includes lines to enter these costs by specification division and calculates the total amount and percentage of self-performed work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24922B0024 0002.pdf | ||
| WD TN20220178 6-17-22.pdf | ||
| 36C24922B0024 0001.docx | DOCX document | |
| Specs 626-22-501_Flooring and Abatement_.pdf | ||
| Header - List of Attachments.docx | DOCX document | |
| Contractor EMR Certification Form.pdf | ||
| WD 20220178 5-6-22.pdf | ||
| RFI Form - Replace flooring and abatement.pdf | ||
| Drawings 626-22-501 Flooring and Abatement_.pdf | ||
| 36C24922B0024_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK Project # 626-22-501 Replace Flooring and Abatement
Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for specialty trade NAICS codes with 237 and 238 prefix) of the cost of the contract performance incurred for personnel must be performed by the Service Disabled Veteran Owned Small Business (SDVOSB) awardee or those of a verified SDVOSB subcontractor. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
Specification Division SDVOB Vendor (Y or N) Personnel Cost Material/Equipment Costs Division 01 $ $ Division 02 $ $ Division 03 $ $ (Add additional lines as necessary for each Division applicable to this project)
Sub Total (Personnel Costs, Material/Equipment Costs)
Profit $ Home Office Overhead $ Bond $ Grand Total $
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $
3. Remainder is ‘Total amount of work to be self-performed under the Contract’: $
4. Self-performed work = Line 3/Line 1 x 100 = %
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)