STATEMENT OF WORK

5/19/2020 Shadow Bay Campground Water Well Page 1 of 29

USDA FOREST SERVICE - R6 PACIFIC NORTHWEST

WILLAMETTE NATIONAL FOREST

MIDDLE FORK RANGER DISTRICT

LANE COUNTY OREGON

OREGON PUBLIC WATER SYSTEM #4192815

SHADOW BAY CAMPGROUND

WATER WELL

5/19/2020 Shadow Bay Campground Water Well Page 2 of 29

1. PART 1 - GENERAL

1.01 SUMMARY

A. This project connects Shadow Bay Campground to an underground water supply (well) removing the current surface water source (Waldo Lake) to provide a safer water supply. This is an update to the existing OHA public water system #4192815 records.

B. The work of this Contract includes all labor and materials required to:

1. Drill and develop new water well (100 feet minimum depth producing a minimum 20 gpm of water).

2. Install pitless adapter in well.

3. Construct concrete pad with Transenclosure over well.

3. Install new submersible pump in well.

4. Install water level transducer in well.

5. Retrofit pump controls in water system building from removed wet well submersible pump to operate well submersible pump.

6. Install water level display (stand-alone unit) display connected to transducer in well.

7. Install water pipe with power cable and transducer cable in joint trench between from well to water system building.

8. Cap and abandon the existing Waldo Lake surface water inlet pipe, remove submersible pump, fill and abandon pump wet well.

C. New site work (outside of water system building to depth of well pump) piping and electrical wiring will be paid by actual quantities (AQ) installed depending on actual well location and depth verified with CO.

D. All materials and construction shall be in accordance with this SOW, Plans / Details, Project Specifications and/or the manufacturer’s recommendations; Federal, State, and local building codes; and industry standards. In the event of discrepancies between these requirements, the most stringent requirements shall apply, unless otherwise approved in writing by the Contracting Officer.

E. This project shall require construction by an Oregon of State licensed plumbing / electrical contractor and all aspects shall comply with the Oregon Administrative Rules for Well Construction issued by the Oregon Water Resources Department.

F. Contractors are strongly encouraged to visit this project site prior to submitting their bid to verify the details of the scope of work, including the location of the project and proposed improvements, existing conditions, vehicle maneuver clearances, actual distances, feasibility of the work as described, etc. Coordinate site visits with USFS Middle Fork Ranger Station - Recreation Department: Chloe Goldade-Holbrook

(541) 782-5230. All project / contract questions shall only be addressed to the Contracting Officer.

G. This project site is accessible by wheeled vehicle but is not open for public access. The Contractor shall keep existing gate(s) closed and locked or provide temporary vehicle barriers /chains / cables to prevent

5/19/2020 Shadow Bay Campground Water Well Page 3 of 29 public vehicle access when contractor is not on-site if well head is not yet sealed/secured or there are safety, or potential hazards to public.

1.02 PROJECT LOCATION

A. The project is located East of Eugene Oregon at Waldo Lake. From Eugene Oregon, travel on Highway 58 approximately 67 miles. Turn left (North) onto Forest Road #5897 and travel approximately 6 miles to Forest Road #5896 intersection. . Travel approximately 1.5 miles on Forest Service Road# 5896 to Shadow Bay Campground project site.

Elevation is approximately 5,400 feet.

B. Approximate Coordinates: N 43.701084, W 122.042825

5/19/2020 Shadow Bay Campground Water Well Page 4 of 29

5/19/2020 Shadow Bay Campground Water Well Page 5 of 29

1.03 CURRENT CONDITIONS

A. Project site has open areas surrounded by openly spaced conifer trees with grass ground cover and some exposed soil. Slopes are gradual toward the west with some soil mounds and exposed rock. Access to the project site is by a unpaved roadway extending from the Shadow Bay Campground asphalt roadway loop. No roadway improvements or clearing is anticipated for vehicle access or maneuvering.

B. Soils are typical of area. Refer to USDA National Cooperative Soil Survey (NCSS) for soil survey information available online https://websoilsurvey.nrcs.usda.gov No specific site geotechnical reports are available.

C. The Following photos show the general project site conditions.

Photo #1. Water System Building. Back and West Side showing generator air intake and exhaust.

https://websoilsurvey.nrcs.usda.gov/

5/19/2020 Shadow Bay Campground Water Well Page 6 of 29

Photo #2. Access Roadway at Side of Water System Building.

Photo #3. New Well Area South / West of Water System Building.. Typical ground cover. Valve Boxes shown of existing piping from Waldo Lake.

5/19/2020 Shadow Bay Campground Water Well Page 7 of 29

Photo #4. West side of Water System Building. Pump electrical conduit entrance through wall exterior. Entrance doors on South side.

5/19/2020 Shadow Bay Campground Water Well Page 8 of 29

Photo #5. Inside West wall of Water System Building. Existing electrical panel and pump control panels on right side.

5/19/2020 Shadow Bay Campground Water Well Page 9 of 29

Photo #6. Inside West wall of Water System Building. Existing electrical panel and pump control panels on right side.

5/19/2020 Shadow Bay Campground Water Well Page 10 of 29

Photo #7. Inside West wall of Water Pump Building. Existing electrical panel to remain with 20 amp circuit for existing submersible pump at Waldo Lake inlet.

5/19/2020 Shadow Bay Campground Water Well Page 11 of 29

Photo #8. Inside west wall of Water Pump Building. Existing storage tank float relays.

5/19/2020 Shadow Bay Campground Water Well Page 12 of 29

Photo #9. Inside north wall of Water Pump Building. Existing propane generator to remain.

Photo #10. Inside of Water Pump Building. Existing propane generator to remain.

5/19/2020 Shadow Bay Campground Water Well Page 13 of 29

1.04 DESIGN HYDRAULIC INFORMATION.

A. Existing Hydraulic Conditions shown are from available records and may not represent all improvements. Assigned elevation benchmark. Need to field verify.

Existing Pump at Waldo Lake STA 80+87 EL = 1113.5 Existing Generator/Chlorinator STA 74+87 EL = 1150 Storage Tank Entrance STA 29+60 EL = 1297 Storage Tank Full STA 29+60 EL = 1311

B. Piping.

3” PVC Pipe between lake and Water System Building.

3” PVC Pipe between Water System Building to Storage Tank.

C. Existing 30,000 gallon concrete storage tank.

D. Design water demand and flow calculation for Shadow Bay CG.

Shadow Bay CG has 96 camping spaces x 3 people per space average = 288 people.

FSH 7409.11 Water Consumption 20-30 gpd per person (Camping w/flush toilets)

Average Daily Water Demand 20gpd x 288 people =5,760 gpd

Average Daily Flow 5,760 gpd / 24 hours per day / 60 minutes per hour = 4 gpm

Peak Daily Flow 4 gpm x 5 (peak factor) = 20 gpm

E. Pump Hydraulic Calculations. Field Verify Elevations along with Well Log to draw down pumping level and distance to well. Complete Total Dynamic Head (TDH) with Pump submittal.

Partial Data:

Static Head =

161 feet elevation difference. Top of storage tank inlet to top of well (surface elevation near well).

Dynamic Head

4,527 feet 3-inch PVC pipe from water system building to storage tank.

5/19/2020 Shadow Bay Campground Water Well Page 14 of 29

Preliminary Pump Selection: Top of storage tank inlet - surface elevation near well = 161 feet. Allows for 139 feet of additional TDH (field verify measurements) for selected 20 gpm 300 TDH pump.

1.05 REFERENCES

A. American Society for Testing and Materials (ASTM) B. National Sanitation Foundation (NSF) C. Oregon Administrative Rules (OAR) D. Oregon Revised Statutes (ORS) E. Uniform Plumbing Code (UPC) F. Federal Highways FP-14 G. Project Specifications (CSI format)

1.06 SUBMITTALS

A. Work Schedule

1. Submit a proposed work schedule detailing the work in sufficient detail to show the approximate days that significant work items (i.e.

mobilization, site preparation, drilling, testing etc.) for each portion of the project will be conducted.

2. The Contractor shall allow enough time for review and approval of the schedule at least 7 days in advance of schedule dates (unless otherwise approved) to give Forest Service personnel time to prepare for partial closures and other disruptions.

B. Pump and Controls

1. Submit manufacturer data sheets of selected pump model and controls to the CO. Include electrical schematic of existing wiring to pump controls, power supply connection, float wiring connection, along with associated new work, selected pump model curve with pump head elevations and distances (static and dynamic head) for review and approval.

C. Product Information

1. Submit manufacturer's product information and installation recommendations for the materials and equipment proposed for use in this Contract.

2. Submit to the Contracting Officer two (2) sets of product data/catalog cut sheets in hard copy, or submit a single electronic (pdf) copy of clean, easy to read product sheets. Product submittals shall include the material data for the product and the manufacturer's installation, operating, and maintenance instructions for all material and equipment that is proposed to be used for this Work.

3. Allow three (3) working days for Government review of submittals. If resubmittals are necessary, allow three (3) working days for review of the resubmittals, and so on.

4. Obtain written approval for the above submittals prior to construction, assembly, and delivery.

5/19/2020 Shadow Bay Campground Water Well Page 15 of 29

5. Furnish complete material submittals where possible. Partial submittals will be considered only to allow timely ordering of material.

6. Submittals shall have sufficient detail to determine if ratings, characteristics, and physical construction are equivalent to those specified.

7. Where manufacturer's catalog sheets are used, indicate the specific items to be supplied in ink either by arrow, encircled on the sheet, or the inapplicable portion blocked out. List manufacturer's name, contract, section and drawing sheet reference number on each catalog sheet. Identify where material is to be used.

8. Submittals shall show any changes to be made resulting from proposed substitution of equipment or material for those that are specified.

D. Laboratory Bacteriological Test

1. Submit 1 copy of Laboratory Bacteriological Test results to the CO within 15 days of completion and acceptance of construction.

E. Operation and Maintenance Manual / As-Builts

1. Submit to the Contracting Officer one (1) bound set (to remain at water treatment building) of installed product data/catalog cut sheets, manufacturer warranties, as-built plans and details, with operation instructions, troubleshooting guide and system maintenance requirements in hard copy AND submit one (1) single electronic (pdf) copy within 15 days of completion and acceptance of construction.

1.07 PROTECTION OF EXISTING FACILITIES

A. The Contractor shall be responsible for locating and protecting existing structures, trees, and utilities (including underground) that are not designated for removal during construction operations. In the event of damage to existing structures, trees, or utilities, stop all work associated with the damage, and immediately notify the Contracting Officer. Repair the damage as directed by the Contracting Officer at the Contractor’s expense.

B. Fire Restrictions. Check (daily) current fire danger level with the USFS Middle Fork Ranger Station. Comply with any work activities restrictions and provide firefighting tools and equipment (as required).

C. Contractor shall be given a key(s) for water treatment building and any project site entrance gate(s) during construction period. Key(s) shall be returned upon completion of project. Gates shall remain locked when contactor is not present.

D. Vehicles shall remain on roadways or approved otherwise by CO. Any operation that will result in soil disturbance that can contribute to the introduction and spread of invasive plants shall be mitigated. Mitigations (Executive Order 13112) to reduce this risk include:

1. Reduce ground disturbance to the minimum necessary to complete project.

5/19/2020 Shadow Bay Campground Water Well Page 16 of 29

2. All heavy equipment (excluding passenger vehicles) shall be clean and free of soil, vegetative matter, or other debris that may contain or hold weed seeds prior to entering National Forest System lands (WO-B/BT 6.36). Coordinate equipment inspection / verification with CO prior to mobilization.

1.08 QUALITY ASSURANCE

A. Provide and install all materials in accordance with the product manufacturer’s recommendations; Federal, State, and local building codes; and industry standards.

1.09 SAFETY

A. All work shall be done in accordance with Occupational Safety and

Health Act (OSHA) regulations, and all Oregon OSHA.

1.10 WARRANTY

A. Contractor shall be responsible for assembling all applicable warranty information and delivering to the Contracting Officer prior to final payment.

1.11 DRAWINGS

A. Refer to the following drawings for construction plans and details.

5/19/2020 Shadow Bay Campground Water Well Page 17 of 29

5/19/2020 Shadow Bay Campground Water Well Page 18 of 29

5/19/2020 Shadow Bay Campground Water Well Page 19 of 29

5/19/2020 Shadow Bay Campground Water Well Page 20 of 29

5/19/2020 Shadow Bay Campground Water Well Page 21 of 29

5/19/2020 Shadow Bay Campground Water Well Page 22 of 29

5/19/2020 Shadow Bay Campground Water Well Page 23 of 29

5/19/2020 Shadow Bay Campground Water Well Page 24 of 29

5/19/2020 Shadow Bay Campground Water Well Page 25 of 29

5/19/2020 Shadow Bay Campground Water Well Page 26 of 29

5/19/2020 Shadow Bay Campground Water Well Page 27 of 29

5/19/2020 Shadow Bay Campground Water Well Page 28 of 29

5/19/2020 Shadow Bay Campground Water Well Page 29 of 29

2. PART 2 – PRODUCTS (NOT USED)

3. PART 3 – EXECUTION (NOT USED)

4. PART 4 - MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT

A. There will be no separate measurement or payment for work in this section.

Payment will be included at the contract unit price as shown on the Schedule of items and project specifications for method of measurement.

ATTACHMENTS:

PROJECT SPECIFICATIONS

SECTION 01025 MEASUREMENT AND PAYMENT

SECTION 001200 MOBILIZATION

SECTION 017700 PROJECT CLOSEOUT

SECTION 024113 SELECTIVE SITE DEMOLITION

SECTION 02520 WELLS

SECTION 02730 WELL ABANDONMENT

SECTION 031000 CONCRETE FORMS AND ACCESSORIES

SECTION 032000 CONCRETE REINFORCEMENT

SECTION 033000 CAST-IN-PLACE CONCRETE

SECTION 331113 UTILITY PIPE MATERIALS

SECTION 262716 FIBERGLASS TRANSCLOSURE

SECTION 312500 SEDIMENT AND EROSION CONTROL MEASURES

SECTION 332100 WELL PUMP AND CONTROLS

END OF STATEMENT OF WORK

1. Part 1 - GENERAL
1.01 SUMMARY
A. This project connects Shadow Bay Campground to an underground water supply (well) removing the current surface water source (Waldo Lake) to provide a safer water supply. This is an update to the existing OHA public water system #4192815 records.
B. The work of this Contract includes all labor and materials required to:
1. Drill and develop new water well (100 feet minimum depth producing a minimum 20 gpm of water).
2. Install pitless adapter in well.
3. Construct concrete pad with Transenclosure over well.
3. Install new submersible pump in well.
4. Install water level transducer in well.
5. Retrofit pump controls in water system building from removed wet well submersible pump to operate well submersible pump.
6. Install water level display (stand-alone unit) display connected to transducer in well.
7. Install water pipe with power cable and transducer cable in joint trench between from well to water system building.
8. Cap and abandon the existing Waldo Lake surface water inlet pipe, remove submersible pump, fill and abandon pump wet well.
C. New site work (outside of water system building to depth of well pump) piping and electrical wiring will be paid by actual quantities (AQ) installed depending on actual well location and depth verified with CO.
D. All materials and construction shall be in accordance with this SOW, Plans / Details, Project Specifications and/or the manufacturer’s recommendations; Federal, State, and local building codes; and industry standards. In the event of discrepancies...
E. This project shall require construction by an Oregon of State licensed plumbing / electrical contractor and all aspects shall comply with the Oregon Administrative Rules for Well Construction issued by the Oregon Water Resources Department.
F. Contractors are strongly encouraged to visit this project site prior to submitting their bid to verify the details of the scope of work, including the location of the project and proposed improvements, existing conditions, vehicle maneuver clearanc...
G. This project site is accessible by wheeled vehicle but is not open for public access. The Contractor shall keep existing gate(s) closed and locked or provide temporary vehicle barriers /chains / cables to prevent public vehicle access when contract...
1.02 project location
A. The project is located East of Eugene Oregon at Waldo Lake. From Eugene Oregon, travel on Highway 58 approximately 67 miles. Turn left (North) onto Forest Road #5897 and travel approximately 6 miles to Forest Road #5896 intersection. . Travel appr...
B. Approximate Coordinates: N 43.701084, W 122.042825
1.03 current conditions
A. Project site has open areas surrounded by openly spaced conifer trees with grass ground cover and some exposed soil. Slopes are gradual toward the west with some soil mounds and exposed rock. Access to the project site is by a unpaved roadway exte...
B. Soils are typical of area. Refer to USDA National Cooperative Soil Survey (NCSS) for soil survey information available online https://websoilsurvey.nrcs.usda.gov No specific site geotechnical reports are available.
C. The Following photos show the general project site conditions.
Photo #1. Water System Building. Back and West Side showing generator air intake and exhaust.
Photo #2. Access Roadway at Side of Water System Building.
Photo #3. New Well Area South / West of Water System Building.. Typical ground cover. Valve Boxes shown of existing piping from Waldo Lake.
Photo #4. West side of Water System Building. Pump electrical conduit entrance through wall exterior. Entrance doors on South side.
Photo #5. Inside West wall of Water System Building. Existing electrical panel and pump control panels on right side.
Photo #6. Inside West wall of Water System Building. Existing electrical panel and pump control panels on right side.
Photo #7. Inside West wall of Water Pump Building. Existing electrical panel to remain with 20 amp circuit for existing submersible pump at Waldo Lake inlet.
Photo #8. Inside west wall of Water Pump Building. Existing storage tank float relays.
Photo #9. Inside north wall of Water Pump Building. Existing propane generator to remain.
Photo #10. Inside of Water Pump Building. Existing propane generator to remain.
1.04 dESIGN HYDRAULIC information.
A. Existing Hydraulic Conditions shown are from available records and may not represent all improvements. Assigned elevation benchmark. Need to field verify.
Existing Pump at Waldo Lake STA 80+87 EL = 1113.5
Existing Generator/Chlorinator STA 74+87 EL = 1150
Storage Tank Entrance STA 29+60 EL = 1297
Storage Tank Full STA 29+60 EL = 1311
B. Piping.
3” PVC Pipe between lake and Water System Building.
3” PVC Pipe between Water System Building to Storage Tank.
C. Existing 30,000 gallon concrete storage tank.
D. Design water demand and flow calculation for Shadow Bay CG.
Shadow Bay CG has 96 camping spaces x 3 people per space average = 288 people.
FSH 7409.11 Water Consumption 20-30 gpd per person (Camping w/flush toilets)
Average Daily Water Demand
20gpd x 288 people =5,760 gpd
Average Daily Flow
5,760 gpd / 24 hours per day / 60 minutes per hour = 4 gpm
Peak Daily Flow
4 gpm x 5 (peak factor) = 20 gpm
E. Pump Hydraulic Calculations. Field Verify Elevations along with Well Log to draw down pumping level and distance to well. Complete Total Dynamic Head (TDH) with Pump submittal.
Partial Data:
Static Head =
161 feet elevation difference. Top of storage tank inlet to top of well (surface elevation near well).
Dynamic Head
4,527 feet 3-inch PVC pipe from water system building to storage tank.
Preliminary Pump Selection: Top of storage tank inlet - surface elevation near well = 161 feet. Allows for 139 feet of additional TDH (field verify measurements) for selected 20 gpm 300 TDH pump.
1.05 REFERENCES
A. American Society for Testing and Materials (ASTM)
B. National Sanitation Foundation (NSF)
C. Oregon Administrative Rules (OAR)
D. Oregon Revised Statutes (ORS)
E. Uniform Plumbing Code (UPC)
F. Federal Highways FP-14
G. Project Specifications (CSI format)
1.06 submittals
A. Work Schedule
1. Submit a proposed work schedule detailing the work in sufficient detail to show the approximate days that significant work items (i.e. mobilization, site preparation, drilling, testing etc.) for each portion of the project will be conducted.
2. The Contractor shall allow enough time for review and approval of the schedule at least 7 days in advance of schedule dates (unless otherwise approved) to give Forest Service personnel time to prepare for partial closures and other disruptions.
B. Pump and Controls
1. Submit manufacturer data sheets of selected pump model and controls to the CO. Include electrical schematic of existing wiring to pump controls, power supply connection, float wiring connection, along with associated new work, selected pump model c...
C. Product Information
1. Submit manufacturer's product information and installation recommendations for the materials and equipment proposed for use in this Contract.
2. Submit to the Contracting Officer two (2) sets of product data/catalog cut sheets in hard copy, or submit a single electronic (pdf) copy of clean, easy to read product sheets. Product submittals shall include the material data for the product and ...
3. Allow three (3) working days for Government review of submittals. If resubmittals are necessary, allow three (3) working days for review of the resubmittals, and so on.
4. Obtain written approval for the above submittals prior to construction, assembly, and delivery.
5. Furnish complete material submittals where possible. Partial submittals will be considered only to allow timely ordering of material.
6. Submittals shall have sufficient detail to determine if ratings, characteristics, and physical construction are equivalent to those specified.
7. Where manufacturer's catalog sheets are used, indicate the specific items to be supplied in ink either by arrow, encircled on the sheet, or the inapplicable portion blocked out. List manufacturer's name, contract, section and drawing sheet referen...
8. Submittals shall show any changes to be made resulting from proposed substitution of equipment or material for those that are specified.
D. Laboratory Bacteriological Test
1. Submit 1 copy of Laboratory Bacteriological Test results to the CO within 15 days of completion and acceptance of construction.
E. Operation and Maintenance Manual / As-Builts
1. Submit to the Contracting Officer one (1) bound set (to remain at water treatment building) of installed product data/catalog cut sheets, manufacturer warranties, as-built plans and details, with operation instructions, troubleshooting guide and sy...
1.07 Protection of existing facilities
A. The Contractor shall be responsible for locating and protecting existing structures, trees, and utilities (including underground) that are not designated for removal during construction operations. In the event of damage to existing structures, tr...
B. Fire Restrictions. Check (daily) current fire danger level with the USFS Middle Fork Ranger Station. Comply with any work activities restrictions and provide firefighting tools and equipment (as required).
C. Contractor shall be given a key(s) for water treatment building and any project site entrance gate(s) during construction period. Key(s) shall be returned upon completion of project. Gates shall remain locked when contactor is not present.
D. Vehicles shall remain on roadways or approved otherwise by CO. Any operation that will result in soil disturbance that can contribute to the introduction and spread of invasive plants shall be mitigated. Mitigations (Executive Order 13112) to redu...
1. Reduce ground disturbance to the minimum necessary to complete project.
2. All heavy equipment (excluding passenger vehicles) shall be clean and free of soil, vegetative matter, or other debris that may contain or hold weed seeds prior to entering National Forest System lands (WO-B/BT 6.36). Coordinate equipment inspectio...
1.08 QUALITY ASSURANCE
A. Provide and install all materials in accordance with the product manufacturer’s recommendations; Federal, State, and local building codes; and industry standards.
1.09 safety
A. All work shall be done in accordance with Occupational Safety and Health Act (OSHA) regulations, and all Oregon OSHA.
1.10 WARrANTy
A. Contractor shall be responsible for assembling all applicable warranty information and delivering to the Contracting Officer prior to final payment.
1.11 DRAWINGS
A. Refer to the following drawings for construction plans and details.
2. Part 2 – PRODUCTS (NOT USED)
3. Part 3 – EXECUTION (NOT USED)
4. PART 4 - MEASUREMENT AND PAYMENT