This is Amendment 1 to a federal contract solicitation consisting of Requests for Information (RFI) and clarifications regarding an arc flash assessment and electrical study update project for USDA facilities.
The project involves updating a 2022 electrical short-circuit and arc flash study for a 91-building campus with 663 electrical panels. The contractor must perform limited field spot verification focused only on new or modified equipment added since 2022, which the Government will identify in advance—approximately 15 to 20 new panels plus two buildings with changed electrical service (one converted from 13.8kV to 13.2kV and one new building fed from Building 5). The Government will provide all 2022 SKM PowerTools project files, library files, one-line diagrams in editable format (.drw files and PDFs), and existing panel datasets as starting points. The contractor must obtain updated utility short-circuit and fault contribution data independently from two feeders (Alliant Energy and City of Ames). Field verification must verify upstream and downstream protective device settings and feeder/conductor data only for affected panels. The contractor must update SKM models and one-line drawings for modified areas only, with coordination study updates limited to modified areas and any changes in utility fault data. Arc flash analysis must use the latest versions of NFPA 70E and IEEE 1584 standards. All labels must be updated and field-installed with outdoor-rated, color-formatted labeling per Government-provided examples. The contractor must provide mitigation recommendations only, with USDA staff implementing corrections. One draft review cycle of the report and one-line drawings is required, with the Government needing one week for comments. Government escorts will be provided throughout the project during normal work hours (7:00 AM to 3:30 PM, Monday through Friday). The warranty applies only to labels. Offerors must acknowledge this amendment per SF 30 Box 11 instructions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C05_SolicitationAmendmentAttachment5NorthShortCircuitReport_1232SA26Q0763.pdf | ||
| C05_SolicitationAmendment1_1232SA26Q0763.pdf | ||
| C05_SolicitationAmendmentAttachment6SouthShortCircuitReport_1232SA26Q0763.pdf | ||
| C05_SolicitationAmendmentAttachment7AppFSampleLabels_1232SA26Q0763.pdf | ||
| 1232SA26Q0763.pdf | ||
| SolicitationAttachment2QASP_1232SA26Q0763.pdf | ||
| SolicitationAttachment1PWS_1232SA26Q0763.pdf | ||
| SolicitationAttachment3Wage Determination_1232SA26Q0763.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 1 RFIs and additional information.
Offerors must acknowledge this amendment. See instructions in Box 11 of the SF 30.
The following will be added as attachments to the award:
Attachment 4, Requests for Information Attachment 5, North Short Circuit Report Attachment 6, South Short Circuit Report Attachment 7, App F Sample Labels
Requests for Information:
1) Is there any way you could send over reports / drawings from the previous study, or any information to better understand electrical density? Answer: Reports attached.
2) Regarding Section 3.0, Task 2 "Field Spot Verification": The scope states that because minimal system changes have occurred since 2022, only "limited" field spot-verification is required.
Task 2 — Field Spot Verification
a. Confirm select breaker/fuse settings
b. Verify new or modified panels
c. Document findings with photos While Task 2b requires us to verify new or modified panels, Task 2a separately asks the contractor to confirm "select" breaker/fuse settings. Could the Government please clarify approximately how many, or what percentage, of the existing 663 panels should be opened to satisfy the "select" verification requirement in Task 2a?
Does this essentially mean Field Spot Verification of new equipment added after 2022 study or am I reading too much into the task?
Answer: This is just to verify the new equipment that has been added since 2022.
3) The Statement of Work (Section 1.0) states that the Government will provide the 2022 SKM PowerTools project file to the winning contractor. Could you please clarify if the SKM library file (.lib) associated with that 2022 study will also be provided alongside the project file? Answer:
Yes, all files from the 2022 assessment will be given to the awarded contractor.
4) Since the SOW states that minimal system changes have occurred since the 2022 study and that only limited field spot-verification is required, can the Government confirm the expected extent of field verification (for example, approximate percentage of panels/equipment to be spot-checked, or whether verification is limited only to known modified locations)? Answer:
Verification will be limited to new or modified locations. This is a very small percentage of the total panels. Of the 663 panels, there are approximately 15 to 20 new ones. We have had 1 building that was changed from 13.8kV to a 13.2kV service and one new building that is fed from building 5. Those panels and feeders will need to be assessed to ensure the breaker settings are correct for the new services.
5) Please confirm whether the Contractor is expected to open and inspect all 663 panels, or whether the requirement is to update the study for all 663 panels while performing field verification only on selected equipment. Answer: Just the new or modified panels.
6) For new or modified panels, will the Government identify these locations in advance, or is the Contractor expected to determine them entirely during the site visit/field verification process? Answer: Yes, the USDA will identify those in advance.
7) Can the Government clarify whether the scope includes verification of upstream protective device settings only, or whether downstream device settings and feeder/conductor data must also be revalidated in the field? Answer: Since only some of the panels have changed feeds or have been added, only those that would be affected by these changes need to have their protective devices verified. Upstream and down.
8) If discrepancies are identified between the 2022 documentation and field conditions, should the Contractor update only the affected portions of the model and drawings, or perform broader validation beyond those discrepancies? Answer: If by discrepancy you mean “mistake” then, yes, the contractor shall bring that to the attention of the COR. If discrepancy means “something new has been added” then yes, the contractor shall update this accordingly.
9) The SOW indicates that the Government will provide the 2022 SKM PowerTools project file and 2022 one-line diagrams. Please confirm whether these files will be provided in editable native format (e.g., SKM working file and CAD source files), in addition to PDF copies if available. Answer: The SKM files we have are extensive and include “.drw” files. There are some pdfs with these. I will give all these files to the awarded contractor.
10) Please confirm whether utility short-circuit / fault contribution data will be provided by the Government, or whether the Contractor is expected to obtain updated utility data independently. Answer: Utility short circuit/fault data will be expected to be obtained by the contractor. We are fed by 2 feeders on out site. Alliant Energy and city of Ames. Contractor will need to contact them for that information.
11) For the required complete panel dataset (all 663 panels), can the Government clarify whether an existing panel database/schedule will be furnished as a starting point, or whether the Contractor is expected to build a complete dataset from scratch? Answer: The SKM files should have all the panel datasets. Contractor can use that and only add what is new or has been modified.
12) If electrical one-line drawings or panel schedules have been revised since 2022 by others, will those revised documents be made available to the successful Contractor before field work begins? Answer: No one lines have been revised since 2022. Contractor will be given the 2022 one lines and then revise them as part of this project.
13) Please confirm whether the Government expects a full coordination study update for the entire campus, or only coordination revisions as needed, where changed settings or discrepancies are identified. Answer: Only in the modified areas. If the utility fault data has changed since 2022, then this will need to be addressed during this study. If nothing has changed then nothing will need to change, other than the areas that have changed or been modified since 2022.
14) Can the Government confirm the required basis of calculation / standard edition for the updated arc flash analysis (for example, whether the current IEEE 1584 methodology is required throughout)? Answer: Latest versions of the NFPA70E and IEEE 1584
15) Does the Government expect the Contractor to provide mitigation recommendations only, or also a construction-level scope / implementation-level recommendations for any mitigation measures identified in the report? Answer: Mitigation recommendations only. USDA staff will make the corrections.
16) The SOW notes that the Contractor will develop a construction bid that itemizes the level of effort identified in the SOW and per the bid for construction documents. Please clarify whether this project requires only the arc flash assessment/update services, or also a separate priced implementation/construction package for future corrective work. Answer: Only the arc flash assessment/update services
17) If field installation of labels is required, please confirm whether labels are required on all assessed equipment or only on equipment whose incident energy/arc flash results have changed from the 2022 study. Answer: All labels will need to be updated and field installed by the contractor.
18) Can the Government provide the expected label material/specification requirements (e.g., adhesive type, environmental durability, color format, size, lamination, or preferred manufacturer standard)? Answer: Contractor shall provide a submittal of arc flash labeling. Label must be able to withstand being outdoors, adhesive must be outdoor rated, color formatting shall follow the example provided.
19) Please clarify whether draft submittals (draft report/draft labels/draft one-lines) are required for Government review before final submission, and if so, what review duration should be assumed for Government comments. Answer: One review of report and one lines. USDA will need one week to review and comment.
20) The SOW states that the Government will provide facility access and escorts. Please confirm whether escorts will be continuously available during all field activities, and whether any limitations on daily access duration should be assumed in the quotation. Answer: Contractor will be provided a government escort for the duration of the project. No special requirements for daily access.
21) Are there any buildings, rooms, or electrical spaces within the 91-building scope that will require additional security clearances, special health/sanitation protocols, or restricted scheduling windows beyond normal contractor access requirements? Answer: No
22) If work must occur outside the normal work hours of 7:00 AM to 3:30 PM, Monday through Friday, does the Government anticipate any restrictions on the number of after-hours requests that may be approved? Answer: Work should all fall within normal work hours and anything past that will be reviewed and approved by the COR
23) The closeout section references a one-year warranty for all work. Please clarify how the warranty applies to an engineering assessment/update project, particularly for analytical deliverables such as the SKM model, calculations, and labels. Answer: Warranty will only be for the labels.